Battery storage · Field note

Kenya’s mini-grid battery tender: a firm price for batteries its own documents size two ways

REREC asked for a firm lump sum for seven Kenyan solar mini-grids, but at three sites its specification and price schedules size the batteries differently: 162 against 378 kWh at Biamadhow. The tender’s own rules for settling such conflicts point both ways, so a bidder had to fix its price without knowing which battery REREC was buying.

ListingMinds · Published · Updated and sources verified

Geography: Kenya · Procurement rounds covered: Kenya REREC RFX 1000001594, closed

On this page

At Biamadhow, one of seven solar mini-grids in a Kenyan battery tender, the specification asks for 162 kWh of new battery storage; the price schedule bidders had to complete for the same site asks for 378 kWh. At Sangailu the two documents give 274 and 252 kWh, at Shimbir Fatuma 315 and 162 kWh, and at the other four sites they agree. The buyer, Kenya’s Rural Electrification and Renewable Energy Corporation (REREC), asked for a firm lump sum, not adjusted during the contract.1 At three of the seven sites, then, a bidder had to fix its price without the documents settling which battery REREC was buying.

REREC tendered the works as RFX No. 1000001594, in three lots awarded lot by lot, and the tender document states no contract value or budget. The plants, in Turkana, Wajir, Garissa and Mandera counties, run on solar PV with valve-regulated lead-acid batteries and a diesel generator in reserve. The works replace those batteries with a lithium-ion system and every inverter with a hybrid inverter, add solar PV, a 315 kVA step-up substation to 11 kV and a container, and remove the old equipment.1

Bids were due on .1 As of , REREC’s tender register lists no addendum, opening record or award for the tender, and its most recent list of contract awards covers July to December 2025.2, 3

Priced on one figure, designed to another

Bids were ranked on price: the tender that met the qualification criteria, was substantially responsive and had the lowest evaluated tender price was to be selected for award. That price was built from the price schedules, each site’s schedule carried into its lot’s summary and the lot totals into the Form of Tender. Before any price counted, the technical evaluation asked for the complete design and expected performance of each bid’s battery system and full compliance with the technical specifications for the lithium batteries, and a failure on any critical parameter made the tender non-responsive.1 A bid’s battery design went to the technical evaluators; its price was built on the schedules’ quantities.

The solar PV figures disagree as well: the project location table prints a total of 110 kWp although its site rows add up to 190 kWp, and the three parts of the tender that give the figure differ at Lowareng and Sangailu.1

Quantities per site, as each part of the tender document gives them
SiteLotAdditional PV, project location table (p. 88)Additional PV, site scope table (p. 93)Additional PV, price schedulesBattery storage, site scope table (p. 93)Battery storage, price schedules
Lowareng120 kWp0 kWp20 kWp252 kWh252 kWh
Eliye (Ille) Springs120 kWp20 kWp20 kWp100 kWh100 kWh
Biamadhow240 kWp40 kWp40 kWp162 kWh378 kWh
Sangailu230 kWp30 kWp80 kWp274 kWh252 kWh
Kiliwehiri320 kWp20 kWp20 kWp252 kWh252 kWh
Shimbir Fatuma340 kWp40 kWp40 kWp315 kWh162 kWh
Burduras320 kWp20 kWp20 kWp252 kWh252 kWh
Total as printed110 kWpnone printednone printednone printednone printed

Source: the tender document’s project location table (p. 88), summary of specific site scope (p. 93) and price schedules for each site (pp. 193 to 218).1

The tie-breakers lead back to each other

Once signed, the contract ranks its documents in the order it lists them wherever they conflict or are ambiguous: the Form of Tender and Price Schedules come second, the Specification fifth. The scope table that asks for 162 kWh at Biamadhow sits in the tender’s section headed Specifications; the price schedules sit in its bills of quantities. The bills say that their item descriptions are purely for identification and “in no way” modify or supersede the detailed descriptions in the conditions of contract and the specifications, and that their quantities are “estimated and provisional”. The general conditions add that, subject to the order of precedence, the contract documents are “correlative, complementary and mutually explanatory” and the contract is read as a whole.1 That deference is written into the very bills that hold the price schedules, the document the order of precedence puts second, so the rule that should settle the conflict leads back to the specification it was meant to outrank. Read alone, the contract’s order would put the schedule’s 378 kWh at Biamadhow above the specification’s 162 kWh; read with the bills’ own terms, the specification would govern.

The price itself is both fixed and measured. The special conditions make the contract price a firm lump sum, not adjusted during the contract. Yet the bills, whose quantities are provisional, pay on the contractor’s rates for the quantities of work actually done, and each interim certificate is valued “strictly” on the actual value of works executed and verified on site. The general conditions let the firm price move for a Change in the Facilities or where the contract provides for it, with a change priced, as far as practicable, at the rates and prices already in the contract. Each battery item in the schedules is a quantity in kWh, against which a bidder was to enter a unit price.1 A firm total and measured payment pull opposite ways, and where the quantity itself was in doubt, the price per kWh a bidder entered was, as far as practicable, the basis for pricing any change to it.

An error in the schedules fell under two rules as well. The Tender Data Sheet says any error touching the unit price and the total price leads to disqualification, and an error of more than 1% is a major deviation; the bills say arithmetic errors are corrected, the unit rate governing, and a tender is rejected if the bidder does not accept the correction.1 The same slip could end a bid under one section and be corrected under the other.

Two ceilings on delay damages

The time for completion is 40 weeks from the effective date, and the tender did not permit alternative completion times. Liquidated damages for late completion are 0.05% per day of the late part’s price, and the special conditions state two maximums in the same clause: “10 Percent of the final Contract Price” and “Maximum deduction for liquidated damages: 5% of contract price”. Once the maximum is reached, REREC may consider terminating the contract.1 Which maximum applies decides both how much lateness can cost in damages and when REREC may consider ending the contract.

Worked exampleDays of delay until each liquidated-damages maximum is reachedIn this hypothetical case, with the whole of the works late, damages at 0.05% per day reach the 5% maximum deduction after 100 days of delay and the 10% maximum after 200 days. Read one way, liquidated damages stop at 5% of the contract price after 100 days; read the other, they run to 10% after 200 days. A delay to one part of the works reaches either maximum later, since the rate applies to that part’s price.Show the calculation
Worked exampleDays of delay until each liquidated-damages maximum is reachedA hypothetical case: the whole of the works is late, so the daily rate applies to the full contract price. Only the maximum changes between the two steps.
Published values
Liquidated damages per day of delay, share of the late part’s price0.05 %1
Maximum deduction for liquidated damages5 % of contract price1
Other maximum in the same clause10 % of final contract price1
Assumptions
Share of the contract price that is late100 %
Calculation
StepCalculationResult
Days until the 5% maximum deduction is reached5% ÷ 0.05% per day100 days
Days until the 10% maximum is reached10% ÷ 0.05% per day200 days

Result. In this hypothetical case, with the whole of the works late, damages at 0.05% per day reach the 5% maximum deduction after 100 days of delay and the 10% maximum after 200 days. Read one way, liquidated damages stop at 5% of the contract price after 100 days; read the other, they run to 10% after 200 days. A delay to one part of the works reaches either maximum later, since the rate applies to that part’s price.

Method. ListingMinds’ calculation: the days until each liquidated-damages maximum is reached, the maximum divided by the daily rate, both as a percentage of the contract price, in a hypothetical case where the whole of the works is late; no project-specific data. The clause states both maximums; the example does not choose between them.

Thresholds set for the whole tender, not the lot

The financial resources the lowest evaluated bidder had to show before award, a construction cash flow and an average annual construction turnover, are each stated once, not per lot.1 A bidder for Lot 1 alone therefore faced the same turnover and cash-flow tests as one bidding for all three lots.

What a bidder needed to bid and be awarded, and what a winner would sign
TermWhat the tender sets
Lots and awardThree lots, awarded lot by lot. A bidder may bid for all three but can be awarded at most two; where it is the lowest evaluated in more than two, REREC decides which two it receives.
Tender securityA bank guarantee valid for at least 180 days from opening: Kshs 2,100,000.00 for Lot 1, Kshs 2,500,000.00 for Lot 2 and Kshs 3,500,000.00 for Lot 3.
Similar contracts, before awardAt least 3 similar contracts within the last 5 years, in Kenya, the East African Community or abroad, each worth at least Kenya shillings 143,928,000.00 equivalent and successfully and substantially completed.
Financial resources, before awardA construction cash flow of Kenya shillings 53,973,000.00 and an average annual construction turnover of at least Kenya shillings 449,776,000.00 over the last 5 years, each stated once, not per lot.
Company licencesA valid EPRA licence, class C1 (solar) and Class A (electrical), and National Construction Authority registration in category 4 and above for electrical or mechanical works, with a current annual practising licence.
Key staffA Project Supervisor registered as a professional engineer with the Engineers Board of Kenya, with at least 5 years’ experience, and two technicians with at least 2 years’ experience; at least one key staff member holds EPRA T3 (solar) and Class A (electrical) licences.
Critical equipmentFor each critical item, such as PV modules, lithium batteries, inverters and the step-up transformer: the manufacturer’s authorisation and warranty form, its ISO 14001:2015 certificate or NEMA licence, and its ISO 9001:2015 certificate or KEBS certification.
BatteriesLithium iron phosphate (LFP) to IEC 62619, with a warranty of at least 5 years and at least 6,000 cycles, a minimum 90% depth of discharge and at least a C/4 charge and discharge rate, in an insulated, air-conditioned room or container.
PaymentInterim certificates for work executed, capped cumulatively at 30% of the contract price after site clearance, access roads and fencing, 50% after foundation bases and 75% after station buildings, with the balance after installation, testing and commissioning.
Amount held back10% of every certified amount until completion of the whole works; half is paid on completion and half after the defects liability period.
Performance security10% of the contract amount, as a bank guarantee, not reduced on the date of operational acceptance.

Source: the tender document’s Tender Data Sheet (pp. 31 to 36), evaluation and qualification criteria (pp. 37 to 48), award limitation (pp. 91 and 220), battery specification (p. 97) and special conditions on payment and security (pp. 276 to 277).1

Bid security, net worth and entity rules on larger storage tenders are the subject of our note on reading a storage tender from the back.

What the site visit was meant to settle

The site visit on 4 and was mandatory; its form, signed and stamped by the bidder’s and REREC’s representatives, had to be in the tender at preliminary evaluation. Bidders were to visit “to obtain all information that may be required to guide on their costing decisions and any technical requirement that might have been omitted”, and the Tender Data Sheet said the visit’s minutes would be published on REREC’s website.1

Notes to the price schedules require all proposed equipment to be fully compatible with lithium battery systems where these are already installed and only need more capacity, and make any incompatibility the bidder’s sole responsibility. The tender’s own inventory of the seven plants lists a bank of 2 V lead-acid cells at every site and no lithium battery at any.1 The visit was where a bidder could check whether the note applied to any plant; if it did, the cost of a mismatch with the proposed equipment sat with the bidder.

Written questions had to reach REREC by 12:00 noon on ; REREC said it would publish its responses on its website or send them by email the same day.1 As of , the register shows neither the site visit’s minutes nor any clarification.2, 3 An answer sent only by email would not show there; on the public record, the tender’s figures stand as printed.

Sources (3)

  1. 1

    Rural Electrification and Renewable Energy Corporation (REREC), Kenya: tender document, RFX No. 1000001594, battery replacement and upgrade works at seven solar mini-grids · Tier 1 · official · Verified

    Where in the document

    Pages are the printed page numbers (“Page N of 306”), which match the PDF pages. Cover (p. 1); Invitation to Tender, the title and item 1 (p. 8); ITT 43.3 (p. 28); TDS ITT 1.1 and 8.1 (pp. 31–32); TDS ITT 8.2, 8.4 and 9.1 (p. 32); TDS ITP 13.1 (j) items 2, 6 and 8 to 11 (pp. 32–33); TDS ITT 15.2 and 19.7 (p. 33); TDS ITT 22.1 and 25.1 (p. 34); TDS ITT 34.2 (p. 35); TDS ITT 43 (p. 36); Section III, 1.4 and preliminary evaluation items 3, 18, 22, 24 to 27 and 29 (pp. 37–39), technical evaluation items 2, 3 and 5 with the note after them and financial evaluation item 2 (pp. 39–40), 4.1 (p. 42) and 7 b) i) to iii) (p. 43); qualification tables 3.2 and 3.3 (p. 47) and 4.2(a) with its note (p. 48); Section IV heading, Site Visit and Project Location table (p. 88); description and table of the existing system (pp. 89–90); General Scope and Award Limitation (p. 91); Summary of Specific Site Scope (p. 93); BESS clauses 6.1 to 6.4 (p. 97); Section VI, Bills of Quantities: introduction (p. 189); price schedules for each site (pp. 191–218), battery items at pp. 193, 197, 201, 206, 210, 214 and 218; summaries for Lots 1 and 2 (pp. 199, 207); summary for Lot 3, cost summary, notes a) to c) and Multiple Site Awards (p. 220); GCC 2.1 (pp. 237–238); GCC 11.2 (p. 242); GCC 26.2 (p. 257); GCC 39.1.1 and 39.2.4 (pp. 265–266); SCC 8.1, 8.2, 11.2 and 12 a) and b) (pp. 276–277); SCC 12 f) and h), 12.3 and 13.3.1 to 13.3.3 (p. 277); SCC 26.2 (p. 278); Contract Agreement, Articles 1.1, 1.2 and 2.1 (p. 285). Later documents checked: REREC’s tender register lists no addendum, clarification, site-visit minutes, opening record or award for this RFX (searched for the RFX number on ); the tender says any addendum is uploaded to REREC’s website under the tender documents (p. 8, item 9).

  2. 2

    REREC: tender register, search for RFX 1000001594 (notices, documents, opening minutes and awards) · Tier 1 · official · Verified

    Where in the document

    Documents tab, row DOC-01104: the tender document, file name ending “-FINAL”, public date . The same search returns no notice, addendum, opening minutes or award for this RFX. The search finds addenda where they exist: the same search for RFX 1000001591 returns that tender’s “ADDENDUM 001” notice.

  3. 3

    REREC: tender register, all tabs (tender notices, tender documents, opening minutes and tender awards) · Tier 1 · official · Verified

    Where in the document

    Tab labels and counts on : Tenders Notices 795, Tenders Documents 1136, Opening Minutes 317, Tenders Awards 4. Opening Minutes, newest first: opening schedules of other RFXs to 21 October 2026, none for RFX 1000001594. Tenders Awards: four half-yearly lists of contract awards, the latest “CONTRACT AWARDS FROM JULY TO DECEMBER, 2025”. A text search of the page for 1594 finds only the tender document, DOC-01104.

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “Kenya’s mini-grid battery tender: a firm price for batteries its own documents size two ways”, , updated . https://www.listingminds.com/energy/field-notes/kenya-mini-grid-battery-replacement-tender