Grid and T&D · Sector guide
How grid and transmission equipment is procured: the supplier field narrows before the project
Europe’s transmission buyers increasingly turn to long-term frameworks, and some to qualification systems: either way, who may compete, and under a framework on what terms, is settled before the project contract. A place there is a chance to compete for the work, not the work itself.
ListingMinds · Published · Updated and sources verified
Markets and rounds covered: United Kingdom, Netherlands, Germany, Denmark, Zambia, European Union; 1 procurement round, closed
On this page
In its report of , the IEA found buyers of transmission equipment competing for limited production slots, in many cases with only one supplier available, and turning increasingly to long-term framework agreements, especially in Europe; in the United States, contracts are generally still project based. For a supplier in Europe, that moves much of the contest out of the project tender and into earlier steps.1
Under the EU utilities directive, the contracts a qualification system covers are awarded among the suppliers already qualified, while a framework agreement sets the terms, in particular on price, for contracts awarded during its term. Admission to the list decides who may compete for the contracts it covers; the framework award decides on what terms. Neither is the work itself: a place brings the chance to compete for later contracts, not the contracts themselves.2
Admission sets the bar before any price is asked
A qualification system is a standing list: under the directive, suppliers must be able to apply to join it at any time, and the entity running it must give an applicant its decision within six months.2 TenneT’s qualification system for platforms and HVDC for its Dutch 2 GW projects, published on , asked for an HVDC type test certificate or report with one reference project, topside and jacket reference projects with the fabrication yard, and environmental, quality and safety management certificates.3 Energinet and 50Hertz’s system for HVDC converter substations, as published on , asked for an equity ratio of at least 20% and at least two references for HVDC point-to-point VSC converters of at least 320 kV, each in commercial operation for at least 12 months.4
These are conditions a supplier meets or fails before any price is asked for: without the references, it cannot compete for the contracts the system covers, however low it would bid. Nor can such a reference be produced for the occasion: the converter must already have run in commercial operation for the period the notice sets.
The right to apply at any time does not mean a list is still taking suppliers in. In a notice of , TenneT said a tender under its qualification system for 2 GW HVDC stations had finished in 2023 and that, with no new tender foreseen, it was not planning to review new requests to qualify. Before preparing an application, check the system’s latest notice for whether it is still reviewing requests.5
A framework sets the terms before the work is called off
In its report of , the IEA found that supply frameworks for transmission equipment typically run up to five years, with fixed and variable price components, the variable part commonly indexed to inflation or raw material prices. For a supplier, the framework award is where it commits to a price for work not yet called off, and the indexation terms decide how much of a later rise in costs that price absorbs.1
National Grid’s contract notice for its HVDC converter framework, published on , put the framework’s estimated total value at GBP 24.6 billion excluding VAT. On , National Grid awarded HVDC supply chain frameworks to six cable suppliers, one of them a consortium, for about GBP 21.3 billion, and to four converter suppliers for about GBP 24.6 billion, each for five years with a possible extension of three.6, 7, 8 On , it awarded civil works for about GBP 12 billion, the third and final stage.9 These are framework values, the converter figure an estimate in the notice itself, not orders: the work under them is awarded as call-offs, contracts placed under the framework during its term.
The early projects show how closely the framework and project contests can run. The converter notice named Eastern Green Link 4 and Sealink as early projects whose call-offs would run in parallel with the procurement of the framework itself, given their criticality and the timeframe set by Ofgem’s Accelerated Strategic Transmission Investment (ASTI) framework. A place on the framework would be a condition for the award of any call-off contract, and suppliers would have to take part in the early call-offs before that place was confirmed; for those projects, National Grid also reserved its rights to use different procurement routes. For those early projects, a supplier would bid for the work before knowing whether it could be awarded it at all.6
TenneT’s 2 GW cables partnership tender awarded framework agreements in five lots, concluded on , to NKT, Nexans and a group of Jan De Nul, Denys and LS Cable & System; the notice publishes no values.10 On , TenneT signed multi-year framework agreements with Allseas and Heerema for at least 28 transport and installation slots until 2031, not linked to specific projects, and said all major framework agreements of its 2GW Program had been awarded. Slots booked without a project attached reserve capacity before the work is defined.11
Why buyers commit early
Large equipment takes years to arrive: the IEA, in a survey of industry players in 2024 (its report does not give the number of respondents), found that large power transformers can take up to four years to obtain, and the same report notes that buyers in Europe and the United States are booking manufacturing slots rather than buying material for delivery.1 Ofgem’s decision of on an Advanced Procurement Mechanism brings forward about GBP 4 billion of the transmission owners’ allowances, money that would otherwise be approved later as projects reach funding milestones, so that they can book capacity for equipment and services years before it is needed. It notes that, in some instances, supply chain capacity is already booked up several years out.12
Scarce factory capacity is one reason these buyers commit early, not the only one: National Grid’s notice tied the planned parallel call-offs to the projects’ criticality and to the timeframe of the ASTI framework.
Our field note on transformer lead times and grid tenders follows those lead times from the framework into the contract, where a long wait becomes a supplier’s risk.
Which law sets the limits
Under the EU utilities directive, a framework agreement may not run for more than eight years, save in exceptional cases duly justified. The directive also draws a line by origin: it gives suppliers from countries covered by the WTO Government Procurement Agreement or the EU’s other agreements treatment no less favourable than the EU’s own suppliers receive, but a supply tender may be rejected where products from third countries without such an agreement make up more than 50% of the total value of its products. For an equipment maker whose products come mostly from such countries, that is a ground for rejection that no price can offset.2
Like the directive, the UK’s Procurement Act 2023 limits a utilities framework to eight years, unless the buyer considers that the nature of the goods, services or works requires a longer term and gives its reasons in the notice; the limit does not apply to a framework awarded by a private utility.2, 13 The Cabinet Office’s guidance says the Act replaces qualification systems, and dynamic purchasing systems, with the dynamic market: a list of qualified suppliers eligible to take part in future procurements.14
The Act does not apply to procurement by devolved Scottish authorities, except in cases it sets out. A public undertaking or private utility that operates only in, or in relation to, Scotland is treated as one of those authorities unless all of its activities relate to reserved matters. Scotland has its own Utilities Contracts (Scotland) Regulations 2016, which this guide does not cover.15, 16, 17 Under the Scotland Act 1998, the generation, transmission, distribution and supply of electricity are reserved matters.18 A Scotland-only electricity utility whose activities all fall within that reservation is therefore not a devolved Scottish authority, and is not excluded from the Act on that ground.
The Utilities Contracts Regulations 2016, which do not extend to Scotland, still govern a utility’s procurement where, before , it had concluded the framework agreement or submitted a contract notice or a notice on the existence of a qualification system, among other cases the transitional rules list. A qualification system run under those Regulations expires, if it has not already, at the end of , and its period of validity may not be changed after . A supplier on such a list keeps that place no longer than that; a utility’s new lists under the Act are dynamic markets. National Grid’s converter framework, advertised on , therefore falls under the 2016 Regulations, not the Act.19, 20
When the project is tendered on its own
Not every grid buyer works through a list or a framework. ZESCO’s Request for Bids for Package 4, the Nakonde Stepdown and Kasama 330 kV substations in Zambia, was issued on , and after amendment bids were due on . It was an international Request for Bids under the World Bank’s procurement regulations, open to all eligible bidders and without prequalification. Each bid still had to clear a qualification bar: an average annual energy-sector turnover of at least USD 42 Million over the last three years, and similar experience on contracts for a greenfield substation of at least 330 kV in the last ten years.21, 22 To compare bids, and for that purpose only, the evaluation added capitalised losses to each bid’s price: transformer no-load losses at USD 12,000/kW and load losses at USD 7,000/kW, and reactor total losses at USD 12,000/kW. After factory tests, losses above the guarantee could bring penalties per kW, and a transformer or reactor more than 10% over its guaranteed losses could be rejected.21
Our field note on the Nakonde and Kasama substation tender reads those loss rules, the scoring and the contract in full. There, no list or framework stood between a supplier and the bid, and the bid carried the whole commitment: a lower guaranteed loss improved the evaluated cost, and losses above the guarantee could bring penalties.
Reference
| Route | What it is | Who may compete for its contracts | Examples in this guide |
|---|---|---|---|
| Qualification system | A standing list of qualified suppliers; under the EU utilities directive, suppliers may apply at any time and get a decision within six months | Suppliers already qualified | TenneT’s systems for its 2 GW programme (notices of 2021 and 2024); Energinet and 50Hertz’s for converter substations (2023) |
| Framework agreement | Sets the terms, in particular on price, for contracts awarded during its term: up to eight years under the EU utilities directive and the Procurement Act 2023, with each rule’s exceptions | Suppliers party to the framework | National Grid’s HVDC frameworks (awarded 2025); TenneT’s 2 GW cable frameworks and installation slots (2023) |
| Call-off | A contract awarded under a framework agreement | The framework’s suppliers; National Grid’s notice made a framework place a condition of any call-off award | Eastern Green Link 4 and Sealink, National Grid’s early converter projects, whose call-offs were to run in parallel with its framework procurement (notice of 2023) |
| Single-project tender | One contract tendered on its own, with the qualification requirements judged inside each bid | Any eligible bidder, without prequalification | ZESCO’s Package 4, the Nakonde Stepdown and Kasama 330 kV substations, Zambia (2026) |
How grid equipment and works are bought
- Qualification system
- What it isA standing list of qualified suppliers; under the EU utilities directive, suppliers may apply at any time and get a decision within six months
- Who may compete for its contractsSuppliers already qualified
- Examples in this guideTenneT’s systems for its 2 GW programme (notices of 2021 and 2024); Energinet and 50Hertz’s for converter substations (2023)
- Framework agreement
- What it isSets the terms, in particular on price, for contracts awarded during its term: up to eight years under the EU utilities directive and the Procurement Act 2023, with each rule’s exceptions
- Who may compete for its contractsSuppliers party to the framework
- Examples in this guideNational Grid’s HVDC frameworks (awarded 2025); TenneT’s 2 GW cable frameworks and installation slots (2023)
- Call-off
- What it isA contract awarded under a framework agreement
- Who may compete for its contractsThe framework’s suppliers; National Grid’s notice made a framework place a condition of any call-off award
- Examples in this guideEastern Green Link 4 and Sealink, National Grid’s early converter projects, whose call-offs were to run in parallel with its framework procurement (notice of 2023)
- Single-project tender
- What it isOne contract tendered on its own, with the qualification requirements judged inside each bid
- Who may compete for its contractsAny eligible bidder, without prequalification
- Examples in this guideZESCO’s Package 4, the Nakonde Stepdown and Kasama 330 kV substations, Zambia (2026)
Source: the procurement law and the buyers’ notices and releases cited below.2, 3, 4, 5, 6, 7, 8, 10, 11, 13, 21
Terms not explained above
- HVDC: high-voltage direct current.
- VSC: voltage source converter.
- Lot: a part of a procurement awarded on its own, often by project or by equipment.
- Lead time: the time from order to delivery of a piece of equipment.
Where the notices are published
The EU notices cited here are on Tenders Electronic Daily (TED), which also carries notices on the existence of a qualification system; the UK ones are on Find a Tender.
Sources (22)
- 1
International Energy Agency (IEA): Building the Future Transmission Grid · Tier 1 · official · Verified
Where in the document
Abstract (p. 3); executive summary (p. 8); chapter 2 (pp. 28 and 29). Later version checked: the current file differs from the copy of by one acknowledgement name only.
- 2
EUR-Lex: Directive 2014/25/EU on procurement by entities in the water, energy, transport and postal services sectors, consolidated text of · Tier 1 · official · Verified
Where in the document
Article 43; article 51(1); article 77(1) and 77(5); article 85(1) and 85(2). The consolidated text of has the same wording as the original 2014 text for these articles.
- 3
TED: TenneT TSO B.V., qualification system for platforms and HVDC, Dutch 2 GW projects, 2021/S 067-173826 · Tier 1 · official · Verified
Where in the document
Section III.1.9, qualification for the system (HVDC type test certificate or report and one reference project; topside and jacket reference projects and the fabrication yard; management certificates). Later notice checked: notice 2022/S 123-350998 replaces the indefinite duration with an end date of .
- 4
TED: Energinet and 50Hertz, supplier qualification system for HVDC converter substations, 2023/S 186-580538 · Tier 1 · official · Verified
Where in the document
Section III.1.9, qualification for the system (economic and financial standing: equity ratio of at least 20%; technical ability: two or more references, multi-level HVDC point-to-point VSC converters of at least 320 kV, each in commercial operation for at least 12 months).
- 5
TED: TenneT, qualification system for 2 GW HVDC stations (converter systems and platforms), 41764-2024 · Tier 1 · official · Verified
Where in the document
Section 2.1, description (the tender under the system finished; no new tender foreseen; no review of new requests); section 5.1.3 (duration unlimited); section 2.1.4 (Directive 2014/25/EU).
- 6
Find a Tender: National Grid UK Limited, contract notice for the HVDC converter framework, 2023/S 000-035470 · Tier 1 · official · Verified
Where in the document
Notice header (“F05: Contract notice – utilities”, published ); section II.1.5 (estimated total value, £24,600,000,000 excluding VAT); section II.2.4 (the early projects, Eastern Green Link 4 and Sealink: call-offs to be run in parallel with the framework procurement within the ASTI timeframe; a framework place a condition of any call-off award; other procurement routes reserved); sections II.2.7 and II.2.11 (96 months: an expected 60, with an option of up to 36). Later notice checked: award notice 2025/S 000-009131 (contracts concluded on 24 and , no values published).
- 7
National Grid: press release, HVDC supply chain framework contracts awarded · Tier 1 · official · Verified
Where in the document
The release: two parts of the framework, six cable suppliers (about GBP 21.3 billion) and four converter suppliers (about GBP 24.6 billion), five years with a possible three; paragraph naming the early projects.
- 8
Find a Tender: National Grid UK Limited, award notice for the HVDC cable framework, 2025/S 000-010596 · Tier 1 · official · Verified
Where in the document
Section V (the award, concluded on ). Correction checked: notice 2025/S 000-061176 adds the other cable suppliers, “7 suppliers in total” counting the consortium members separately.
- 9
National Grid: press release, HVDC civil works agreements awarded · Tier 1 · official · Verified
Where in the document
The release: “third and final stage of our £59bn supply chain framework awards”; paragraphs on Lot 1 (converter civils, about GBP 9.07 billion) and Lot 2 (onshore cable civils, an estimated GBP 3.7 billion).
- 10
TED: TenneT, award notice for the 2 GW cables partnership agreement tender, 2023/S 118-369939 · Tier 1 · official · Verified
Where in the document
Section II.1.4 (framework agreements by lot); section V (lots 1 to 5 awarded, concluded on ; no values published). No correction or modification found for this notice.
- 11
TenneT: release, transport and installation slots for 2GW offshore platforms awarded to Allseas and Heerema · Tier 1 · official · Verified
Where in the document
The release: first paragraph (at least twenty-eight slots, running to the year 2031); “In short” (all major framework agreements of the 2GW Program awarded); the paragraph on the vessels (slots not linked to specific projects). The page shows it was last updated on ; the text read is that version.
- 12
Ofgem: Advanced Procurement Mechanism, decision document and impact assessment · Tier 1 · official · Verified
Where in the document
P. 1 (publication date); p. 4 (“brings forward c.£4bn in allowances … booking capacity for equipment and services years in advance of when it is needed”); p. 9, paragraph 2.5 (“in some instances supply chain capacity is already booked up several years out”). Later document checked: the licence decision letter of puts the mechanism into the licence (special condition 3.43) and changes none of these points.
- 13
Procurement Act 2023, section 47 (frameworks: maximum term), legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Section 47(1)(a), 47(2), 47(3), 47(4)(b), 47(5)(a) and 47(5)(b); in force from . Re-read on .
- 14
Cabinet Office: Guidance: Dynamic Markets (HTML), Procurement Act 2023 guidance, updated · Tier 1 · official · Verified
Where in the document
Paragraph 1 (a list of qualified suppliers eligible to participate in future procurements) and paragraph 7 (the Act replaces dynamic purchasing systems and qualification systems with the dynamic market). Re-read on ; the page still gives its last update as .
- 15
Procurement Act 2023, section 2 (contracting authorities), legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Section 2(1) (contracting authority, other than an excluded authority); 2(5)(a) (a devolved Scottish authority is an excluded authority, except where it carries out procurement falling within section 115A); 2(6) to 2(8) (devolved Scottish authority; a public undertaking or private utility operating only in or as regards Scotland). In force from ; section 2(5)(a)’s exception inserted from the same date.
- 16
Procurement Act 2023, section 115A (application of the Act where a devolved Scottish authority carries out procurement under a reserved procurement arrangement etc.), legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Section 115A(1) to (4), inserted from : the Act applies, in whole or as Schedule 9A sets out, where a devolved Scottish authority procures under a reserved, devolved Welsh or transferred Northern Ireland procurement arrangement, jointly, through a centralised procurement authority, or under a framework or dynamic market.
- 17
Procurement Act 2023, section 115 (powers relating to procurement arrangements), legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Section 115(4): “Scottish procurement legislation” includes the Utilities Contracts (Scotland) Regulations 2016 (S.S.I. 2016/49).
- 18
Scotland Act 1998, Schedule 5 (reserved matters), legislation.gov.uk, latest revised text · Tier 1 · official · Verified
Where in the document
Part II, Head D (Energy): Section D1, “Generation, transmission, distribution and supply of electricity”; Section D2 (oil and gas), item (j), “the conveyance, shipping and supply of gas through pipes”, with the exceptions “The manufacture of gas” and “The conveyance, shipping and supply of gas other than through pipes”.
- 19
The Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 (SI 2024/716), regulation 8, legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Regulation 8, paragraphs (1), (3)(a) and (d) and (4)(a) and (c): the 2016 Regulations continue to apply, and the Act does not, where before a framework agreement was concluded or a contract notice or a notice on the existence of a qualification system was submitted; such a qualification system’s period of validity may not be changed after and expires at the end of . The revised text read on includes the amendments of (SI 2025/1337) and (SI 2026/297).
- 20
The Utilities Contracts Regulations 2016 (SI 2016/274), regulation 1 (citation, commencement and extent), as made, legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Regulation 1, paragraph (5): “These Regulations do not extend to Scotland.”
- 21
ZESCO Limited: Package 4, Nakonde Stepdown and Kasama 330 kV substations (RFB ZM-ZESCO-495237-CW-RFB), Update 4 archive: Request for Bids REV05 of , Addendum No. 5 and its notice, Clarifications No. 2 · Tier 1 · official · Verified
Where in the document
The controlling version, RfB REV05 (PDF page first, printed page after it): cover (PDF p. 1); Specific Procurement Notice (PDF p. 3, “Issued on: ”), ¶3 and ¶7 (PDF pp. 3–4); BDS ITB 4.11 (PDF p. 53, printed p. 43); Section III §3(b), the capitalisation of losses for comparative evaluation only (PDF pp. 129–130, printed pp. 119–120); §3(c), Failure in Guarantees, and footnote 2 (PDF pp. 131–132, printed pp. 121–122). Addendum No. 5, item 6 (p. 5): bids due on . Amendments and clarifications checked, each with what it changed: Addendum No. 1 (deadline from to ); Addendum No. 2 (deadline to ); Addendum No. 3 (Guarantee Test window from 730 to 30 days, extended defects liability from 12 to 36 months, late-payment interest wording, “Air Insulated Substation” in the similar-contract test, ZESCO’s safety rules, technical changes, deadline to ); Clarifications (RFC 1–421), answered before Addendum No. 3; Addendum No. 4 (deadline to , no new date for clarification requests); Addendum No. 5 (exchange-rate date, type tests less than 8 years old in §7.5.1, Tunduma interface, technical and price schedule changes, deadline to ); Clarifications No. 2 (RFC 422–482).
- 22
ZESCO Limited: Package 4 (RFB ZM-ZESCO-495237-CW-RFB), Update 2 archive: Addendum No. 3 and its notice, Request for Bids REV03 of , Clarifications (RFC 1–421) · Tier 1 · official · Verified
Where in the document
Addendum No. 3: item 6 (p. 10, late-payment interest wording); item 11 (p. 17, PCC 27.10 from 12 to 36 months); item 13 (p. 18, “Air Insulated Substation”); item 14 (pp. 18–19, PCC 25.2.2 from 730 to 30 days). Its notice (p. 1, table): tender closing from to ; clarification close-out to . Item 12 of the addendum gives the earlier date as ; the notice gives , the date Addendum No. 2 had set. Clarifications (pp. 1–188): RFC 68 (p. 39); RFC 95 (p. 52); RFC 270 (p. 123); RFC 273 (pp. 124–125); RFC 274 (p. 125).