Hydrogen · Field note

Australia’s Hydrogen Headstart Round 2: pricing an unindexed credit at the first stage

Round 2 applicants named their own unindexed production credit; an upper estimate given at the first stage was expected to cap later requests. Cost growth belonged in that figure, and the budget is unclear: ARENA reports the program’s funding revised to $1 billion, but its Round 2 page says up to $2 billion.

ListingMinds · Published and updated · Sources verified

Geography: Australia · Procurement rounds covered: AU Hydrogen Headstart Round 2, closed

On this page

The Headstart Production Credit that the Australian Renewable Energy Agency (ARENA) offers in Round 2 is a rate per kilogram of hydrogen, or per unit of derivative, on each unit of eligible production for a maximum of 10 years. The applicant names it, and should base it on the commercial gap between the cost of renewable hydrogen, including a justifiable return on capital, and its sales price. It is not increased for inflation and should stay fixed over the support period, unless ARENA, at its discretion, accepts another profile. Nothing is paid before the facility is operational, and ARENA said it was unlikely to contribute to capital costs. At the expression of interest, the first of the round’s two stages, an applicant could give two figures, a target credit and an upper estimate; the upper estimate was expected to be the most it could request at the Full Application. The total production volume in the Full Application caps total ARENA funding.1, 2

So for an applicant that gave an upper estimate, the allowance for inflation and cost growth, through development and up to 10 years of operation, belonged in that estimate: the credit would not rise for inflation, and the credit requested at the Full Application was expected to stay within it.

The Guidelines of put the total funding allocated for the Program at “up to $2 billion” (Australian dollars), intended for “a small number of Projects”, and let ARENA allocate more or less. They also foresaw an oversubscribed second stage: the invited applicants’ cumulative request was “expected to exceed the Total Funding Allocation”.1 On , announcing the seven projects shortlisted for the Full Application, ARENA wrote that “The Australian Government has revised the amount of funding allocated to the program in the 2026 Federal Budget to $1 billion”. Its Round 2 page, as read on , still said “Up to $2 billion of funding is available”.4, 5

The release is the most recent dated statement of the revision, and it speaks of the program, not of Round 2; neither it nor the Round 2 page says how much of the revised funding Round 2 can draw on. That matters to a bidder because the second stage was expected to ask for more than the Guidelines’ allocation: if the revision applies to Round 2, the same requests would compete for less.

Applications were assessed against five equally weighted merit criteria, and the credit sits inside one of them, financial viability and co-funding commitment. Under that criterion, ARENA considers the proposed credit and the total funding request, and cost competitiveness by the implied cost per kilogram of hydrogen delivered over the contract term, including capital and operating costs and excluding any concessional funding. That pulls the proposed credit two ways: the higher it is set, the larger the request this criterion weighs; the lower, the less room it leaves for cost growth the applicant must carry, unindexed, for up to 10 years.1

As of , ARENA’s funding opportunities page listed Round 2 among closed opportunities “no longer accepting applications”, in a section that says successful projects “will be publicly announced at a later date”.6

The eligibility floor

A project needed a new electrolysis facility, 100% powered by renewable energy from behind-the-meter generation or from surrendered eligible renewable electricity certificates created within 12 months of production or a timeframe agreed with ARENA; coal gasification or steam methane reforming with carbon capture and storage was not eligible, and all end uses, export included, were. The minimum was 30 MW of electrolysis at a single site, measured as nameplate capacity, with production in Australia; production spread across geographically diverse sites was not eligible.1

Shortlisted is not funded

The seven projects ARENA shortlisted range from 120 MW to 750 MW of electrolysis, in Tasmania, Queensland, Victoria and Western Australia, for end uses including methanol, ammonia, urea and alumina. All seven sit well above the 30 MW floor.5

The seven projects ARENA shortlisted for Round 2, as its release lists them
ApplicantProjectElectrolysis (MW)StateHydrogen end use
Bell Bay Powerfuels Pty LtdBell Bay Powerfuels300TASMethanol
European Energy Australia Pty LtdSouth East Queensland Power-to-X Project150QLDMethanol
HAMR Energy Pty LtdPortland Renewable Fuels Project220VICMethanol and SAF
HIF Asia Pacific Pty LimitedHIF Tasmania e-Fuel Facility140TASMethanol
Murchison Hydrogen Renewables Pty Ltd, as trustee for Murchison Hydrogen Renewables Project TrustMurchison Green Hydrogen Project Stage 1B500WAAmmonia
Perdaman Commercial Developments Pty LtdPerdaman Helios (Karratha): Decarbonising Fertilisers750WAUrea
Summit Hydro Pty LtdGladstone Green Hydrogen Project120QLDAlumina

Source: ARENA’s release announcing the Round 2 shortlist, its table and footnote.5

ARENA’s release said only applications meeting “a high merit threshold” would be considered for funding, and that a recommendation would then go to the Minister for Climate Change and Energy for approval.5 Success at the Full Application brings only a non-binding Offer to Negotiate a Funding Agreement: every funding offer and payment is conditional on executing a Funding Agreement, and ARENA may withdraw or reduce an offer during negotiation.1

No money moves at the shortlist: a shortlisted project still has to clear that threshold, negotiate under a non-binding offer and sign a Funding Agreement, and even then the credit is paid only on eligible production. Our hydrogen guide follows the same distinction, between being selected and being funded, in the European Hydrogen Bank’s auctions.

What an offer to negotiate costs the applicant

When ARENA issues an Offer to Negotiate, the applicant must provide a bid bond, in an amount ARENA confirms but “not expected to exceed $5 million”. It may be forfeited in situations that include withdrawing from negotiations or missing agreed milestones, such as Financial Close, unless ARENA extends them. The bond must come from a bank with a branch in Australia rated at least A- by Standard & Poor’s or A3 by Moody’s and, if not called, is expected to be returned at Financial Close. So the bond is at risk before any credit flows: it is expected back at Financial Close, and nothing is paid until the facility operates.1

The Funding Agreement is expected to include upside sharing if a project materially outperforms: ARENA expects 50% of upside to be shared, which may be negotiated, with repayment capped at the total funding provided.1 Agreeing a Knowledge Sharing Plan is a condition of funding, and ARENA’s template marks the Data Snapshots public apart from agreed exceptions: due every 6 months, 20 times, from commissioning to 10 years after, with monthly electricity, water and other O&M costs among their data. The template leaves the scope and contents of each deliverable to be developed through the Full Application stage and the Funding Agreement negotiations. If the template’s marking survives negotiation, a funded project’s monthly power, water and other operating costs would be public, apart from any exceptions agreed with ARENA.1, 3

Where the round stands

ARENA’s release on the shortlist gave applicants until early to submit Full Applications, later than the the Guidelines had given, subject to ARENA’s confirmation; the Guidelines mark every date of that stage as “subject to change”.1, 5

Round 2 as its Guidelines set it, with every date after the expression of interest “subject to change”, and what ARENA said later (amounts in Australian dollars)
StepRound 2’s GuidelinesLater, from ARENA
FundingUp to $2 billion for the Program, the Total Funding Allocation; ARENA may allocate more or lessRevised to $1 billion for “the program” in the 2026 Federal Budget, ARENA wrote on ; on its Round 2 page still said up to $2 billion
Expressions of interestOpen from Friday ; due 5:00pm AEDT, Monday ; late ones accepted only in exceptional circumstances, as ARENA determinesOn ARENA’s funding opportunities page listed the round as closed
Outcome of the first stageApplicants notified in ARENA publicly announced seven shortlisted projects on
Full Applications due, a date ARENA would confirm with invited applicantsEarly , in ARENA’s release on the shortlist
DecisionBetween October and On the funding opportunities page listed the round as closed, under a section line saying successful projects “will be publicly announced at a later date”; it gave no date

Source: Round 2’s Program Guidelines (the funding allocation and the timetable); ARENA’s release on the shortlist; ARENA’s Round 2 page and funding opportunities page.1, 4, 5, 6

The Guidelines put the decision between October and , subject to change. Projects ARENA names as successful at the decision would hold a non-binding offer and a bond to post, not a Funding Agreement.1

Sources (6)

  1. 1

    Australian Renewable Energy Agency (ARENA): Hydrogen Headstart Round 2, Program Guidelines · Tier 1 · official · Verified

    Where in the document

    Dated on the cover; commencing on (cl. 1.18). The cover is printed “Page 0 of 34”, so each printed page is the PDF page minus one; printed pages are given, with the PDF page. Cl. 1.2 and 1.3 (p. 4); cl. 1.10 to 1.12 (p. 5); cl. 1.14 (p. 6); cl. 2.1, the timetable, cl. 2.2 and cl. 2.3 (p. 7); Part 3, Eligibility Criteria A and B (pp. 8–9); cl. 4.3 and the Part 4 headings (pp. 11–13); Merit Criterion D (p. 13); cl. 5.9 (p. 14); cl. 6.1 to 6.3, 6.5, 6.6, 6.8 and 6.9 (p. 18); cl. 7.4 and 7.5 (p. 19); Appendix A, A.1 to A.3 (pp. 23–24) and A.11 and A.12 (p. 25); glossary, “Grant” (p. 33) and “Total Funding Allocation” (p. 34). Amendments checked: this is the only Guidelines file linked from ARENA’s Round 2 page on ; no amended Guidelines, clarification or published FAQ was found there, although cl. 1.19 and 5.12 allow ARENA to amend the Guidelines after the EOI stage; ARENA’s outcome letters to shortlisted applicants (cl. 5.11) are not public. Later statements: ARENA’s release of (S-214) revised the program’s funding to $1 billion and moved the Full Application date to early ; it does not reissue or amend the Guidelines. The template Funding Agreement (cl. 7.1) is not on the Round 2 page.

  2. 2

    ARENA: Hydrogen Headstart Round 2, Project Summary template (spreadsheet) · Tier 1 · official · Verified

    Where in the document

    The file carries no date; it is linked from ARENA’s Round 2 page under “Step 2: How to apply”. Sheet “Project Overview”, section “Headstart Production Credit (HPC)”, rows “Target: HPC value (hydrogen)” and “Upper estimate: HPC value (hydrogen)” (“expected to be a cap for the funding that can be requested at the Full Application stage”).

  3. 3

    ARENA: Hydrogen Headstart Round 2, Knowledge Sharing Plan template · Tier 1 · official · Verified

    Where in the document

    The file carries no date; it is linked from ARENA’s Round 2 page under “Step 2: How to apply”. Deliverables table, row KS6 “Data Snapshots” (“20 times”; every 6 months, due by 31 March and 30 September, from commissioning to ten years after; “Public, apart from any exceptions agreed with ARENA”); section 1.9.1, rows “Hydrogen power costs”, “Hydrogen water costs” and “Hydrogen other O&M costs” (monthly totals, “Public”). The template says the scope of each deliverable is settled during the Full Application stage and Funding Agreement negotiations.

  4. 4

    ARENA: Hydrogen Headstart Round 2, funding page · Tier 1 · official · Verified

    Where in the document

    The page shows no date; as read on . Step 1, “About the program” (“Up to $2 billion of funding is available under Hydrogen Headstart Round 2”); Step 3, “Observe the key dates” (EOI open and due dates). The page links three documents: the Program Guidelines (S-210), the Project Summary spreadsheet (S-211) and the Knowledge Sharing Plan template (S-212); no amendment, FAQ or template Funding Agreement is listed.

  5. 5

    ARENA: news release, “ARENA shortlists major projects to scale Australia’s renewable hydrogen industry” · Tier 1 · official · Verified

    Where in the document

    Dated and last updated . Third paragraph (funding revised “in the 2026 Federal Budget to $1 billion”; the assessment and “high merit threshold” wording); the shortlist table (applicant, project title, electrolysis facility size in MW, state, hydrogen end use) and its footnote (Murchison Hydrogen Renewables Pty Ltd as trustee); last paragraph (“Shortlisted applicants now have until early to submit their full application”, used in the timetable table).

  6. 6

    ARENA: Funding Opportunities · Tier 1 · official · Verified

    Where in the document

    The page shows no date; as read on . Section “Closed”, its introduction (“no longer accepting applications. Successful projects will be publicly announced at a later date”) and the entry “Hydrogen Headstart Round 2” (“Status: Closed”).

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “Australia’s Hydrogen Headstart Round 2: pricing an unindexed credit at the first stage”, . https://www.listingminds.com/energy/field-notes/australia-hydrogen-headstart-round-2