Taiwan’s offshore wind R3.3: the NT$30 billion pledge that won full points also decides a licence year
In Taiwan’s R3.3 offshore wind round, NT$30 billion of local procurement per 500 MW won the full 10 points and, delivered with the plan and the farm completed by its deadline, earns a 12-month licence extension. Spending less earns none of those months; an unremedied shortfall costs 20% of the gap, claimable beyond the security.
ListingMinds · Published and updated · Sources verified
Geography: Taiwan · Procurement rounds covered: Taiwan offshore wind zonal phase 3 (R3.3), closed
On this page
In Taiwan’s third phase of zonal offshore wind development, R3.3, the local-procurement figure that won an applicant all 10 local-benefit points, NT$30 billion per 500 MW, is also the figure its final contract template uses to grant, or withhold, a year on its electricity licence (電業執照). The points went to a commitment of NT$30 billion of local procurement and investment (在地採購及投資金額) per 500 MW applied for, to be delivered before completion and grid connection; NT$20 billion earned 5. The template grants the 12 months, on the ministry’s audit, to a developer that performs the commitments in its plan, completes by the deadline in its allocation notice and has spent NT$30 billion per 500 MW of the capacity allocated. A shortfall not made up by the ministry’s deadline costs a punitive penalty (懲罰性違約金) of 20% of the gap, and the ministry can claim penalties beyond the performance security (履約保證金).1, 3, 4
For a pledge of exactly NT$30 billion per 500 MW, the reward and the penalty turn on the same figure: deliver all of it, with the rest of the plan and by the deadline, and the licence runs a year longer; end the audit short of it and that year is gone, while any gap not made up by the ministry’s deadline is charged at 20%. The size of the pledge was a financial position, taken at application and settled years later on audited figures.
R3.3 closed for applications at 17:00 on , and as of the ministry’s Energy Administration had published no allocation result.2, 6, 7
What the pledge was worth in the review
The performance-capability review gave 35 points for developer track record, 30 for developer financial capability and 35 for project execution capability, the last made up of execution progress 15, ESG planning 15 and energy resilience 5. Local benefits carried 10 of the 15 ESG points, environmental sustainability 3 and corporate social responsibility 2. An application needed a total of 70 points or more to qualify. Qualified applications were then ranked by total score, and capacity was allocated in that order, first to the first-ranked application, then to the second, and so on. Points above the qualifying line therefore bought a place in the queue for capacity.1
Each applicant could file one application, for between 300,000 kW and 1,000,000 kW. Because the pledge was judged per 500 MW, a larger application needed a proportionally larger commitment for the same points. For local suppliers, that makes the pledge local procurement and investment the developer must deliver before its farm is completed and connected. Energy resilience had a pledge of its own, scaled the same way: NT$1.6 billion invested within five years after completion and grid connection scored 2 points and NT$2.5 billion scored 5.1
The contract amount and the reward both rest on the scored figure
A selected applicant does not sign up to its plan’s figure as such: under the allocation rules as amended on , the amount written into its administrative contract, the ESG local amount (ESG 在地金額), is the plan’s commitment multiplied by the wind farm’s obligation-capacity ratio, the capacity allocated divided by the capacity applied for. The reward scales actual spending back to 500 MW, multiplying it by 500 MW divided by the capacity allocated, and gives 12 months at NT$30 billion and one month more for each further NT$1 billion. We put each such further month, for an assumed 1,000 MW allocation, at another NT$2 billion of audited local spending. The ratios fit together: a developer that spends exactly its ESG local amount lands on the figure it was scored on, whatever share of its capacity it was allocated.1, 3
The reward is granted on the ministry’s audit, and only to a developer that performs the commitments in its plan and completes and connects its whole capacity by 31 December of the completion year in its allocation notice. In all it is capped at five years: early completion adds its days, and energy resilience adds a month at NT$2.5 billion and another at NT$3 billion, measured the same way. We read the template’s wording as putting more at stake than the local months: performing the plan is a condition of the whole reward, so a local shortfall could also cost the early-completion days and the resilience months.1, 3
The same contract lets a developer that has installed all its foundations, or connected 50% of its capacity, by that deadline finish in the following year, but the reward is tied to the original deadline, not to that extra year. Delay penalties are measured as shares of the security: 10% of the total allocated-capacity security for each month late on the establishment permit or the work permit, and 5% a month late on completion, rising to 10% a month from the seventh month. A farm that misses the original deadline loses the whole reward even if it qualifies for the extra year, and one late on completion pays the monthly penalty as well.1, 3
A shortfall is priced on the pledge, not on the security
The ESG local amount is reported on as it is spent and audited by the ministry after completion: within six months after financing is in place the developer files an implementation plan (落實計畫), then reports by the end of March and of September until completion, each report with a CPA’s special-audit attestation, and files its evidence for the ministry’s audit after completion. The actual spending a shortfall is measured against is the total the ministry recognises after that audit.3
If the ESG local amount is not delivered and the gap is not made up by the ministry’s deadline, the punitive penalty is 20% of the gap. In a serious case (情節重大), where execution reports are late or progress lags and is not put right within the next three reporting periods, the ministry may claim up to a further 10%, with the two capped together at 30% of the gap. The template sets out a route for a developer that cannot perform: with supporting evidence, it may ask the ministry to agree to change its ESG or energy-resilience obligations, and must then update its implementation plans.3, 4
An unremedied shortfall in the energy-resilience amount costs 20% of its own gap. The environmental and social measures are priced as shares of the security instead: each one not delivered and not remedied costs 10% of the total allocated-capacity security divided by the number of measures in its category, at least 2% of the security, with each category capped at 10% of the security. Only the two investment pledges are penalised on their own size, so only their penalties grow with the commitment.3
Nor does the security set a ceiling: the ministry may claim penalties beyond the allocated-capacity security, and the developer gives up its Civil Code defence that an excessive punitive penalty should be reduced (酌減之抗辯). The security itself is NT$2,000,000 per MW, at least 50% of it paid before a selected applicant applies to sign the administrative contract and the rest within one year of signing or one month after project financing is in place, whichever comes first.1, 3
Worked exampleA local pledge of exactly NT$30 billion per 500 MW on an assumed 1,000 MW allocation, delivered in full or NT$10 billion shortOn an assumed 1,000 MW allocated in full, the pledge is NT$60 billion. Delivered in full and by the deadline, it adds 12 months to the electricity licence. NT$10 billion short at the audit and not made up by the ministry’s deadline, it earns no local-benefit months and costs NT$2 billion at 20%, the same as the whole performance security for 1,000 MW, and up to NT$3 billion in a serious case. These are the penalties on one commitment only, before any delay, energy-resilience or environmental and social penalty.Show the calculationHide the calculation
| Pledge per 500 MW applied for, for the full 10 local-benefit points | 30 billion new Taiwan dollars1 |
|---|---|
| Actual spending per 500 MW allocated, for 12 months on the licence | 30 billion new Taiwan dollars1, 3 |
| Local-benefit penalty on the gap | 20 %3, 4 |
| Further penalty in a serious case, at most | 10 %3, 4 |
| Cap on the two together, as a share of the gap | 30 %3, 4 |
| Performance security | 2,000,000 new Taiwan dollars per MW1, 3 |
| Capacity applied for and allocated | 1,000 MW |
|---|---|
| Local procurement and investment delivered, second case | 50 billion new Taiwan dollars |
| Step | Calculation | Result |
|---|---|---|
| Pledge needed for 10 points at 1,000 MW | 30 billion × 1,000 MW ÷ 500 MW | 60 billion new Taiwan dollars |
| Case 1, delivered in full: spending per 500 MW allocated | 60 billion × 500 MW ÷ 1,000 MW | 30 billion new Taiwan dollars |
| Case 1: licence reward for local benefits | 30 billion reaches the 30 billion level | 12 months |
| Case 2, delivered short: spending per 500 MW allocated | 50 billion × 500 MW ÷ 1,000 MW | 25 billion new Taiwan dollars |
| Case 2: licence reward for local benefits | 25 billion is below the 30 billion level | 0 months |
| Case 2: gap between the ESG local amount and what was delivered | 60 billion − 50 billion | 10 billion new Taiwan dollars |
| Case 2, no serious case: penalty at 20% | 10 billion × 20% | 2 billion new Taiwan dollars |
| Case 2, serious case: further penalty of up to 10% | 10 billion × 10% | up to 1 billion new Taiwan dollars |
| Case 2, serious case: total, within the 30% cap | 2 billion + 1 billion; 10 billion × 30% | up to 3 billion new Taiwan dollars |
| Performance security for 1,000 MW | 1,000 MW × 2,000,000 | 2 billion new Taiwan dollars |
Result. On an assumed 1,000 MW allocated in full, the pledge is NT$60 billion. Delivered in full and by the deadline, it adds 12 months to the electricity licence. NT$10 billion short at the audit and not made up by the ministry’s deadline, it earns no local-benefit months and costs NT$2 billion at 20%, the same as the whole performance security for 1,000 MW, and up to NT$3 billion in a serious case. These are the penalties on one commitment only, before any delay, energy-resilience or environmental and social penalty.
The penalty grows with the pledge and the shortfall; the security does not.
Where R3.3 stands
The allocation rules set the phase at 3,600,000 kW “as a principle” (為原則), for completion and grid connection in 2030 and 2031. Applications could be delivered by hand or by registered mail, the postmark counting.1, 2
By the close, the ministry reported in-person applications from 2 development teams for 2 wind farms; applications by registered post also count. The Energy Administration said factors including developers’ global investment plans and the selection timetable not fitting together had indirectly affected willingness to take part. For the applicants, their lenders and their local suppliers, the pledge was fixed in the application: an allocation would scale it, and a change would need the ministry’s agreement. As of , the Energy Administration had published no allocation result: its renewable energy laws and notices page, where the phase 1 and phase 2 results are listed, shows none for phase 3, and none of its news releases after concerns the round. Its release of , the last on the round, said it planned to complete the selection and publish the allocation by the end of 2026.5, 6, 7
Sources (7)
- 1
Ministry of Economic Affairs (經濟部), Energy Administration: offshore wind zonal development capacity allocation rules (離岸風力發電區塊開發場址容量分配作業要點), as amended · Tier 1 · official · Verified
Where in the document
The amended rules (修正規定) attached to the ministry’s announcement of ; point 20 applies this text to phase 3 (phases 1 and 2 use earlier texts). Pages are PDF pages (30 in all, no printed numbers). Point 3(11), the floor price, where 新臺幣 is first named (p. 2); point 4(1)(3) (p. 2); point 5, opening (p. 3) and item (5) (p. 4); point 8 (p. 5); point 10 (p. 6); point 13, paragraph 1 (p. 7) and paragraph 3 (p. 8); point 15, paragraph 5, the contract commitment as the plan’s commitment times allocated ÷ applied capacity (p. 10), and paragraph 6 (p. 10); point 16, paragraphs 1 and 3 (p. 11) and paragraphs 5 and 6 (pp. 11–12); point 18 (pp. 12–13); point 20 (p. 13); Annex 7, the review items (pp. 26–27), ESG planning and energy resilience (p. 27); Annex 8 (p. 29). Later versions checked: the ministry’s list of renewable energy laws and notices, read on , shows no later amendment for phase 3; the ministry’s law database refused a plain request. No clarifications or questions and answers for phase 3 were found on the ministry’s pages read. Point 3(5) and 3(6), the obligation-capacity and allocated-capacity ratios (p. 1).
- 2
Ministry of Economic Affairs (經濟部): notice of the phase 3 application period, 經能字第11558000840號, (Energy Administration, legal notices) · Tier 1 · official · Verified
Where in the document
The notice as shown on the page, section (公告事項, announcements), item 1 (the period, from 上午9時 on 1 April to 下午5時 on 30 September, ROC year 115) and item 2 with its sub-item (2) (by hand or registered mail, the postmark counting). The file linked from the page, 經濟部公告 經能字第11558000840號 (signed notice, file 13835), is a scan read as images and has the same text. No extension or change of the period is listed on the ministry’s renewable energy notices page, read on .
- 3
Ministry of Economic Affairs (經濟部): allocated-capacity contract template for phase 3 (離岸風力發電區塊開發獲配容量契約書, 契約範本), announced · Tier 1 · official · Verified
Where in the document
Attachment 1 of the ministry’s announcement of ; no date is printed on the document. Pages: PDF page first, printed page after it (the cover has no number). Art. 1(3), the Chinese text controls (PDF pp. 5–6, printed pp. 4–5); Art. 4 (PDF p. 7, printed p. 6); Art. 6(1)–(3) (PDF p. 9, printed p. 8); Art. 11(1) (PDF p. 11, printed p. 10); Art. 11(7)–(8) (PDF pp. 12–13, printed pp. 11–12); Art. 14(1)–(3) (PDF pp. 16–17, printed pp. 15–16); Art. 16(2)–(3) (PDF pp. 18–19, printed pp. 17–18); Art. 18 (PDF pp. 19–20, printed pp. 18–19); annex point 1 (壹), item 1(1), the ESG local amount as the plan’s commitment times allocated ÷ applied capacity (PDF p. 24, printed p. 23); annex point 3 (參), item 1(1)1–3 (PDF pp. 25–26, printed pp. 24–25) and item 2(2) (PDF p. 28, printed p. 27); annex point 4 (肆), items 1(1) to 1(5) and item 2 (PDF pp. 29–31, printed pp. 28–30). Documents beside it checked: Expansion-capacity contract template (擴充容量契約書), attachment 2 of the same announcement, with the same security, delay and penalty structure and completion by ; Earlier version of the allocated-capacity contract template (file 29165), which this template replaces: the ESG penalties moved from its Art. 15 to annex point 4 (Art. 15 now covers other breaches), the local-benefit penalty changed from a flat 30% of the gap to 20% plus up to 10% in a serious case with a 30% cap, the one-year completion flexibility no longer needs the ministry’s consent, and Art. 11 adds the cap and period of the cross-security for expansion capacity and a top-up duty. Art. 2(4)–(5), the obligation-capacity and allocated-capacity ratios (PDF p. 6, printed p. 5); annex point 2 (貳), items 1 and 2, changing the ESG and energy-resilience obligations with the ministry's agreement (PDF p. 25, printed p. 24).
- 4
Ministry of Economic Affairs (經濟部): expansion-capacity contract template for phase 3 (離岸風力發電區塊開發擴充容量契約書, 契約範本), announced · Tier 1 · official · Verified
Where in the document
Attachment 2 of the ministry’s announcement of ; no date is printed on the document. Pages: PDF page first, printed page after it. Annex point 4 (肆), item 1(1)1–3 and item 1(2) (PDF p. 27, printed p. 26): 20% of the gap, up to a further 10% in a serious case, at most 30% together, as in the allocated-capacity template; item 2 (PDF pp. 27–28, printed pp. 26–27): energy resilience, 20% of its gap. Also read: Art. 6(3), completion by 31 December of ROC year 120 (PDF p. 9, printed p. 8); Art. 11(1) and 11(5) (PDF pp. 11–12, printed pp. 10–11).
- 5
Ministry of Economic Affairs (經濟部), Energy Administration: news release 「離岸風電區塊開發第三期截止收件 共2件申請案參與選商」 · Tier 1 · official · Verified
Where in the document
A web page (extract stored, T10-D30). Paragraph 1: the count at the close (2 development teams, 2 wind farms, in person) and the planned completion years (2030 to 2031); paragraph 2: registered post also accepted, review after all filings are collected, selection and allocation result by the end of 2026, and the Energy Administration's explanation of the turnout (開發商全球投資佈局及選商時程規劃未能配合等因素,間接影響參與遴選意願).
- 6
Ministry of Economic Affairs (經濟部), Energy Administration: renewable energy laws and notices (能源法規, 法令規章, 再生能源), as read on · Tier 1 · official · Verified
Where in the document
A list page, the result address of R-024. Section 風力發電: the zonal development entries, from the allocation rules (離岸風力發電區塊開發場址容量分配作業要點, linked to the ministry’s law database, GL001196, and to a ZIP of an earlier text dated 2025-04-29) to 公告離岸風力發電區塊開發場址容量分配作業之第三期受理申請時間 (S-163); the phase 1 and phase 2 results listed as 公告「離岸風力發電區塊開發第一期容量分配結果」 and 公告「離岸風力發電區塊開發第二期容量分配結果」; no phase 3 result. Page footer: 更新日期:115-10-19.
- 7
Ministry of Economic Affairs (經濟部), Energy Administration: news releases (新聞), list page, as read on · Tier 1 · official · Verified
Where in the document
A list page, first page (106 entries in all, newest first): releases dated 115-09-23 to 115-10-18. The only release on zonal offshore wind among them is 離岸風電區塊開發第三期截止收件 共2件申請案參與選商 (115-09-30, S-185); none after it concerns R3.3.
ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work
How to cite
ListingMinds, “Taiwan’s offshore wind R3.3: the NT$30 billion pledge that won full points also decides a licence year”, . https://www.listingminds.com/energy/field-notes/taiwan-offshore-wind-r3-3-local-commitments