Battery storage · Field note
Australia’s CIS Tender 10: the revenue floor you bid is the one you sign
Each Tender 10 bid named its own unindexed revenue floor, ceiling and cap for up to 15 years, and a selected bid is signed on that basis. If Financial Close is then not reached, the contract ends automatically and the developer owes up to AUD 4,000,000, backed by its performance security.
ListingMinds · Published and updated · Sources verified
Geography: Australia · Procurement rounds covered: AU CIS Tender 10, NEM dispatchable, closed
On this page
In Tender 10 of Australia’s Capacity Investment Scheme (CIS), every bidder wrote the money terms of its own contract, an unindexed revenue floor, ceiling and cap for up to 15 years; the financial score rewarded low numbers, all else being equal, while the Guidelines asked for numbers the project could finance. Under the resulting Capacity Investment Scheme Agreement (CISA), the Australian Government tops a project’s revenue up by 90% of the difference when it falls below the Annual Floor, the operator pays the Government 50% of the excess revenue above the Annual Ceiling, and the Annual Payment Cap limits both payments. Each of the three is a fixed nominal amount per financial year with no indexation or escalation, and the support term, also bid, runs at most 15 years after the Support Start Date.1, 2, 3
The Guidelines told proponents to make their bids both competitive and “sufficient to enable their Project to reach Financial Close”, considering the project’s financing structure and realistic expectations of debt and equity, and left each proponent responsible for its own figures. Yet the financial criterion, MC1, carried 50% of the merit score and favours a low forecast Net CISA Cost and Maximum Liability, which, all else being equal, fall with a lower floor, ceiling and cap and fewer support years.1 So, all else being equal, the figures that scored best on MC1 gave the project the least downside protection to raise finance against, and a selected developer signs on the basis of them, unindexed, for the whole term, unless the Government agrees amendments. During the tender, AEMO Limited and its subsidiary AusEnergy Services Limited (ASL), which administer it, may also ask proponents to respond to amended Bid Variables.1
As of , the Open CIS tenders page of the Department of Climate Change, Energy, the Environment and Water (DCCEEW), last updated on , listed Tender 10, whose bids closed on , among the CIS tenders in progress, with results indicated for January/February 2027.5 On the same day, , ASL’s Tender 10 page, last updated on , gave Q1 2027 for announcing successful bids.4 The Guidelines had said . The tender sought an indicative 4 GW of 4-hour equivalent, or 16 GWh, of dispatchable capacity in the National Electricity Market (NEM), a volume the Government may raise or lower within the tender’s Policy Objectives.1, 4
What a selected bid has to sign
A Tender 10 bid is binding: an offer open for acceptance through its Validity Period, which ends when the bid entity signs a CISA, at the Government’s notice (expected about nine calendar months after bids closed), if the tender is cancelled, or if the proponent withdraws by notice giving its reasons. The contract was part of the bid: a clean version of the project documents in a form “considered capable of acceptance by the Australian Government”, needing no further changes beyond details still to be completed, with a Departures Table giving the reason for any departure. Departures were to be “strictly necessary”: one that adds risk, administrative burden or cost for the Government, or strays from the Policy Objectives, can exclude a bid, and a bid without a Departures Table accepts the documents in full.1
The Government, through the Minister, selects the successful proponents on the recommendation of AEMO Limited and ASL, notifies each that it intends to sign on terms satisfactory to the Government, and may reject proposed departures. A selected proponent must then enter into the project documents on the basis of its bid, subject to any amendments agreed with the Government, and may not raise departures it did not bid, unless they concern provisions the Government has changed since.1
In drawing up the recommended bids, AEMO Limited and ASL may take into account whether a proponent announced as successful in an earlier CIS tender went on to execute its binding commitments and sign the project documents. A selected developer that decides not to sign can still withdraw, but that record may be weighed against it in a later CIS tender.1
| Term | In Tender 10 | Set by |
|---|---|---|
| Support term (Final Support End Date) | Up to 15 years after the Support Start Date | Bidder |
| Annual Floor | AUD per financial year, fixed nominal; no indexation | Bidder |
| Annual Ceiling | AUD per financial year, fixed nominal; no indexation | Bidder |
| Annual Payment Cap | AUD per financial year, fixed nominal; no indexation | Bidder |
| Revenue Floor Support Percentage | 90% of the shortfall below the Annual Floor | Documents |
| Revenue Ceiling Sharing Percentage | 50% of revenue above the Annual Ceiling | Documents |
| Milestone dates, including Financial Close | Each a date the project must meet, or face a cure plan or termination | Bidder |
| COD Target Date (commercial operations date) | Earlier credible dates score higher under MC2 | Bidder |
| COD Sunset Date | 12 months after the COD Target Date as bid | Documents |
| Final Support Commencement Date | The COD Sunset Date as bid; cannot be extended | Documents |
| Performance Security Amount | AUD 20,000 per MW of Export Capacity, up to AUD 4,000,000 | Documents |
| Early Termination Amount before COD | AUD 20,000 per MW of Export Capacity, up to AUD 4,000,000 | Documents |
Source: Tender 10’s Tender Guidelines (Table 5 and Merit Criterion 2), the proforma CISA (Reference Details, Schedule 5 and the clauses on security, milestones and commissioning) and the Q&A on indexation.1, 2, 3
Missing Financial Close has a price
The milestone dates up to Financial Close are bid as well; a missed date needs a draft cure plan within 30 Business Days, and if Financial Close is not reached within 40 Business Days after the Financial Close sunset date, the CISA ends automatically, unless a draft cure plan is pending or approved or that period is extended. That automatic end, like termination by the Commonwealth for defaults that include missed milestones, late commissioning, the security and the social licence commitments, obliges the operator to pay an Early Termination Amount. Before commercial operation it is AUD 20,000 per MW of export capacity, up to AUD 4,000,000. The Commonwealth puts its own loss higher, at a “genuine pre-estimate of its loss at greater than $4,000,000”, and sets the amount lower for value-for-money reasons.2
The Performance Security uses the same formula. It is a letter of credit or bank guarantee from an Australian branch of an authorised deposit-taking institution rated at least A- (Standard & Poor’s) or A3 (Moody’s), due within 20 Business Days of signing. If the Early Termination Amount goes unpaid, the Commonwealth may draw on the security. The bid was already scored on this: MC3, the criterion on organisational, resource and financing capability, assessed the ability to provide the security and counted evidence of it as higher merit.1, 2 Before commercial operation, then, the security covers exactly what the developer would owe if the project failed to reach Financial Close, whatever the reason.
Worked examplePerformance Security and pre-COD Early Termination Amount at three project sizes, Tender 10’s proforma CISABoth amounts grow with export capacity up to 200 MW, where they reach the AUD 4,000,000 cap. A 400 MW project posts, and on termination before COD would owe, the same AUD 4,000,000 as a 200 MW one: AUD 10,000 per MW instead of AUD 20,000.Show the calculationHide the calculation
| Performance Security and pre-COD Early Termination Amount, per MW of Export Capacity | AUD 20,0002 |
|---|---|
| Maximum amount | AUD 4,000,0002 |
| Export Capacity, small project | 50 MW |
|---|---|
| Export Capacity, medium project | 200 MW |
| Export Capacity, large project | 400 MW |
| Step | Calculation | Result |
|---|---|---|
| Small project | 50 MW × AUD 20,000 per MW | AUD 1,000,000 |
| Medium project | 200 MW × AUD 20,000 per MW, equal to the cap | AUD 4,000,000 |
| Large project | 400 MW × AUD 20,000 per MW = AUD 8,000,000, capped | AUD 4,000,000 |
| Large project, per MW of Export Capacity | AUD 4,000,000 ÷ 400 MW | AUD 10,000 |
Result. Both amounts grow with export capacity up to 200 MW, where they reach the AUD 4,000,000 cap. A 400 MW project posts, and on termination before COD would owe, the same AUD 4,000,000 as a 200 MW one: AUD 10,000 per MW instead of AUD 20,000.
MC4, First Nations participation and benefits sharing, and MC5, social outcomes and community benefits sharing, carried 12.5% of the merit score each. Once a selected proponent signs, the commitments behind those scores become Social Licence Commitments in the CISA, with reporting, cure plans, abatements and termination for a failed cure plan.1, 2, 3 A termination they lead to before commercial operation carries the same Early Termination Amount.
The time to test whether the project can be financed on the terms it bid is therefore before the CISA is signed: until then, a selected developer that walks away risks a record that may be weighed in later CIS tenders; afterwards, failing to reach Financial Close costs up to AUD 4,000,000.
A late start shortens the support
Projects were to show a credible pathway to commercial operations by ; under MC2, project deliverability and timeline, earlier credible dates score higher, and a later COD Target Date (COD: the commercial operations date), or no credible pathway, “may be considered low merit and not further assessed”.1 The COD Sunset Date “must be 12 months after the COD Target Date as bid”; missing it lets the Commonwealth terminate, unless a COD cure plan it requested is pending, or approved and followed. The support clock hangs on that bid date: the Support Period starts at commercial operation or at the Final Support Commencement Date, whichever comes first, and that date is the COD Sunset Date as bid, which “cannot be extended under this agreement (even if the COD Sunset Date is extended by reason of Force Majeure)”. The support term, at most 15 years, is counted from that start.2
So a project that commissions after its COD Sunset Date as bid, under an extension or a cure plan, starts its support term on that date anyway, and each month beyond it comes off its years of support. An earlier COD Target Date scores better under MC2 if it is credible, but it also brings forward the date from which the Commonwealth may terminate and the latest start of the support term.
If Tender 10 is the last dispatchable round
Tender 8, the previous NEM dispatchable round, had the same 4 GW / 16 GWh target, drew 73 bids for 76.4 GWh and selected 15 projects of 4.2 GW / 16.1 GWh, so most of the 76.4 GWh bid went unselected. By our arithmetic, its bids offered 4.8 times its target volume.5
Tender 10’s Guidelines call it likely to be the final NEM dispatchable tender under the CIS if its targets are met, and as of DCCEEW’s scheme page, last updated on , listed a proposed Tender 13 for NEM dispatchable capacity only “if required”. If Tender 10 meets the remaining dispatchable targets, that page says, the proposed Tender 13 will not be needed.1, 4, 6 For bids not selected, the Guidelines provide a Reserve List: the Government may place proponents on it for a stated period and, within that period and the bid’s Validity Period, make one a successful proponent, still bound by its bid. If Tender 10 does meet those targets, a place on its Reserve List, still bound by the bid, would be the last route to a CIS dispatchable contract in the NEM in the scheme’s published plans.1
For bid security and entity rules in another storage tender, see reading a storage tender from the back; the battery storage guide sets other routes by which batteries are bought beside each other.
Sources (6)
- 1
Department of Climate Change, Energy, the Environment and Water (DCCEEW), published by ASL: Capacity Investment Scheme Tender 10, National Electricity Market, Dispatchable Capacity, Tender Guidelines · Tier 1 · official · Verified
Where in the document
Dated on the cover; ASL lists it under ; printed page numbers are the PDF page numbers. “What to know for CIS Tender 10” (p. iii); Table 1 (pp. iii–v); Table 2 (p. vi); Table 3, “Important Dates”, and its note (p. vii); section 1.1, including “Jurisdictional Allocations” and Table 4 (pp. 11–12); Table 5, key commercial terms (p. 13); Table 7, EC1, EC2, EC5, EC7, EC9 and EC10 (pp. 15–17); Table 8 (pp. 18–20); section 3 and Table 9 (p. 21); section 3.1, Merit Criterion 1 (p. 22); Merit Criterion 2 (p. 24); section 4.1 (p. 36); section 4.4 and Table 10 (pp. 38–40); section 4.7 (pp. 41–42); section 5.3.2 (p. 46); section 5.5 (p. 48); section 6.27 (p. 70); Glossary, “Validity Period” (p. 91). No addendum is listed on ASL’s tender page; dates are changed through the Online Portal (Table 3 note) and addenda under section 6.36 (p. 74). Clarifications and notices checked: Q&A Responses, releases 1 to 15, of (Q&A 6, 19 and 29 confirm the cited rules; none changes them); Notice of update to Bid Form, of (a mandatory Registered Capacity field; ASL says the Guidelines, the assessment and the deadline are unchanged). The information pack of holds byte-identical copies of the tender documents. Section 3.1, Merit Criterion 3, “Development funding” (p. 26); section 5.4, “Recommended Bids” (p. 47); section 5.5.1, “Reserve List” (p. 48); section 6.22, “Withdrawal of Bid” (p. 67).
- 2
DCCEEW, published by ASL: Proforma Capacity Investment Scheme Agreement (CISA), CIS Tender 10, NEM Dispatchable Capacity · Tier 1 · official · Verified
Where in the document
The document carries no date; its notice refers to Tender Guidelines issued on , and ASL lists it under that date. Reference Details, items 17 (Final Support End Date, up to 15 years), 18 (Milestones and Milestone Dates), 19 (FC Sunset Date), 21 (COD Sunset Date, with its note), 22 to 24 (Annual Floor, Annual Ceiling, Annual Payment Cap) and 25 (Performance Security Amount); clause 1.1, definitions of Revenue Floor Support Percentage (90%), Revenue Ceiling Sharing Percentage (50%), Performance Security and Acceptable Credit Rating; clause 1.2 (“$” is the currency of Australia); clause 3.1; clauses 5.3 and 5.4(a) to (c); clauses 7.4 and 7.5; clauses 11.4 to 11.6. Clarifications checked: Q&A Responses, releases 1 to 15, of (Q&A 12 and 33 on Schedule 2A; Q&A 27 and 31 announce drafting fixes at contract finalisation, to clauses not cited). The Proforma CISA for Aggregated Projects sets the same Performance Security Amount (Reference Details, item 25). Reference Details, item 16 (Final Support Commencement Date, with its note) and the note to item 17; clause 1.1, definitions of Support Period, Support Start Date and Support Year; clause 3.3(a)(i); clauses 22.1 and 22.5(a); Schedule 5, “Early Termination Amount”, before COD, and its note.
- 3
DCCEEW, published by ASL: CIS Tender 10, NEM Dispatchable Capacity, Q&A Responses, releases 1 to 15 · Tier 1 · official · Verified
Where in the document
Version table (p. i): releases 1 to 15, the last of . Q&A 6, release 5 (PDF p. 6): no indexation or escalation of Bid Variables, and no term beyond 15 years. Q&A 12, release 8 (PDF p. 11), and Q&A 33, release 14 (PDF p. 22): the MC4 and MC5 commitments become the Schedule 2A Social Licence Commitments. Q&A 19, release 11 (PDF pp. 15–16): the 2-hour test is on Registered Capacity; the MC1 Returnable Schedule guide note was an error. Q&A 29, release 13 (PDF p. 21): no exemptions, extensions or alternative avenues for EC10.
- 4
AusEnergy Services Limited (ASL): CIS Tender 10, NEM Dispatchable Capacity, tender page · Tier 1 · official · Verified
Where in the document
Page last updated . The timeline at the top of the page (registration, questions and bid closing dates; “Announce Successful Bids”); headings “At a glance” and “Overview” (the target and the sentence on the final tender); heading “Important Information”, the notice of update to the Bid Form of ; the Tender Documents tab (the documents and their listing dates) and the Tender Q&A tab (the Q&A Responses of ).
- 5
Department of Climate Change, Energy, the Environment and Water (DCCEEW): Open CIS tenders · Tier 1 · official · Verified
Where in the document
Page last updated . The second “Tenders” table (single-stage bids): row “Tender 8 – NEM dispatchable” (target, bids, GWh bid, successful projects with their GW and GWh) and row “Tender 10 – NEM dispatchable” (bids closed ; the indicative result months quoted in the piece). “Tenders overview” (the CIS tenders in progress).
- 6
Department of Climate Change, Energy, the Environment and Water (DCCEEW): Capacity Investment Scheme · Tier 1 · official · Verified
Where in the document
Page last updated . The section on the tenders proposed to commence that year: the table “Proposed tender rounds” (tenders 9 to 13, system, technology, indicative opening and announcement months), its row “13 (if required)*” and the note under the table on Tender 10 and Tender 13. The same table’s indicative announcement month for Tender 10 is older than the one on DCCEEW’s Open CIS tenders page (S-102, last updated ) (X-024). Read by a plain request on (HTTP 200); the site does not answer curl.
ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work
How to cite
ListingMinds, “Australia’s CIS Tender 10: the revenue floor you bid is the one you sign”, . https://www.listingminds.com/energy/field-notes/australia-capacity-investment-scheme-tender-10