Grid and T&D · Field note
In Zambia’s Nakonde–Kasama tender, losses are priced into the bid and enforced at the factory test
ZESCO’s tender for work at two 330 kV substations added each bid’s guaranteed transformer and reactor losses, valued per kilowatt, to its price for comparison; its contract deducts penalties at the same rates for losses above the guarantee at factory tests. A guarantee had to be low enough to compete and safe enough to meet.
ListingMinds · Published · Updated and sources verified
Geography: Zambia · Procurement rounds covered: Zambia ZESCO RETRADE Package 4, closed
On this page
In ZESCO’s Package 4, a tender for work at two 330 kV substations, each bid’s guaranteed transformer and reactor losses were added to its price before the bids were compared: USD 12,000/kW for transformer no-load and reactor losses, USD 7,000/kW for transformer load losses. The contract terms brought the same rates back after the factory tests: a penalty per kilowatt found above the guarantee was to be deducted from the Contract Price, and a transformer or reactor more than 10% over its guaranteed losses could be rejected.1, 2
One figure thus worked on a bid at two moments: in the evaluation, a lower guaranteed loss meant a lower evaluated cost and a better cost score, and at the factory it became the line the measured losses had to stay under.
The package covered two equipped 330 kV line bays with line reactors at the existing Kasama substation and the new greenfield Nakonde Stepdown substation, about 18 km west of Nakonde Town, with 330 kV lines to Tunduma and Kasama and 330/(132)66/11 kV, 90 MVA transformers. The World Bank’s procurement plan for the project, revised on , put the package at an estimated US$26,052,525.18, describing it only as a new Nakonde 330/132/66 kV substation; the request for bids itself states no budget or contract value.1, 6 As of , ZESCO’s tender register showed no notice of evaluation or award for Package 4, whose listing gave a closing date of at 10:30, and the World Bank’s procurement notices for the project listed no contract award for it.7, 8
In the evaluation, a lower guarantee bought cost points
The losses were added for comparison only, and where a bidder offered transformers from more than one maker, the highest guaranteed losses were used. Bids came in two envelopes, technical and financial, and only substantially responsive bids with a technical score of at least 60% were to have their financial parts opened. Cost then carried half the score, measured against the lowest evaluated cost, and rated technical and non-price criteria the other half, measured against the highest technical score; the best-scoring qualified bid was the Most Advantageous Bid.1
Two bids show the trade-off.
Worked exampleTwo bids under Package 4’s scoring, at two costs for the cheaper bidBid A, the technical leader, wins when Bid B’s evaluated cost is 90% of A’s (95.00 points to 91.67) and loses when it is 80% (90.00 to 91.67). The scores are equal at 83.33% of A’s cost, the same share as B’s technical score is of A’s, 75 out of 90. Both bids pass the 60% technical mark. The costs are evaluated costs, after any capitalised losses, not quoted prices.Show the calculationHide the calculation
| Weight for cost (X) in Package 4 | 50 %1 |
|---|---|
| Weight for rated technical and non-price criteria | 50 %1 |
| Technical score needed to have the financial part opened | 60 %1 |
| Bid A technical score (the best) | 90 points |
|---|---|
| Bid B technical score | 75 points |
| Bid A evaluated cost | 100 index |
| Bid B evaluated cost, case 1 | 90 index |
| Bid B evaluated cost, case 2 | 80 index |
| Step | Calculation | Result |
|---|---|---|
| Case 1, Bid A: cost part | 90 ÷ 100 × 0.5 × 100 | 45.00 points |
| Case 1, Bid A: technical part | 90 ÷ 90 × (1 − 0.5) × 100 | 50.00 points |
| Case 1, Bid B: cost part | 90 ÷ 90 × 0.5 × 100 | 50.00 points |
| Case 1, Bid B: technical part | 75 ÷ 90 × (1 − 0.5) × 100 | 41.67 points |
| Case 1: Bid A and Bid B | 45.00 + 50.00; 50.00 + 41.67 | 95.00 and 91.67 points |
| Case 2, Bid A: cost part (Bid B now has the lowest cost, 80) | 80 ÷ 100 × 0.5 × 100 | 40.00 points |
| Case 2: Bid A and Bid B | 40.00 + 50.00; 50.00 + 41.67 | 90.00 and 91.67 points |
| Bid B’s cost at which the two scores are equal | 100 × 75 ÷ 90 | 83.33 index |
Result. Bid A, the technical leader, wins when Bid B’s evaluated cost is 90% of A’s (95.00 points to 91.67) and loses when it is 80% (90.00 to 91.67). The scores are equal at 83.33% of A’s cost, the same share as B’s technical score is of A’s, 75 out of 90. Both bids pass the 60% technical mark. The costs are evaluated costs, after any capitalised losses, not quoted prices.
With cost and technical merit weighted equally, a cheaper bid with a lower technical score beat the technical leader in a two-bid comparison only if its evaluated cost, as a share of the leader’s, was below its technical score as a share of the leader’s. That evaluated cost already included the capitalised losses, which is where the loss guarantee entered the score.1
At the factory, the same rates returned as penalties
After the factory tests, the functional-guarantee clauses set the evaluation’s figures as penalties, although a footnote to the evaluation criteria calls the penalty higher than the capitalisation value. The contract’s appendix says the penalties “shall be stated once only and shall be identical to the values below”, and deducts them “from the Contract Price”. Asked whether losses were counted twice, ZESCO pointed to the capitalisation for the evaluation and to the appendix for the penalties; no addendum or clarification in the documents read addresses the footnote. As printed, a kilowatt over the guarantee would cost the contractor the rate at which a guaranteed kilowatt had been priced into the comparison, not the higher penalty the footnote describes.1, 2
The trigger is worded differently for the two: the transformer penalties apply where losses exceed the guarantee “by more than the margins specified hereunder”, the reactor penalty where they exceed it “by not more than the margins”, each charged per full kilowatt above the guaranteed value, with 0.5 kW and above rounded up. The only loss margins the clauses list are those beyond which ZESCO could reject a unit, 10%, and the transformer specification calls the guaranteed losses maximum values that “shall not be exceeded”. Read literally, a transformer penalty would start only beyond the 10% at which ZESCO could also reject the unit, and would then count every kilowatt above the guarantee, while the specification says the guarantee is not to be exceeded at all; the reactor clause reads the other way round, and no addendum or clarification addresses the point.1
The reactor rate itself is printed two ways: the reactor data table in the technical specification gives 7000 USD/kW for the capitalisation of losses, against USD 12,000/kW for reactor losses in the evaluation criteria and in the specification’s own reactor formula, and 12,000 USD/kW for the reactor penalty. No addendum or clarification addresses the difference.1
The appendix limits the functional guarantees to the transformer and reactor loss and noise values the contractor guaranteed, caps its liquidated damages for missing them at 10% of the Contract price in total, and levies them separately from, and concurrently with, damages for delay. Delay damages ran at 0.5% a week, applied to the price, as quoted in the Price Schedule, of the part not completed on time, up to 10% of the Contract Value. Damages for missed loss and noise guarantees had, in other words, a ceiling of their own, beside the delay ceiling rather than inside it, and a unit more than 10% over its guaranteed losses could also be rejected.1
No prequalification, but the record had to be the bidder’s own
Access did not depend on a prior list: the request for bids was international, under the World Bank’s Procurement Regulations for IPF Borrowers, Seventh Edition, issued in , open to all eligible bidders, without prequalification and with no electronic bidding. Qualification was tested inside the evaluation instead: only substantially responsive bids from eligible and qualified bidders were to go on to the detailed technical evaluation. ZESCO was to judge qualification on the bidder’s own documents, without counting the qualifications of its subsidiaries, parent entities, affiliates or subcontractors, other than specialised subcontractors where permitted.1
The financial bar was an average annual energy-sector turnover of at least USD 42 million over the last three years and access to at least USD 7 million in financial resources other than advance payments, plus the cash flow for this contract and its current commitments. The experience bar was narrower: at least two contracts of at least USD 20 m each, or one of at least USD 40 m, in the last ten years, completed or at least 80% complete. Each had to be for an air-insulated substation with a new greenfield substation of at least 330 kV, two or more transformers of 330 kV or above and two or more line bays of 330 kV or above with line reactors, all “under one contract”, as ZESCO answered a bidder. Experience as contractor, joint-venture member, management contractor or subcontractor counted, and in a joint venture the members combined had to meet the requirement. A group whose substation and reactor-bay references sat in separate contracts, or in a parent company that was not itself the bidder or a joint-venture member, could not qualify on them.1, 2
The grid and transmission guide sets substation tenders like this one beside the frameworks and qualification systems through which transmission owners buy.
What the winner signs up to beyond the losses
The performance security was 10% of the total contract sum, as a bank guarantee within 28 days of the Letter of Acceptance. The particular conditions print its reduction clause twice, once saying the security “shall not be reduced” at Operational Acceptance and once that it “shall be reduced” to 10% of the value of the components under the extended defects liability. The bank-guarantee form in the contract forms says something else again, halving the guarantee at Operational Acceptance, though a footnote to the form says its text is to be revised where needed, among other things for an extended warranty obligation. The components under extended liability include the transformers and reactors: defects liability ran for 24 months from Operational Acceptance, and for 36 months for transformers, reactors, circuit breakers, disconnectors, instrument transformers, SAS and WAMPACs. Liability was capped at 1.1 times the contract price; asked to lower the multiplier to 1, ZESCO answered that the clause “shall not be revised”.1, 2
If the network in Tanzania, at Tunduma, or other connecting lines could not be energised when Nakonde was complete, successful loop-back tests by the contractor would let ZESCO issue the Operational Acceptance Certificate and make the completion payments, with no delay to payment and no liquidated damages for those lines, while the live tests across the link became a call-out service paid from a provisional sum. Taking over after that call-out still required the site acceptance and commissioning tests, including the protection tests across the link, SCADA and telecom availability, metering accuracy and earthing checks. The contractor still answered for telecom interoperability between Nakonde and Tunduma, with TANESCO’s contractors there coordinated by the utility project managers, and ZESCO told a bidder there would be some works at Tunduma substation.1, 2
What the addenda changed before bids closed
Package 4 was issued on with a bid deadline of ; after five addenda, bids were due on at 10:30 CAT, when their technical parts were to be opened in public at ZESCO’s headquarters in Lusaka.1, 2, 3, 4, 5
Addendum No. 3 cut the window for the Guarantee Test of the completed facilities from 730 days after Completion to 30 days, and added that passing it does not relieve the contractor of its obligations during the defects liability period. The same addendum raised the extended defects liability from 12 to 36 months, after a bidder had asked ZESCO to confirm 12. Addendum No. 5, after a bidder asked, fixed the date of the OANDA selling rate used to convert bid prices to US dollars at 28 days before the bid deadline; before, it could be any date from then to the expiry of bid validity. A bid priced on the documents as first issued would have assumed 12 months of extended defects liability on the transformers and reactors, not 36, and a Guarantee Test window of 730 days, not 30.1, 2, 3, 4
Where the result will show what the guarantees weighed
Before any award, every bidder was to receive a Notification of Intention to Award giving each bidder’s price as read out and as evaluated, its technical score, and the winner’s contract price and combined score. A standstill period of 10 business days then had to run, unless only one bid was submitted or the Bank recognised an emergency, and longer if a requested debriefing was delayed. Within 10 business days of the Letter of Acceptance, ZESCO was to publish a Contract Award Notice listing every bidder’s price as read out and as evaluated, the bids rejected and why, and the final contract price, on its website with free access if available, otherwise in a national newspaper or the official gazette. How the World Bank’s standstill and complaint rules compare with those of other development banks is set out in our field note on development-bank procurement rules.1
Every evaluated price in that notice includes the bidder’s capitalised losses, so, once the notice is published, the gap between a bid’s read-out and evaluated price will include what its loss guarantees added in the comparison.
Sources (8)
- 1
ZESCO Limited: Package 4, Nakonde Stepdown and Kasama 330 kV substations (RFB ZM-ZESCO-495237-CW-RFB), Update 4 archive: Request for Bids REV05 of , Addendum No. 5 and its notice, Clarifications No. 2 · Tier 1 · official · Verified
Where in the document
The controlling version, RfB REV05 of (PDF page first, printed page after it). Cover (PDF p. 1); Specific Procurement Notice ¶3, ¶4 and ¶7 (PDF pp. 3–4); Section I: ITB 30.2, 30.3, 31.1, 31.2, 31.4 and 33.1 (PDF pp. 40–41, printed pp. 32–33), ITB 41.1 and 42.1 (PDF p. 47, printed p. 39), ITB 44.2 and 44.3 (PDF pp. 48–49, printed pp. 40–41), ITB 45.2 (PDF p. 49, printed p. 41); BDS ITB 4.11 (PDF p. 53), 23.1 and 26.1 (PDF p. 60), 32.2 with the 60% minimum (PDF pp. 61–64), 36.2 and 39.1 (PDF p. 66). Section III: the preamble (PDF p. 67, printed p. 57); Table 6, factors 3.2 and 3.3 (PDF pp. 102–103); Table 7, factor 4.2(a) and footnote 9 (PDF pp. 104–105); §3(b) (PDF pp. 129–130); §3(c), footnote 2 and the rejection margins (PDF pp. 131–132); Table 11 (PDF pp. 133–134); §4, Combined Evaluation (PDF p. 135). Section VII: §1.3.1 and §1.3.2 (PDF p. 295); Table 9-1, IF-12 and IF-13 (PDF pp. 374–375); §12.12.2 (PDF p. 526, printed p. 476); Table 12-10, row “Capitalisation of losses” (PDF p. 557, printed p. 507); §12.13 reactor formula (PDF p. 559, printed p. 509); §12.20.3 (PDF p. 685). Section IX: PCC 13.3.1 to 13.3.3, the two PCC 13.3.3 entries side by side (PDF pp. 1011–1012); PCC 25.2.2, 26.2, 26.3, 27.2, 27.10 and 30.1(b) (PDF pp. 1012–1013). Section X: Appendix 8, sections 3, 4.1 and 4.2 (PDF pp. 1050–1052); Performance Security Form – Bank Guarantee (PDF pp. 1053–1054, printed pp. 497–498). Addendum No. 5, items 2, 3, 4 and 6 (pp. 2–5) and its notice (p. 1); Clarifications No. 2, RFC 427 (p. 4) and RFC 470 (p. 28). A text search finds no budget or contract value. Amendments and clarifications checked, each with what it changed: Addendum No. 1 (deadline from to ); Addendum No. 2 (deadline to ); Addendum No. 3 (Guarantee Test window from 730 to 30 days, extended defects liability from 12 to 36 months, late-payment interest wording, “Air Insulated Substation” in the similar-contract test, ZESCO’s safety rules, technical changes, deadline to ); Clarifications (RFC 1–421), answered before Addendum No. 3; Addendum No. 4 (deadline to , no new date for clarification requests); Addendum No. 5 (exchange-rate date, type tests less than 8 years old in §7.5.1, Tunduma interface, technical and price schedule changes, deadline to ); Clarifications No. 2 (RFC 422–482). REV05 was compared with every earlier revision; no addendum or clarification changes the loss rates, the footnote, the penalty trigger wording or the reactor data table.
- 2
ZESCO Limited: Package 4 (RFB ZM-ZESCO-495237-CW-RFB), Update 2 archive: Addendum No. 3 and its notice, Request for Bids REV03 of , Clarifications (RFC 1–421) · Tier 1 · official · Verified
Where in the document
Addendum No. 3: item 6 (p. 10, late-payment interest wording); item 11 (p. 17, PCC 27.10 from 12 to 36 months); item 13 (p. 18, “Air Insulated Substation”); item 14 (pp. 18–19, PCC 25.2.2 from 730 to 30 days). Its notice (p. 1, table): tender closing from to ; clarification close-out to . Item 12 of the addendum gives the earlier date as ; the notice gives , the date Addendum No. 2 had set. Clarifications (pp. 1–188): RFC 68 (p. 39); RFC 95 (p. 52); RFC 270 (p. 123); RFC 273 (pp. 124–125); RFC 274 (p. 125).
- 3
ZESCO Limited: Package 4 (RFB ZM-ZESCO-495237-CW-RFB), original tender documents archive: Request for Bids of , REV01 and Addendum No. 1 · Tier 1 · official · Verified
Where in the document
Request for Bids of , Specific Procurement Notice (the issue date; ¶7, the first deadline). Addendum No. 1 (pp. 1–3): Specific Procurement Notice ¶7, BDS ITB 23.1 and 26.1, deadline and opening from to , 10:30 CAT, issued with RfB REV01. The archive on ZESCO’s server was replaced after issue (server date ) and holds Addendum No. 1.
- 4
ZESCO Limited: Package 4 (RFB ZM-ZESCO-495237-CW-RFB), Update 1 archive: Addendum No. 2 and Request for Bids REV02 of · Tier 1 · official · Verified
Where in the document
Addendum No. 2, item 1 (p. 1): deadline from to , 10:30 CAT; Annex 1 (p. 2): REV02 supersedes REV01. RfB REV02, PCC 25.2.2 (PDF p. 992, printed p. 960): the Guarantee Test to be “completed within 730 Days from the date of Completion”, the wording Addendum No. 3 replaced.
- 5
ZESCO Limited: Package 4 (RFB ZM-ZESCO-495237-CW-RFB), Update 3 archive: Addendum No. 4 (titled Amendment No. 4), its notice and Request for Bids REV04 of · Tier 1 · official · Verified
Where in the document
Addendum No. 4, item 1 and the note to all bidders (p. 1): deadline from to , 10:30 CAT; forms, including any bid validity declaration, to match the new date. Its notice (p. 1, table): clarification close-out , new date “None”; tender closing .
- 6
World Bank: Procurement Plan, RETRADE-SA MPA Phase 1: Zambia - Tanzania Interconnector Project (P507033), revised · Tier 1 · official · Verified
Where in the document
P. 8, Works table, row ZM-ZESCO-495237-CW-RFB: description, “IDA / E3960”, review type “Prior”, estimated amount 26,052,525.18 in the column headed US$, and the planned dates (out of date, not used). Revised plan date in the header of the same page. The plan describes Package 4 only as a new Nakonde substation, without Kasama; the page states this beside the figure.
- 7
ZESCO Limited: tender register · Tier 1 · official · Verified
Where in the document
The register as read on and again, byte-identical, on : the Package 4 entries, from the original (issued ) to “ZM-ZESCO-495237-CW-RFB-UPDATE-4-FILES-8/09/2026” (issued , closing at 10:30). No evaluation or award notice for Package 4 appears on the page. The Update 1 entry shows a closing time of 15:12 where Addendum No. 2 gives 10:30 CAT; the page uses the addendum.
- 8
World Bank: procurement notices for project P507033, RETRADE-SA MPA Phase 1: Zambia - Tanzania Interconnector Project (as listed on ) · Tier 1 · official · Verified
Where in the document
The list as read on : 11 notices. ZM-ZESCO-495237-CW-RFB (Package 4) appears only as the Invitation for Bids of 07-May-2026 (notice OP00443306); there is no Contract Award notice for it. The latest notice is a Contract Award of 14-Oct-2026 for ZM-ZESCO-471432-CW-RFB (Mpika–Kasama lines), another package. The same data feeds the procurement tab of the project page on projects.worldbank.org, which is built by script. Names of officials are not used.
ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work
How to cite
ListingMinds, “In Zambia’s Nakonde–Kasama tender, losses are priced into the bid and enforced at the factory test”, , updated . https://www.listingminds.com/energy/field-notes/zambia-nakonde-kasama-substation-tender