Grid and T&D · Field note

Vizag’s green hydrogen transmission tender: the charge waits for all eight elements, the guarantee does not

Vizag phase I was won at a flat Rs. 8,564.11 million a year, none of it payable under the draft agreement until all eight elements are commissioned. The guarantee, delay damages and the draft’s six-month deadline for two CERC orders come earlier; as of 22 October 2026, CERC’s orders page showed neither.

ListingMinds · Published and updated · Sources verified

Geography: India, Andhra Pradesh · Procurement rounds covered: India RECPDCL Vizag transmission, phase I, closed

On this page

Adani Energy Solutions Limited was the lowest of the four qualified bidders for India’s Vizag phase I transmission scheme, with a final quoted charge of Rs. 8,564.11 million a year. That one figure is the whole price: bidders quoted a single annual charge for 35 years from the project’s scheduled commercial operation date (Scheduled COD), covering all costs, taxes, duties and levies, and the same charge is payable every year of the agreement’s term. It pays for eight elements that REC Power Development and Consultancy Limited (RECPDCL) tendered together for green hydrogen and ammonia projects in the Vizag area: two new 765/400 kV substations, a STATCOM, three 765 kV double-circuit lines and two 400 kV connections.1, 5, 6

Each element listed all seven others as pre-required, and the tender makes every element wait for them: the RFP considers its charges only after they are commissioned, and the draft agreement issued with the RFP declares its COD only after theirs. Read together, the RFP and the draft agreement make the charge start for the whole scheme or not at all: no element was to be paid for until all eight were commissioned, so the slowest element sets the day the money starts. From then on, the draft agreement pays the charge against availability: with a target of 98%, a month’s charges for the AC system are paid in full at 98% to 98.5%, rise in proportion above that up to a cap at 99.75%, fall in proportion below 98%, and below 95% carry a further deduction.1, 2, 4

The obligations start sooner: within ten days of the letter of intent, the selected bidder had to give the Central Transmission Utility of India Limited (CTU), the Nodal Agency under the draft agreement, a contract performance guarantee of Rs. 196.75 Crore, valid to three months after the Scheduled COD and then extended to three months after the actual COD. In the same ten days it had to buy 100% of the project company, Vizag Power Transmission Limited, the transmission service provider in the draft. The draft agreement gives the provider six months from its Effective Date (the latest of the guarantee given, the project company bought and the agreement signed) to obtain two orders from the Central Electricity Regulatory Commission (CERC): a transmission licence, and the adoption of its charge.1, 2, 3

A late element costs twice: damages owed while no charge is paid

Every element had a Scheduled COD of 30 months, which the RFP counts from the Effective Date and the draft agreement’s schedule from the transfer of the project company. Under the draft agreement, a provider that misses an element’s or the project’s Scheduled COD, as extended, pays the Nodal Agency 3.33% of the Monthly Transmission Charges applicable to that element or to the project for each day of delay up to sixty days, and 5% beyond that, “as liquidated damages for such delay and not as penalty”. The draft caps the damages at the amount for six months of delay, after which its default and termination article applies; damages left unpaid come out of the contract performance guarantee, then out of transmission charges. For the project after its COD, the draft defines Monthly Transmission Charges as the annual charge multiplied by the days in the month and divided by the days in the year.1, 2, 4

Put the draft’s two rules together and a late element costs the provider twice: for each day it owes damages to the Nodal Agency, up to the six-month cap, while nothing is paid for the finished elements either.

Worked exampleDelay damages on the whole Vizag phase I project at the winning charge, after 30 and 60 daysIf the whole Vizag phase I project were 30 days late, the damages at the winning charge would be about Rs. 703.20 million, almost exactly the Rs. 703.90 million of one 30-day month’s charges; at 60 days about Rs. 1,406.40 million, roughly 71% of the Rs. 1,967.50 million performance guarantee from which unpaid damages are recovered. These are damages owed, on top of the charges not yet paid: by ListingMinds’ reading of the pre-required elements, no element’s charges were to be paid until every element was commissioned.Show the calculation
Worked exampleDelay damages on the whole Vizag phase I project at the winning charge, after 30 and 60 daysThe whole project misses its Scheduled COD by the same number of days, so the damages are worked out on the project’s Monthly Transmission Charges. A 30-day month and a 365-day year. Only the days of delay change between the two cases.
Published values
L1 final quoted transmission charge, per yearRs. 8,564.11 million1, 6
Delay damages for each day, up to 60 days of delay3.33 % of Monthly Transmission Charges2
Contract performance guaranteeRs. 196.75 Crore1, 2
Assumptions
Days in the month30 days
Days in the year365 days
Delay in case A30 days
Delay in case B60 days
Calculation
StepCalculationResult
Monthly Transmission Charges, 30-day monthRs. 8,564.11 million × 30 ÷ 365Rs. 703.90 million
Damages for each day of delayRs. 703.90 million × 3.33%Rs. 23.44 million
Case A: 30 days lateRs. 23.44 million × 30 daysRs. 703.20 million
Case B: 60 days lateRs. 23.44 million × 60 daysRs. 1,406.40 million
Performance guarantee in the same unitRs. 196.75 Crore × 10 million per croreRs. 1,967.50 million
Case B as a share of the guaranteeRs. 1,406.40 million ÷ Rs. 1,967.50 million × 10071.48 %

Result. If the whole Vizag phase I project were 30 days late, the damages at the winning charge would be about Rs. 703.20 million, almost exactly the Rs. 703.90 million of one 30-day month’s charges; at 60 days about Rs. 1,406.40 million, roughly 71% of the Rs. 1,967.50 million performance guarantee from which unpaid damages are recovered. These are damages owed, on top of the charges not yet paid: by ListingMinds’ reading of the pre-required elements, no element’s charges were to be paid until every element was commissioned.

Method. Monthly Transmission Charges = the annual charge × days in the month ÷ days in the year, as the agreement defines them for the project after its COD; the example uses that amount as the base the damages clause names for a delay before COD. Damages = 3.33% of it for each day of delay up to 60 days. Applied to the whole project at the L1 final quoted charge; amounts in Indian rupees (Rs.), as the documents write them, nominal, rounded to two decimals at each step. The rate after 60 days and the six-month cap are not calculated: the agreement’s wording is quoted above.

The result, and the purchase of the project company

Four bidders qualified on their technical bids, each bidding alone with 100% equity: Adani Energy Solutions Limited, Dilip Buildcon Limited, Power Grid Corporation of India Limited and Resonia Limited. The charge was then set in an e-reverse auction, with the lowest Initial Offer as the ceiling, in which bidders saw only the lowest offer, not who had made it.1, 5 RECPDCL’s result lists final quoted charges, in rupees millions a year, of 8,564.11 for Adani Energy Solutions as L1, and 8,585.58, 10,836.52 and 22,932.00 for L2 to L4, whom it does not name. On ListingMinds’ arithmetic, the two lowest offers were Rs. 21.47 million a year apart.1, 6

A bid bond of Rs. 78.70 Crore stood behind the ten days after the letter of intent: it could be invoked if the selected bidder failed to sign the share purchase and transmission service agreements, give the performance guarantee or buy the project company.1, 3 In a disclosure to the stock exchanges dated , Adani Energy Solutions Limited said it had that day executed a Share Purchase Agreement with RECPDCL for 100% of the equity shares of Vizag Power Transmission Limited, and reported the acquisition as completed.7

Two orders from the regulator, on the provider’s clock

The draft agreement has the provider apply to CERC for both orders, the licence and the adoption of its tariff under section 63 of the Electricity Act, within five working days of the project company’s acquisition. The draft then allows six months from the Effective Date to obtain them, along with financial closure and the award of the EPC contract, unless completion is affected by force majeure or the Nodal Agency waives the condition in writing. For EPC contractors, the draft puts the award of their contract on the same clock as the two CERC orders.2

With the acquisition reported as completed on , the draft’s six months cannot have started before that day. As of , neither RECPDCL’s tender page, Adani Energy Solutions’ disclosure nor CERC’s records of the hearings of and gave the date of the letter of intent or of the agreement’s signing. The end of the draft’s six months cannot yet be dated from those documents.2, 7, 8, 9, 10

If a condition is still unmet three months after the time allowed, the draft requires the provider to furnish to the Nodal Agency an additional contract performance guarantee of Rs. 19.68 Crore every month until all are met. If fulfilment slips beyond nine months from the Effective Date without that additional guarantee, or beyond twelve months with it, the draft lets the Nodal Agency, subject to its force majeure provisions, terminate on at least seven days’ notice; the provider then owes liquidated damages of Rs. 196.75 Crore, the full original performance guarantee, recovered by invoking it. Unless a late order counts as force majeure or the Nodal Agency waives the condition, the draft thus makes the regulator’s pace the provider’s risk.1, 2

Vizag Power Transmission Limited’s two petitions, 514/TL/2026 for the licence and 515/AT/2026 for the adoption of the charges discovered in the bidding, were heard on . Its representative said the newspaper notice had been published and CTU had sent its recommendation on the licence; CERC admitted both petitions and issued notice to the respondents. In the adoption case it asked RECPDCL to furnish within a week the Cost Committee Report, the Bid Evaluation Committee’s minutes, the details of the complete bidding process and the computation of the levelized tariff, including its comparison with the tariff the successful bidder quoted. What CERC asked for put the numbers behind the winning charge before it, not only the record of how that charge was reached.8

CERC heard both petitions again on , and the project company asked for them to be reserved for orders. CTU had still not filed what CERC directed on : the minutes of its own consultation meeting of on evolving transmission schemes in the Southern Region (the 49th CMETS-SR). They had not yet been issued, CTU said; CERC gave it ten more days to file them once issued, and said both petitions would be listed for another hearing on . As of , CERC’s orders page showed no order on either.10, 11, 12

The grid and T&D guide covers grid procurement more widely.

Sources (12)

  1. 1

    RECPDCL (REC Power Development and Consultancy Limited): Single Stage Request for Proposal, Transmission system for proposed Green Hydrogen / Green Ammonia projects in Vizag area, Andhra Pradesh (Phase-I) · Tier 1 · official · Verified

    Where in the document

    Pages are the PDF’s page numbers, which match the printed ones. RFP of . RFP Notification para 2, the scope table and its column “Scheduled COD in months from Effective Date” (pp. 3–6); para 6, the Acquisition Price and the transfer of assets after 35 years (p. 7); para 10, the bid deadline (p. 8); definitions “Bid Bond” (p. 14) and “Quoted Transmission Charges” (p. 17); clause 1.6 (p. 24); clause 2.1.2 (pp. 28–29); clauses 2.1.3.1 (p. 29) and 2.1.4 (p. 30); clauses 2.5.3 and 2.5.5.2 (p. 39); clause 2.6.1, table and note (pp. 45–46); clause 2.7.1 (p. 46); clause 2.8.1 (p. 47); clauses 2.11.1 and 2.11.2 (p. 48); clause 2.12 (p. 49); clause 2.13.2 (p. 50); clause 2.15.2 (pp. 50–51); clause 3.6.1 (p. 58); Annexure 21, notes 2 and 5 (p. 129); Specific Technical Requirements for Substation, clause B.2.2, table of NGR values, the line lengths (pp. 153–154). Amendments checked, all nine on RECPDCL’s tender page: Amendment I () names the SPV Vizag Power Transmission Limited in the RFP, TSA and SPA; Amendments II (), III (), IV (printed ), V () and VI () move only the dates in clauses 2.7.1, 2.7.2 and 2.13.1; Amendments VII () and IX () rewrite clause A.20.0 of the technical requirements (towers and pole structures where lines cross protected, urban planning or forest areas), which is not cited; Amendment VIII () moves the bid deadline to with a new schedule and, in para 2, clause 1.2, clause 2.6 and Annexure 8, makes the future switchyard at Pendurthi a 220 kV GIS switchyard and adds a 400 kV bay for a second STATCOM, keeping 30 months and 100% unchanged. No amendment changes any other cited clause. Appendix A (engineering drawings) was not used. Tender documents named, each recorded under Tender documents with what it changes: Amendment-I, Amendment-II, Amendment-III, Amendment-IV, Amendment-V, Amendment-VI, Amendment-VII, Amendment-VIII, Amendment-IX.

  2. 2

    RECPDCL: Transmission Service Agreement, draft issued with the RFP, Transmission system for proposed Green Hydrogen / Green Ammonia projects in Vizag area, Andhra Pradesh (Phase-I) · Tier 1 · official · Verified

    Where in the document

    Pages are the PDF’s page numbers, which match the printed ones. The draft shows no date beyond “2026”; it was posted with the RFP. The parties (p. 3) and recital C (p. 4); Article 1, definitions “Commission” or “CERC” (p. 6), “Expiry Date” (p. 8) and “Monthly Transmission Charges” (pp. 10–11); Article 2.1, Effective Date, and 2.2.2 (p. 18); Articles 3.1.1 to 3.1.3, the guarantee, the licence and adoption application and the conditions subsequent (pp. 20–21); Articles 3.3.1 to 3.3.4, the additional guarantee, termination and force majeure (pp. 22–23); Article 6.2.1, proviso (p. 35); Articles 6.4.1 to 6.4.4 (pp. 36–37); Article 8.2 (p. 40); Article 13 (p. 52); Schedule 2 (pp. 214–215); Schedule 4, para 1.2, AC system (a) to (e) (p. 225), and the definitions of AA and Tmn (p. 226). Amendments checked: Amendment I (the SPV’s name), Amendments VII and IX (clause A.20.0, not cited) and Amendment VIII (Schedule 1 and the Schedule 2 rows for the Pendurthi substation and the STATCOM, 30 months and 100% unchanged); none changes a cited article or schedule.

  3. 3

    RECPDCL: Amendment-I to the RFP Documents, Vizag area green hydrogen / green ammonia transmission system (Phase-I) · Tier 1 · official · Verified

    Where in the document

    One page, a scan read as a page image. Row 1, RFP, TSA and SPA: “All the reference to the name of the SPV may be read as” Vizag Power Transmission Limited.

  4. 4

    RECPDCL: Amendment-VIII to the RFP Documents, Vizag area green hydrogen / green ammonia transmission system (Phase-I) · Tier 1 · official · Verified

    Where in the document

    Seven pages. Row 1, clause 2.7.1: the bid deadline moves from to , 1500 hours (IST); row 2, clause 2.7.2, the new schedule (qualified bidders , Initial Offers , e-reverse auction , letter of intent , transfer of Vizag Power Transmission Limited ); row 3, clause 2.13.1, the technical bids to be opened at 1530 hours (IST) on (p. 1). Rows 4 and 5 (pp. 2–7): RFP para 2 and clause 1.2, TSA Schedule 1, RFP clause 2.6, Annexure 8 and TSA Schedule 2, the future switchyard at Pendurthi made a 220 kV GIS switchyard and a 400 kV bay for a second STATCOM added; 30 months and 100% unchanged.

  5. 5

    RECPDCL: List of Qualified Bidders after opening of the Technical Bids, Vizag area green hydrogen / green ammonia transmission system (Phase-I) · Tier 1 · official · Verified

    Where in the document

    The table, rows 1 to 4: bidder, sole or consortium, equity contribution. The list carries no printed date; its file name and the server’s date are .

  6. 6

    RECPDCL: Result, final quoted transmission charges, Vizag area green hydrogen / green ammonia transmission system (Phase-I) · Tier 1 · official · Verified

    Where in the document

    The table, rows 1 to 4, headed “Final quoted transmission Charges (Rs. In Millions)”: L1 named, L2 to L4 not named. The notice carries no printed date; its file name and the server’s date are .

  7. 7

    Adani Energy Solutions Limited: disclosure to BSE and NSE under Regulation 30 of the SEBI Listing Regulations, execution of the share purchase agreement for Vizag Power Transmission Limited · Tier 2 · direct participant · Verified

    Where in the document

    Three pages. Covering letter dated , paragraph 1: the share purchase agreement with RECPDCL executed that day at about 12:30 p.m. IST, for 100% of the equity shares of Vizag Power Transmission Limited (p. 1). Annexure A, items f) “Completed” (p. 2) and i) 100% (p. 3). Tier 1 searched: RECPDCL's tender page for the Vizag phase I tender, read on , lists the result of but no letter of intent, transfer or signed agreement.

  8. 8

    Central Electricity Regulatory Commission (CERC): Record of Proceedings, petitions 514/TL/2026 and 515/AT/2026 of Vizag Power Transmission Limited, hearing of · Tier 1 · official · Verified

    Where in the document

    Two pages. The subjects of both petitions (p. 1); para 1, the petitioner’s submissions, with CTUIL’s recommendation under section 15(4) (p. 1); para 2, directions (a) to (e), and para 3, the listing for (p. 2). The record carries no date of its own beyond the hearing’s; CERC’s record of proceedings page (S-488, Sl. 1689) gives it as posted on . It does not give the letter-of-intent date, the agreement’s execution or its Effective Date.

  9. 9

    RECPDCL: tender page for transmission projects through tariff-based competitive bidding · Tier 1 · official · Verified

    Where in the document

    The page shows no date; as read on : the entry “Request for Proposal Document for Selection of Bidder as Transmission Service Provider … in Vizag area, Andhra Pradesh (Phase-I)” lists the NIT (English and Hindi), RFP, TSA, SPA, Appendix A, Amendments I to IX, Qualified Bidders and Results, and nothing later.

  10. 10

    Central Electricity Regulatory Commission (CERC): Record of Proceedings, petitions 514/TL/2026 and 515/AT/2026 of Vizag Power Transmission Limited, hearing of · Tier 1 · official · Verified

    Where in the document

    Two pages. The subjects of both petitions and the date of hearing (p. 1); the record’s first paragraph, the petitioner’s submissions, with the bulk consumers impleaded, CTUIL’s recommendation under section 15(4) and the request that the matters be reserved for orders (pp. 1–2); para 2, CTUIL on the minutes of the 49th CMETS-SR meeting of ; para 4, the additional ten days; para 5, the listing for (p. 2). The record carries no date of its own beyond the hearing’s; CERC’s record of proceedings page (S-818, Sl. 1809) gives it as posted on . It does not give the letter-of-intent date, the agreement’s execution or its Effective Date.

  11. 11

    Central Transmission Utility of India Limited (CTUIL): Agenda, 49th Consultation Meeting for Evolving Transmission Schemes in Southern Region (CMETS-SR), ref. CTU/S/00/49th CMETS-SR-Agenda · Tier 1 · official · Verified

    Where in the document

    102 pages. The covering letter (p. 1): the reference, the date 22.08.2026, the subject line, the meeting “now scheduled for 24.08.2026” through virtual mode, and the issuer’s address and website.

  12. 12

    CERC: Orders - 2026 (recent orders page), as opened on · Tier 1 · official · Verified

    Where in the document

    The page shows no date; as read on : the table “Orders - 2026”, newest entries Sl. 526 and Sl. 525, dated and posted 22.10.2026; no entry for petition 514/TL/2026 or 515/AT/2026, and none naming Vizag. The same address as S-487, opened again for this page.

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “Vizag’s green hydrogen transmission tender: the charge waits for all eight elements, the guarantee does not”, . https://www.listingminds.com/energy/field-notes/vizag-green-hydrogen-transmission-tender