Capacity and flexibility · Programme
PJM’s capacity auction: a battery’s shortfall charges can exceed its capacity payments
A battery clearing PJM’s capacity auction is paid the clearing price and must deliver as PJM schedules or dispatches it whenever its zone is under a declared Emergency Action. Unless an exemption applies, shortfalls are charged at a rate set by Net CONE, and in a bad year can exceed what the auction pays.
ListingMinds · Published and updated · Sources verified
Geography: United States · Procurement rounds covered: US PJM BRA 2029/30, not yet open
On this page
PJM’s report on its base residual auction for 2028/2029 shows every megawatt of battery and hybrid capacity offered as cleared: 478.3 MW of unforced capacity, counting commitments under PJM’s Fixed Resource Requirement alternative, against 205 MW the year before. PJM announced on that the auction had cleared at its temporary price cap of $325/MW-day, 6,831 MW short of the reliability requirement. For batteries, clearing was not the hard part; what clearing commits them to is.1, 2
PJM’s capacity market is built on one product, Capacity Performance, and a resource that clears as Capacity Performance is paid a daily auction credit: the megawatts it cleared times its area’s clearing price, for every day of the delivery year. In return, PJM’s tariff obliges it to deliver energy, as PJM schedules or dispatches it, in every Performance Assessment Interval of that year (each five-minute interval for which PJM has declared an Emergency Action), and charges it for a shortfall unless an exemption applies; storage is among the resource types that may offer on these terms. The charge is not built on the clearing price but on the net cost of new entry, Net CONE: the cost of new entry less an offset for net energy and ancillary services revenue, in installed-capacity terms. Only the yearly cap on the charges is tied to the clearing price. For a battery whose committed capacity all cleared in the base auction, that cap is one and a half times its year of capacity payments: in a bad year it can be charged more than the auction paid it.3, 4
As of , PJM’s schedule gives the next base residual auction, for 2029/2030, an offer window from to , with results to be posted on . How much a battery can offer into it is settled before the price; what follows is what it takes on once it clears.5
Paid and assessed on the same megawatts
Accreditation caps what a battery can commit: no resource rated by effective load carrying capability (ELCC), which sets accredited capacity from 2028/2029, may offer more than its accredited unforced capacity.3 As of , PJM’s class rating for four-hour storage in the 2029/2030 auction is 57%; its file says the ratings will be applied to that auction, while its schedule lists the item as preliminary.5, 6 The capacity it commits is then both what it is paid on and what PJM measures it against.
In each Performance Assessment Interval, PJM expects a battery to deliver its committed unforced capacity times a balancing ratio, never above 1.0: the actual performance of all generation and storage in the interval (with net energy imports and some demand-side bonus performance), divided by all the generation and storage capacity committed. The shortfall is calculated over the resources located in the area of the Emergency Action. What counts as delivered is the energy the battery puts into PJM’s system plus any real-time reserve or regulation assignment it holds; expected minus delivered is the shortfall, and a negative result means there is none. So the battery answers for the megawatts it committed, not its nameplate, and a battery that PJM assigns to reserves is not counted as idle.4
Every five minutes of a declared Emergency Action is assessed
Manual 18 sets two conditions that trigger a Performance Assessment Interval, each for the reserve zone or sub-zone concerned. The first is a shortage of primary reserves together with one of four listed procedures: a voltage reduction warning with a reduction of non-critical plant load, or with curtailment of non-essential building load, a manual load dump warning, or a maximum emergency generation action. The second is an order to deploy all resources, reduce voltage, dump load manually or shed load. The condition must hold for the whole interval, and Capacity Performance commitments are exposed to non-performance charges throughout the delivery year.3
The tariff excuses a shortfall only to the extent the resource was unavailable solely because it was on a planned or maintenance outage PJM had approved, was not scheduled by PJM, or was online but scheduled down by PJM for economic dispatch. A shortfall still counts where the resource was needed and would have been scheduled, but was not scheduled or was scheduled down solely because of operating limits in its own offer, or because its market-based offer was higher than its cost-based one.4 None of these grounds mentions a battery’s state of charge, and each interval is assessed on its own. Manual 18 counts every Capacity Storage Resource as a limited duration resource: a generation capacity resource, other than a variable or combination resource, that cannot run continuously at full output for 24 hours or longer. For such a resource, how long it can hold its expected output through a long emergency is a pricing question, not only an operating one.3
An hourly rate set by Net CONE, a yearly cap set by the price
The charge for an interval is the shortfall in megawatts times the tariff’s Non-Performance Charge Rate. That rate is Net CONE for the area and delivery year, times the days in the delivery year divided by 30, divided by the number of settlement intervals in an hour.4 Manual 18 takes the area’s Net CONE only through 2025/2026 and the RTO’s, for PJM’s region as a whole, after that; its revision 63 lists the change as “fixed rate to reflect RTO instead of LDA net CONE from previous tariff change”, while the tariff text as posted names the area’s Net CONE. For a battery in an area whose Net CONE differs from the RTO’s, the two texts give different rates for the same shortfall.3, 4
By our arithmetic, an hour in which a battery is one megawatt short costs a thirtieth of a year’s Net CONE for that megawatt, so thirty such hours in a delivery year cost as much as a full year of Net CONE.
Manual 18 calls the cap the stop-loss: a Capacity Performance resource’s non-performance and non-curtailment charges for a delivery year may not exceed 1.5 times the base residual auction’s clearing price for its area, times its committed unforced capacity (the most committed up to the end of the month of the event), times the days in the delivery year. Because the hourly charge is set by Net CONE and the cap by the clearing price, the lower the clearing price stands against Net CONE, the fewer hours of shortfall it takes to reach the cap.3, 4
The money collected in an interval goes to whoever delivered more than expected in it, capacity resource or not, in proportion to each one’s extra performance, counted only up to the level PJM scheduled it at. A bonus credit is not income to count on: it exists only when others fall short, and its size is what they are charged.3, 4
A late battery can be charged from the first day of its delivery year
The obligation does not wait for an emergency: PJM checks every day of the delivery year that a committed resource can still deliver at least the unforced capacity it committed. A resource can fall short because a planned project is cancelled or delayed and has not started interconnection service by the start of the delivery year, because it is derated or retired, or because its final accredited factor gives it fewer unforced megawatts than it cleared. Each day short is charged at a daily deficiency rate: the resource’s weighted average clearing price for the part of the shortage caused by a lower accredited factor, and that price plus the higher of a fifth of it or $20/MW-day for the rest. Revision 63 of Manual 18, effective , lists the charge for a derate caused by a lower final accredited factor as a new penalty. For a battery still under construction, the start date is part of the bid: one that has not started interconnection service when its delivery year begins can be short from the first day, and each day it is short is charged.3
Where daily shortfalls on a Capacity Performance commitment and non-performance charges fall in the same continuous period, Manual 18 charges the greater of the two totals for that period, and what is billed for it may not exceed that greater total. Outside such an overlap, the daily deficiency charge stands on its own: the stop-loss limits only non-performance and non-curtailment charges.3
The duty to offer outlasts the first auction
Under Manual 18, a planned battery may be offered only after a binding notice of intent, due for 2029/2030 on under PJM’s schedule, and must then be offered, even by a different seller, or it may not offer into later auctions for that delivery year.3, 5 The tariff requires every existing generation capacity resource in the PJM region that is capable, or can reasonably become capable, of qualifying as Capacity Performance to be offered as such in every auction for every delivery year, less any excepted amount; it exempted Capacity Storage Resources from this only through 2025/2026, and from 2026/2027 only demand resources keep the exemption.4 Read with Manual 18’s definition of a storage resource as a generation capacity resource, the end of that exemption brings a built battery that is capable of qualifying as Capacity Performance under the same duty in later auctions. Manual 18 allows exceptions on stated grounds only, among them a resource reasonably expected to be physically unable to meet the Capacity Performance requirements by the start of the delivery year, and a request is due no later than 120 days before the auction’s offer window opens.3
Where the 2029/2030 auction stands
PJM must give its decision on a request to offer as Capacity Performance no later than 65 days before the offer period opens, and rejects one if the seller cannot show the resource can reasonably be expected to meet the obligations by the delivery year. Counted back from , that point and the 120-day deadline for must-offer exceptions had both passed as of , as had the notice of intent due on .4
On , FERC rejected all but two parts of PJM’s large-load proposal of , its Interim Resource Adequacy Service (IRAS) filing, including the rules that would have taken certain new large loads out of the 2029/2030 demand curve, PJM’s Variable Resource Requirement (VRR) curve. It accepted only the proposed definition of large load and a large-load registry, effective .9 As of , PJM’s planning parameters still make the curves’ points subject to adjustment pending FERC’s acceptance of the IRAS filing, with updated curves that would be posted 30 days before the auction in accordance with PJM’s IRAS proposal, and PJM’s capacity market page lists no updated curves.7, 8, 10
As of , the posted price cap for 2029/2030 is $337.83/MW-day in unforced-capacity terms, against the temporary cap of $325/MW-day at which the 2028/2029 auction cleared; PJM attributes the rise to its reference resource’s UCAP factor changing from 79% to 76%.2, 7, 8 Because the battery’s payment and its stop-loss are both set by the clearing price, an auction that clears at the higher cap also raises the most a battery can be charged in non-performance charges for the same committed capacity.
Checklist
- The accredited capacity PJM will give the battery for the delivery year, which caps what it can commit, and so what it can be paid on and measured against
- How many hours of shortfall at its expected clearing price would take the battery to the stop-loss
- Which Net CONE PJM will apply to the hourly charge: the area’s under the tariff as posted, or the RTO’s under PJM’s capacity market manual
- The revision of PJM Manual 18 in force when the offer is made: revision 63 took effect on
Sources (10)
- 1
PJM Interconnection: 2028/2029 Base Residual Auction Report, · Tier 1 · official · Verified
Where in the document
Printed page numbers (“n | P a g e”). Cover (July 14, 2026); p. 12, Table 6 “Offered and Cleared MWs by Type for RPM and Committed FRR for Previous BRAs”, row Battery/Hybrid, and the note under the table (BRA plus FRR Capacity Plan UCAP). Read, not used on the page: Executive Summary, pp. 3–4 (all prices cleared at the cap of $325.00; 149,181.6 MW UCAP procured, 6,831.3 MW below the RTO Reliability Requirement), the result the page states through FERC’s order (C-600). Later versions checked: PJM’s Capacity Market page, read on , still lists this report for 2028/2029.
- 2
Federal Energy Regulatory Commission (FERC): Order Accepting Reliability Backstop Procurement and Establishing Further Procedures, Docket Nos. ER26-3380-000 and EL26-108-000, 196 FERC ¶ 61,245, (copy on PJM’s tariff site) · Tier 1 · official · Verified
Where in the document
Printed order pages. P. -6- (PJM’s announcement of on the 2028/2029 BRA, at the temporary price cap of $325/MW-day); p. -7- and p. -21- (the 6,831 MW shortfall). Read, not used on the page: p. -1- (the Reliability Backstop Procurement, accepted for filing and suspended for five months, effective , subject to refund; a paper hearing).
- 3
PJM Interconnection: Manual 18, PJM Capacity Market, Revision 63, effective · Tier 1 · official · Verified
Where in the document
Printed page numbers, which match the page footers (Revision 63, effective ). Current Revision, pp. 7–8 (the new penalty for a derate caused by a lower final Accredited UCAP factor, §9.1.3; the §9.1.10 rate fixed to the RTO Net CONE); §1.1, p. 14 (the Capacity Performance product type); §4.2.3.1, pp. 63–64 (binding notice of intent); §4.2.7, pp. 66–67 (Accredited UCAP, ELCC Resources); §5.4.1, p. 122 (ELCC offer limits; must-offer exceptions, due 120 days before the offer window); §8.2 and §8.2.1, p. 173 (daily commitment compliance); §8.4A, pp. 178–183 (Performance Assessment Interval triggers; the rate on the RTO Net CONE after 2025/2026, p. 182; the stop-loss, p. 182; bonus credits, pp. 182–183); §9.1.3, pp. 198–199 (Daily Deficiency Rate; the greater of the deficiency and non-performance charges); §9.1.10, p. 204 (stop-loss); §9.3.1, pp. 205–206 (Daily Auction Credit); Attachment A, p. 244 (Limited Duration Resource). §4.8, p. 100, says the Operating Agreement and Tariff govern in a conflict with the RPM credit rules; the rate’s Net CONE is stated side by side with the tariff (C-1194, C-1195). Re-read : identical (SHA-256) to the copies of and .
- 4
PJM Interconnection: Open Access Transmission Tariff, consolidated tariff (PDF), as posted on · Tier 1 · official · Verified
Where in the document
PDF page numbers of the consolidated file (6,605 pages); each tariff record shows its own effective date and docket in its footer. Definitions: p. 48 (Capacity Storage Resource; record effective 2/2/2026, ER26-284-000); p. 99 (Net Cost of New Entry); p. 111 (Performance Assessment Interval; record effective 4/1/2026, ER26-846-001); p. 121 (Real-time Settlement Interval, every five minutes; record effective 10/1/2026, ER26-2446-000). Attachment DD §5.5A(a) and (a)(i)B, p. 6160 (record effective 6/27/2026, ER26-2319-000); §6.6(a), p. 6234 (record effective 2/18/2025, ER25-682-000); §6.6A(a) and (c), p. 6242 (record effective 2/2/2026, ER26-284-000); §10A(b) and (c), pp. 6267–6270 (under §10A(c), the area defined by the Emergency Action, p. 6270); §10A(d), p. 6270; §10A(e) and (f-1), pp. 6270–6271; §10A(g), pp. 6271–6272 (the §10A record effective 6/27/2026, ER26-2319-000). Read side by side: §10A(e) sets the rate on the Net Cost of New Entry “for the LDA and Delivery Year”, while Manual 18 Revision 63 uses the RTO Net CONE after 2025/2026 (C-1195); the page states both and calculates with neither. Re-read : PJM re-posted the file that day (PDF creation date ); the text of every page cited here, footers included, is identical to the file posted on .
- 5
PJM Interconnection: RPM Auction Schedule (spreadsheet), sheet “29-30 BRA Post” · Tier 1 · official · Verified
Where in the document
Sheet “29-30 BRA Post”: rows 3–5 (all auctions open at 12:01 AM EPT and close at 5:00 PM EPT; results posted no earlier than 4:00 PM EPT); row 6 (the OATT governs in any conflict with the timeline); row 11 (notice of intent for Planned Generation Capacity Resources, ); row 24 (“Preliminary ELCC Class Rating and Accredited UCAP Factors”, ); rows 59–61 (window opens , closes , results ). Dates are spreadsheet date values read as calendar dates. Re-read : the same file (identical SHA-256) as the copies of , and .
- 6
PJM Interconnection: ELCC Class Ratings for the 2029/2030 Base Residual Auction · Tier 1 · official · Verified
Where in the document
P. 1: the table (“will be applied to the 2029/2030 Base Residual Auction”), rows 4-hr Storage 57%, 6-hr 66%, 8-hr 69% and 10-hr 76%. The document shows no date; PJM’s ELCC page lists it as dated ; PJM’s schedule (S-186, row 24) calls the item of “Preliminary ELCC Class Rating and Accredited UCAP Factors”, and the page states both. Re-read : identical (SHA-256) to the copies of and .
- 7
PJM Interconnection: 2029/2030 RPM Base Residual Auction Planning Period Parameters, report of · Tier 1 · official · Verified
Where in the document
Printed page numbers (PDF page = printed page + 3). Summary, fifth bullet (p. 1) and “Variable Resource Requirement Curves” (p. 4): the 2029/2030 price cap and floor for the RTO and each LDA, and the change of the Reference Resource’s UCAP factor from 79% to 76%; Summary, last bullet (p. 1) and p. 4: the VRR curve points subject to adjustment pending FERC’s decision on the IRAS filing, with updated curves 30 days before the auction. Re-read and : identical to the copy of ; PJM’s capacity market page lists no later report.
- 8
PJM Interconnection: 2029/2030 RPM Base Residual Auction Planning Parameters (spreadsheet), initial posting , updated · Tier 1 · official · Verified
Where in the document
Sheet “Planning Parameters”: cell D1 (); rows 6 and 9–10 (Reference Resource AUCAP factor 0.76; cap 256.75 and floor 138.25 $/MW-day ICAP); rows 22–25 (337.83 and 181.91 $/MW-day UCAP in every column); row 48 (the VRR curve points subject to adjustment pending FERC acceptance of the IRAS filing; updated curves 30 days before the auction); rows 108–109 (the postings of 8/31/2026 and 9/1/2026). Re-read and : identical to the copy of . Amendment checked: the 9/1/2026 update (PJM WEST CONE calculation) changed only the PJM WEST CONE calculation (row 109); no value used here depends on it.
- 9
Federal Energy Regulatory Commission (FERC): Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, Docket No. ER26-3515-000, 197 FERC ¶ 61,019, (copy on PJM’s tariff site) · Tier 1 · official · Verified
Where in the document
Printed order pages (“-n-”); 57 pages. P. -1-, P 1 (PJM’s filing of : a definition of Large Load, a Large Load Registry, Interim Resource Adequacy Service, a requirement for LSEs serving New Large Load to designate new capacity, rules for Bring Your Own New Capacity arrangements, and rules to exclude Eligible New Large Load from the VRR curve beginning with Delivery Year 2029/2030) and P 2 (the definition and the registry accepted, effective , as requested; a compliance filing within 30 days; the remaining revisions rejected); p. -3-, P 4 (PJM had asked for the whole filing to take effect on so that it could modify the planning parameters for the VRR curve underlying the 2029/2030 BRA); p. -6-, P 15 (the remaining elements, among them the VRR exclusion, rejected as inextricably linked to IRAS and BYONC); p. -24-, P 55 (the VRR exclusion as proposed); p. -50-, ordering paragraphs (A) and (B). The order decides the filing that S-194 and C-585 record as a proposal.
- 10
PJM Interconnection: Capacity Market (RPM) page, as read on · Tier 1 · official · Verified
Where in the document
A web page, read with a plain request (HTTP 200). The postings under the heading Delivery Years, section 2029/2030: the planning parameters spreadsheet (9.1.2026) and report (9.3.2026), the RPM Existing Resource List (8.27.2026), the Transitional System Capability Study Results BRA (9.10.2026), the Default New Entry MOPR Offer Prices (9.22.2026), the Default Gross ACR Values for MOPR and MSOC Purposes (7.10.2026) and the Aggregate Resource Request Form (10.6.2026); no updated VRR curves and no final FRR update. Its visible text is identical to the copy read on (G2-D08); extract of in reports/phase2-run-a/G2/.
ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work
How to cite
ListingMinds, “PJM’s capacity auction: a battery’s shortfall charges can exceed its capacity payments”, . https://www.listingminds.com/energy/field-notes/pjm-capacity-auction-obligations-and-penalties