Roads, bridges and tunnels · Field note

To bid on Germany’s motorway bridges, recent references count more than size

Germany plans to modernise 4,000 bridges on heavily used motorways within ten years; two Autobahn GmbH notices each let one self-contained job, outside any framework. Entry turned on recent references of named kinds and, in Bonn, on proof of having built a bridge faster than its client’s design allowed.

ListingMinds · Published and updated · Sources verified

Geography: Germany, Netherlands · Procurement rounds covered: DE A565 Bonn-Nord approach bridge replacement, first part-structure (design and build); DE A1 replacement of three bridges (VE 1: K147, K268, K276), all closed

On this page

Germany plans to modernise 4,000 bridges on a core network of heavily used motorways within ten years, but the two notices read here from Die Autobahn GmbH des Bundes, the company that runs the federal motorways, each let a self-contained job: three bridges on the A1, and the first part-structure of one approach bridge in Bonn. Neither was a call-off from a framework agreement. What decided who could take part was the evidence each notice demanded: construction references of named kinds from a recent window and, in Bonn, proof of having built a bridge faster than its client’s own design allowed.1, 2, 3, 4, 5

Autobahn GmbH says it gives priority to bridges by their place in the modernisation network and to structures that no longer fully meet the state of the art, and that it aims, where possible, to carry out bridge projects in whole route sections, to keep the intervention in traffic down. The two notices here, one in an open procedure and one in a negotiated procedure, are examples of how that work reaches the market, not a sample of it.2, 4, 5

On the A1, the gate is five years of named kinds of job

The A1 notice, published on by the company’s Westphalia branch, covered the replacement of three bridges carrying county roads, with their demolition and the adjoining road works, in an open procedure decided on price alone, with tenders due on . Each bidder needed references from the last five completed calendar years: at least three in demolition, recycling and disposal, one for a replacement or new bridge with spans over 20.0 m built while motorway traffic kept flowing, and one for a bridge built with precast elements. One reference could count for more than one category, and turnover from comparable work over the last three completed financial years had to be declared, with no minimum stated in the notice. Firms on the construction industry’s prequalification list could prove their suitability through their entry, adding references where the listed ones fell short; others filed a self-declaration as interim proof.4

Three tenders came in, and the contract, concluded on , went to three firms bidding jointly; the award notice does not publish the value.6 What screens a bidder out here is a missing kind of job in a recent window, not its size.

In Bonn, speed is scored twice

Bonn’s northern Rhine bridge, which carried more than 100,000 vehicles a day, was closed on after investigations found structural damage to its load-bearing structure, and on the federal transport ministry reported Autobahn GmbH’s finding that the approach bridge could not be run under traffic and a new structure had to be built. Demolition of the roughly 660 m approach bridge had begun a few weeks before Autobahn GmbH announced the replacement tender on , aiming to award it before Christmas 2026.3, 7

The notice of runs a negotiated procedure with a call for competition for one contract of 22 months covering design and construction together, and Autobahn GmbH says the new bridge is to take at most two years to build. The contract is for the first part-structure: a motorway bridge usually has two, one for each carriageway. As of , Autobahn GmbH counts about 28,000 part-structures on its network of about 13,200 km. The notice invites exactly three candidates to tender, and requests to participate closed on .1, 2, 3, 5, 8

To qualify at all, an applicant needed, from the last ten years, a reference for a road bridge of at least 100 m in steel, steel-composite or prestressed concrete, precast methods included, on a federal trunk road or an equivalent road. It also needed a bridge with spans over 35 m on a dual carriageway that it had built in less time than the client’s own design for that bridge allowed, with the saving shown in months or per cent. Because the contract includes the design, it needed two design references as well, from a design office, for structures of at least 100 m designed in BIM. Missing any of these excluded the request; if more than three applicants qualified, the criteria were assessed to pick the three, under a separate weighting document.5 Autobahn GmbH said fast building weighs considerably in assessing those references, above all proof of shorter construction times, for example through innovative methods, prefabrication or accelerated sequences. Firms that had shown in comparable projects that they could modernise bridges quickly, it said, stood a markedly better chance of reaching the negotiations.3

At award, a shorter completion period carries 30% of the score, as much as price; the construction and logistics concept takes 20%, and the level of the bidder’s mark-ups for overheads, risk and profit, a second cost criterion, the remaining 20%. The notice also reserves the client’s right to award on the initial tenders without further negotiation.5 A contractor without a documented time saving on a comparable bridge could not be shortlisted at all, and at award its programme counts for as much as the price line, with the mark-ups adding a further 20% on cost.

What the two notices asked bidders to prove, as each notice set it out
RequirementA1, three bridgesA565, Bonn approach bridge
ProcedureOpen procedure; variants not allowedNegotiated procedure with a call for competition; exactly 3 candidates invited to tender
ReferencesFrom the last 5 completed calendar years: at least 3 in demolition, recycling and disposal; 1 replacement or new bridge with spans over 20.0 m, built while motorway traffic kept flowing; 1 bridge built with precast elementsFrom the last 10 years: at least 1 road bridge of at least 100 m in steel, steel-composite or prestressed concrete, precast methods included; at least 1 bridge with spans over 35 m on a dual carriageway, built in less time than the client’s design for it allowed; at least 2 design references from a design office, for structures of at least 100 m designed in BIM
Other evidencePrequalification in demolition, recycling and disposal, or a self-declaration, also for planned subcontractors; on request, permits under the Explosives Act and a qualified person for ordnance clearancePrequalification in shoring, concrete, steel-composite, corrosion protection and asphalt layers, or self-declarations, also for planned subcontractors
TurnoverTurnover from comparable work declared for the last 3 completed financial years, including the share of jobs carried out jointly; no minimum statedTurnover from comparable work declared for the last 3 completed financial years, including the share of jobs carried out jointly; no minimum stated
AwardPrice 100%Price 30%; shorter completion period 30%; construction and logistics concept 20%; mark-ups for overheads, risk and profit, a second cost criterion, 20%

Source: Autobahn GmbH’s contract notices for the three A1 bridges and for the first part-structure of the Bonn-Nord approach bridge, on TED.4, 5

Autobahn GmbH’s bridge competence centre, which coordinates the programme’s planning and steering with the branches, says it gives impetus to, for example, fast building with precast construction and a high degree of prefabrication, to keep interventions in traffic to a minimum.2 The A1 notice made precast experience a reference a bidder had to hold; Bonn’s accepted precast bridges as references and, through its time-saving criterion, rewarded the speed the method is meant to deliver.

Bonn’s turnover declaration counted a firm’s share of comparable contracts carried out jointly with other companies, and its self-declarations extended to planned subcontractors.5 What these notices test, then, is the reference file a bidder brings, alone or as a group: construction jobs of the named kinds, a documented time saving and, for design and build, a design office with references of its own.

The money is earmarked; most of it is not listed by project

Autobahn GmbH’s financing and implementation plan for 2025 to 2029, as at , shows €2.5 billion a year from the federal special fund for infrastructure and climate neutrality, to be used only to maintain bridges and tunnels on the existing motorway network, with resurfacing allowed where it is directly tied to that work. The figures rested on the government’s draft budgets and were subject to the final federal budget for 2025, the law creating the fund had still to be passed, and the plan warns that the budget and transport committees’ approval of it does not ensure its whole portfolio is financed. It puts maintenance, bridge modernisation above all, ahead of starting new motorway projects.9

As of , Autobahn GmbH’s page on the fund speaks of around 100 motorway modernisation projects, says the money goes both to planned repairs and replacements and to work already under way before the fund was set up, and says its overview is being added to continuously.10

The plan names maintenance projects above €50 million one by one, about €7.9 billion in all; about €17.7 billion of maintenance, in smaller projects and in the maintenance shares of other schemes, is not listed project by project, because of their number, small scale and shorter planning times.9 For that unlisted part, the larger of the two, the plan gives a bidder no project to prepare for. The two notices read here, once out, left less than a month: to tender on the A1, to apply in Bonn.

The Dutch overview shows volume, not projects

The Dutch agency Rijkswaterstaat published on an overview of the replacement and major renovation of bridges, tunnels and locks it still has to contract over five years, by year of expected tender and award and without project names. Its table, which also carries a line of €0.6 billion for 2025, all with a budget, totals €12.85 billion in expected project costs, including VAT at 2025 prices and part of Rijkswaterstaat’s own costs; €6.3 billion of it has a budget and €6.55 billion does not, and the overview calls itself a snapshot that may change. In every year of the table from the 2028 line on, the amount without a budget is larger than the funded amount.11

As of , Rijkswaterstaat’s page on major maintenance says that the cabinet’s proposed reprioritisation of all national infrastructure projects, sent to parliament on , is to be decided at the spring budget memorandum of 2027, after which Rijkswaterstaat can update its procurement planning, and that some renewal may happen later than foreseen.12 Our guide to how road authorities buy works covers Rijkswaterstaat’s procurement plans and their pause.

The two documents leave different gaps: the Dutch overview shows the volume year by year without naming a project, and more of it unfunded than funded; the German plan shows money set aside for bridges and tunnels but names maintenance projects only above €50 million, the smaller part of its planned maintenance investment.

Sources (12)

  1. 1

    Die Autobahn GmbH des Bundes: FAQ Brücken (questions and answers on bridges; undated, read ) · Tier 1 · official · Verified

    Where in the document

    German. About 28,000 bridge part-structures; about 7,000 km of heavily used transit routes with about 4,000 bridges identified, some already under way; two part-structures per bridge and replacement half by half. Located: the 28,000 part-structures, the 7,000 km and the 4,000 bridges in paragraph 2 of the answer to the question “Wie viele Brücken gibt es und wie groß ist der Modernisierungsbedarf?” (the 28,000 also in section Autobahnbrücken); the two part-structures and replacement half by half in paragraph 1 of the answer to the question “Was bedeutet es für den Verkehr, wenn Brücken ersetzt werden müssen?”. Extract: extracts/faq-bruecken.txt (one answer on construction methods omitted under the excluded-industry boundary; not used). Translation B items F2-B2, F2-B4, F2-B8.

  2. 2

    Die Autobahn GmbH des Bundes: Brückenkompetenzzentrum (bridge competence centre page; undated, read ) · Tier 1 · official · Verified

    Where in the document

    German. Network and part-structure counts; bridge modernisation network and core network (4,000 bridges in ten years); the centre’s founding year and its work with the ten branches; development impetus for precast building; main programme criteria. Located on the page: the network and part-structure counts in the section “Bedeutung der Brücken für das Autobahnnetz” (its first paragraph); the work with the ten branches in the introductory paragraph under the heading “Brückenkompetenzzentrum”; the bridge modernisation network and core network in the section “Priorisierung durch das Brückenmodernisierungsnetz”; the founding year in the section “Gründung des Brückenkompetenzzentrums”; the precast impetus in the team section “Bau”; the main programme criteria in the team section “Steuerung”. Extract: reports/away-run-d/F2/extracts/bridge-centre.txt. Translation B items F2-B1, F2-B3, F2-B5 to F2-B7.

  3. 3

    Die Autobahn GmbH des Bundes: press release, A565: Ausschreibung für den Ersatzneubau der Bonner Vorlandbrücke veröffentlicht, · Tier 1 · official · Verified

    Where in the document

    German. Tender published; negotiated procedure with a call for competition; award planned before Christmas 2026; demolition begun; about 660 m; weight of fast building in the reference assessment; functional tender; at most two years; award criteria; company boilerplate. Located: publication, the procedure type and the award before Christmas in the lead paragraph; demolition begun and the 660 m in the second paragraph; the weight of fast building in the reference assessment in the third paragraph and in the paragraph “Stufe 1 Teilnahmewettbewerb”; the award criteria (price and, above all, the construction time offered) in the paragraph “Stufe 2 Verhandlungsverfahren”; the functional tender and the two years at most in the paragraph after it; the company boilerplate in the closing paragraph. Translation B items F2-B19 to F2-B22.

  4. 4

    Die Autobahn GmbH des Bundes – NL Westfalen: contract notice 432867-2026, VE 1: Brücken - K147, K268; K276 (A1), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/432867-2026/xml. Located: the description in the section ProcurementProject (Description); the open procedure in the section TenderingProcess (ProcedureCode); no framework in the lot section TenderingProcess (ContractingSystemTypeCode none); variants in the lot section TenderingTerms (VariantConstraintCode); price 100% in the lot section AwardingTerms (AwardingCriterion); the deadline in the lot section TenderingProcess (TenderSubmissionDeadlinePeriod); references, prequalification, permits on request and turnover in the lot section TenderingTerms, SelectionCriteria (codes slc-abil-ref-work, slc-abil-staff-tech-work, slc-stand-to-spec and the other slc- entries, with their Description text). Description; open procedure; no framework; variants not allowed; price 100%; deadline; references, prequalification, permits on request, turnover. German; translation B items F2-B32 to F2-B35. SHA-256 (first 16) 8d2d9811e705cc5d.

  5. 5

    Die Autobahn GmbH des Bundes – NL Rheinland: contract notice 498083-2026, A565, Ersatzneubau 1. Teilbauwerk der Vorlandbrücke linksrheinisch der Rheinbrücke Bonn-Nord, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/498083-2026/xml (eForms; the detail page answers 202 to plain requests). Procedure, candidate limits, duration, selection criteria 1 to 3 and the PQ areas, turnover, award criteria and weights, no-negotiation indicator. Located for C-3722 (used in the piece from question 23): the first talks in calendar weeks 42 and 44 in the section ProcurementProject, element Note (its last paragraph); the reservation to award on the initial tenders without negotiation in the lot section AwardingTerms, element NoFurtherNegotiationIndicator (true). Re-read 2026-10-30 for question 23: HTTP 200, 56,073 bytes, SHA-256 first 16 ad7d480b2fbe2ffd, unchanged. The weighting document it names is not readable (T-169). Amended by Change notice 502399-2026 (TED) to contract notice 498083-2026 (T-168), read as S-1107. German; translation B items F2-B23 to F2-B30. SHA-256 (first 16) of the XML ad7d480b2fbe2ffd.

  6. 6

    Die Autobahn GmbH des Bundes – NL Westfalen: contract award notice 642216-2026, VE 1: Brücken - K147, K268; K276 (A1), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/642216-2026/xml. Located in the section NoticeResult: tenders received in LotResult/ReceivedSubmissionsStatistics (code tenders); the contract date in SettledContract/IssueDate; the group of three in TenderingParty (Tenderer entries, one GroupLeadIndicator); value not published in LotTender/LegalMonetaryTotal/PayableAmount and TotalAmount. Coded fields only: tenders received, contract date, the group of three tenderers, value not published. The winners’ names are not used. SHA-256 (first 16) a4df5c6901e6f40f.

  7. 7

    Federal Ministry of Transport (BMV): Schnelles Handeln für die Rheinbrücke Bonn-Nord, update of · Tier 1 · official · Verified

    Where in the document

    German. Closure on 3 June 2026 for structural damage; more than 100,000 vehicles a day; the approach bridge cannot be operated under traffic and must be replaced (Autobahn GmbH informing the ministry’s steering group). Located: the closure, the structural damage and the 100,000 vehicles in the section “Hintergrund” (first paragraph); the finding that the approach bridge cannot be operated under traffic, and the Autobahn GmbH informing the steering group, in the first paragraph under the heading “A565: Abriss der Bonner Vorlandbrücke und zügiger Ersatzneubau in maximal zwei Jahren” (the update dated ). Translation B items F2-B17 and F2-B18.

  8. 8

    Die Autobahn GmbH des Bundes – NL Rheinland: change notice 502399-2026 to contract notice 498083-2026 (A565 Bonn-Nord approach bridge), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/502399-2026/xml. Located: the reason in the section Changes, element ChangeReason/ReasonDescription; the new deadline in the lot section, element TenderingProcess/ParticipationRequestReceptionPeriod; multiple tenders in the lot section, element TenderingTerms/MultipleTendersCode (not-allowed). Change reason and description (deadline moved to 18.08.2026, 10:00); multiple tenders now not allowed. German; translation B item F2-B31. SHA-256 (first 16) a7d02e282c675ca8.

  9. 9

    Die Autobahn GmbH des Bundes: Finanzierungs- und Realisierungsplan (FRP) 2025–2029, as at (PDF, linked from https://www.autobahn.de/planen-bauen/finanzierungs-und-realisierungsplaene) · Tier 1 · official · Verified

    Where in the document

    German. Funding table (Einzelplan 60, Kapitel 6093, Titel 891 51) and its note; the special fund’s restriction; basis in the draft budgets and the reservation of the final 2025 budget; footnote on the fund law; committee approval not ensuring financing; maintenance totals (about €25.6 billion; projects above €50 million about €7.9 billion; about €17.7 billion not listed individually); priority of maintenance. SHA-256 (first 16) b418e3dceee29d68, identical to the origin pack’s stored copy. Unit of the funding table: headed “in Mio. €”, but its lines add up to the total of the next table, headed “in T€”, which the text calls “rund 37,7 Mrd. Euro”: thousand euros. Lines of the plan outside bridges and tunnels not used. Translation B items F2-B9 to F2-B15.

  10. 10

    Die Autobahn GmbH des Bundes: Sondervermögen – rund 100 Projekte der Autobahn-Modernisierung (special fund page; undated, read ) · Tier 1 · official · Verified

    Where in the document

    German. Located: the heading “Rund 100 Projekte der Autobahn-Modernisierung” at the top of the page; the money flowing to planned and running measures in the second paragraph of the section “Sondervermögen Infrastruktur: Maßnahmen im Autobahnnetz”; the overview added to continuously in that section’s third paragraph. Heading; money flowing to planned and already running measures; overview added to continuously. Market data: re-read before publication. Translation B item F2-B16.

  11. 11

    Rijkswaterstaat: Meerjarenoverzicht vernieuwingsopgave bruggen, tunnels en sluizen 2026 - 2030 – Dealflow, published (PDF; landing page https://open.rijkswaterstaat.nl/overige-publicaties/2025/meerjarenoverzicht-vernieuwingsopgave/) · Tier 1 · official · Verified

    Where in the document

    Dutch. Introduction (scope, five years, work still to be contracted, no project names); basis of the amounts (year of tender and award, VAT included, 2025 prices, average of minimum and maximum); snapshot; the overview table by year (financed, not financed, total). Publication date: Rijkswaterstaat’s news release of (https://www.rijkswaterstaat.nl/nieuws/archief/2025/12/rijkswaterstaat-publiceert-meerjarenoverzicht-vernieuwingsopgave-bruggen-tunnels-en-sluizen, extract rws-news-20251208.txt) says the overview was published on Monday ; the publication platform’s metadata gives 2025-12-04 as the date it became available; the PDF’s colophon carries an earlier production month. The publisher’s own statement is used; the piece dates the overview . Unit: the segment tables are headed “Budget in K€ euro (1000x)” and end in the same total as the overview table. Segment tables not used. SHA-256 (first 16) 58f2fedc4bd827e6. Translation B items F2-B36 to F2-B38.

  12. 12

    Rijkswaterstaat: Groot onderhoud (major maintenance page; undated, read ) · Tier 1 · official · Verified

    Where in the document

    Dutch. Letter to parliament of 16 October 2026 on the proposed prioritisation and an extra 18 billion; decision at the spring budget memorandum of 2027, then an update of the procurement planning; work may take place later than foreseen. Re-read in revision 1 (page modified 2026-10-16, unchanged), with the cabinet’s letter of . Newer than S-1070 (modified 2026-07-20) on when the procurement planning returns: conflict X-060. Market data: re-read before publication. Translation B items F2-B39 and F2-B40.

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “To bid on Germany’s motorway bridges, recent references count more than size”, . https://www.listingminds.com/transport/field-notes/autobahn-bridge-renewal-contracts