Roads, bridges and tunnels · Sector guide

How road authorities buy works, and when a contractor’s chance is decided

Road authorities often decide who gets their work before any scheme is let: in a framework competition covering years, or an area-contract round where a firm can win only one. The Texas Department of Transportation instead lets work monthly, behind an annual prequalification capping how much of its work a firm may hold.

ListingMinds · Published and updated · Sources verified · Reviewed

Markets and rounds covered: United Kingdom, European Union, Germany, Ireland, Spain, Sweden, Netherlands, United States, Australia

On this page

Requests to participate in National Highways’ Scheme Delivery Framework 2 (SDF2), an eight-year framework to renew and maintain the existing assets of England’s strategic road network of motorways and major A roads, closed on ; the framework is expected to run from to .1 That one competition settles who can be awarded work under SDF2 for its whole term. The Texas Department of Transportation (TxDOT) opens bids for construction and maintenance contracts every month, at a statewide letting in Austin held on two consecutive days.2

Between the two sit the area and network maintenance contracts of Ireland, Spain and Sweden, each let for a fixed term. For a bid team, the question is less which scheme to chase than which gate stands in front of the work, and when it next opens.

A framework competition settles years of work

The SDF2 notice estimates the framework’s value at £14.5 billion excluding VAT over its projected eight years, and says it builds on two earlier National Highways frameworks, the Scheme Delivery Framework and the Pavement Delivery Framework.1 Under the Procurement Act 2023 a framework must include its estimated value; the Cabinet Office’s guidance explains that the estimate covers all the contracts to be awarded under it, and that payments are made under those contracts, not under the framework itself. It is an estimate of what may be ordered, not money committed to any supplier.8, 9

A framework under the Act is a contract that provides for future contracts to be awarded to the suppliers on it, through a competition among them unless the framework sets out the core terms and an objective way of choosing the supplier. SDF2 will allow both, award without further competition and a competitive selection process, with procedures that differ across its lots. The Act limits such a framework to four years unless the contracting authority considers that the nature of the works requires a longer term, in which case it must give its reasons in the notice.1, 8, 10 Among National Highways’ reasons: at its market engagement, the supply chain preferred an eight-year framework to a four- or six-year one. In the EU, Directive 2014/24/EU allows a framework agreement to run longer than four years only in exceptional cases duly justified, and contracts under it may be awarded only to the economic operators that were party to it when it was concluded.1, 11

SDF2’s 64 lots show where a specialist can enter. One national lot is for a main contractor that delivers and manages complex schemes, through its own work and subcontracts, across the scope of any other lot except design; ten kinds of work, among them pavements, structures, road markings, signs and lighting, and restraint systems, have six regional lots each; tunnels have one national lot, and technology design two regional lots. Each maximum number invited to tender applies to all the regional lots of a kind together: at most 15 suppliers can be invited across the six pavements lots and 20 across the six lots for general civils, drainage and concrete, with 10 for the main-contractor lot and 4 for tunnels. Every lot is weighted 70% on quality and 30% on price.1

A road-markings or restraint-systems firm that is not appointed to its region’s lot cannot be awarded contracts under SDF2; for work let under SDF2, the route left to it is as a subcontractor, for example to the main contractor.

A framework without a competition

Germany’s federal motorway company, Die Autobahn GmbH des Bundes, buys some planning services through an open-house framework that makes no selection, set out in a notice of . Any firm that meets the admission requirements can join it, for each area of work in which it proves them, among them road maintenance schemes, inner-city federal roads and drainage, at any time while the procedure remains open: currently until , after a one-year extension announced on . The original notice also provided for one further one-year extension, to . The notice states that this is not the award of a public contract under Directive 2014/24/EU, that the procurement review chamber is not competent to review it, and that challenges to its conditions can be taken to the administrative courts. Admission makes a firm a party, not the holder of any order: call-offs follow the arrangements set out in the framework agreement.12, 24

Area contracts come back in generations

Transport Infrastructure Ireland’s notice of for the third generation of its motorway maintenance and renewals contracts (MMaRC3G) describes its 5,306 km national road network in three regions, each with a sub-network under its own maintenance and renewals contract; TII intends to appoint three contractors, one per sub-network, and set up a fourth lot in case a fourth network is needed. TII is to shortlist up to eight applicants (a stated minimum of five if enough submissions comply, though TII may invite fewer) and invite them to tender for every lot; a tenderer can win only one. The contracts can run for up to 12 years (eight years, extendable by up to 48 months in all), and TII estimates spending under them at about €1.6 billion, saying the actual spend could likely be between €0.7 billion and €2 billion, allowing for inflation and excluding VAT.3

In Spain, the Directorate-General for Roads (Dirección General de Carreteras) put the maintenance and operation of six road sectors out to tender in a notice of , as six lots of one open procedure for services contracts estimated at €187,928,016.40 in all: a firm could bid for all six but be awarded only one. Each runs for 24 months, with extension provided for.4

Sweden’s transport administration, Trafikverket, lets basic road maintenance area by area, in open procedures and well before the work starts. Its notice for the Västerås area, published on , covers to , with an option of one or two more years, at an estimated SEK 288,000,000. The Blekinge notice of covers to , at an estimated SEK 612,000,000.5, 6

In Ireland and Spain the one-lot limit means no contractor can take a whole round, and in Ireland, Spain and Sweden alike a firm that loses an area gets no second chance at that contract while it runs, up to 12 years in Ireland. The model can also end: Main Roads Western Australia says its move to in-house delivery of road maintenance and some minor capital work is complete, and lists the transitions of its maintenance contracts as complete on dates from to .13

Monthly lettings: the gate is the balance sheet

TxDOT’s letting is the official receipt and opening of bids and the naming of the apparent low bidder; its districts hold local lettings as well, and it publishes the statewide letting dates for the current and following fiscal year.2 To receive a bid proposal at all, a contractor must be prequalified, at one of three levels that each need renewing every year; the level normally used for construction requires an audited financial statement from an independent CPA firm.7

Prequalification sets a bidding capacity, the most a contractor may have under contract with TxDOT at any one time; at the level normally used for construction it is the net working capital in the contractor’s financial statement multiplied by a factor TxDOT sets. A lighter level, the bidder’s questionnaire, is for projects on which TxDOT waives the full requirements, normally smaller construction, routine maintenance, emergency and specialty projects: it needs no financial statement, but limits a contractor to $1 million of capacity unless it submits a compiled or reviewed statement. A contractor may request proposals only for projects whose engineer’s estimate does not exceed its capacity less the TxDOT work it already has under contract, and its prequalification papers must arrive at least 10 days before the letting. The monthly rhythm offers many chances to bid, but each contract won uses up capacity: a contractor near its limit cannot request proposals for a project whose estimate exceeds what is left, until its work under contract falls or its working capital grows.7

Florida writes its gate into law: contractors must be prequalified by the Florida Department of Transportation to bid for road, bridge or public transportation construction contracts above $250,000, and the annual prequalification sets their approved work classes and a maximum capacity rating; maintenance contracts need none. Neither state requires subcontractors to be prequalified: TxDOT says they must still be registered with the Texas Secretary of State and in the federal E-Verify program, and Florida requires no prequalification to bid as a subcontractor in any amount. Main Roads Western Australia uses a national gate: prequalification under Australia’s National Prequalification System is mandatory for most of its road and bridge construction contracts, whatever their value, and a contractor prequalified with another participating agency may apply for mutual recognition.7, 14, 15

On federal-aid highway contracts, federal rules limit both parts of the gate: prequalification may be a condition of bidding or award only if the time between the call for bids and the bid opening lets a bidder obtain it, and a limit on how much work a contractor may bid for or be awarded is approved only if it rests on a full and appropriate evaluation of the contractor’s capability. In California, Caltrans’s Construction Manual says state law requires contract information to be published in the California State Contracts Register before plans and specifications are made public, and that Caltrans allows at least three weeks before bid opening, more for complex projects; emergency projects may have a shorter advertisement period.16, 17

In design-build, CM/GC and ID/IQ projects, federal rules let a state DOT use its own qualification or prequalification procedure for any phase of procurement. For NHHIP 3C-2, the reconstruction of the I-10, I-45 and I-69 mainlanes in Harris County, TxDOT chose a design-build contract: the Texas Transportation Commission authorised a request for qualifications on , and TxDOT issued it on . There the first gate is a qualification round, as in a framework competition, not the monthly letting.16, 18

Seeing the next competition coming

Where a gate opens only once in several years, the forward plans matter more than any single notice. Trafikverket publishes its procurement timetable as a spreadsheet and a map, grading each line by how certain its planned month of publication is, and warns that the data are preliminary and that new needs can arise at short notice.19

In the Netherlands, Rijkswaterstaat says it publishes a procurement plan three times a year, usually in March, June and November, listing the contracts it intends to tender one to two years ahead. As of , its planning page, last changed on , says it expects its 2027–2030 programming can be fixed at the end of 2026, that it then expects to publish a fully updated plan, and that none will be published in the meantime.20 Its page on major maintenance, as of , says that the proposed prioritisation of all national infrastructure projects, made known in a letter to parliament of , will first be discussed with the House of Representatives and then decided politically at the spring budget memorandum of 2027, on the basis of which Rijkswaterstaat can update its procurement planning.21

Under the Procurement Act 2023, a contracting authority other than a private utility that considers it will pay more than £100 million under its contracts in the coming financial year must publish a pipeline notice within 56 days of the year’s first day. The notice lists the contracts above £2 million for which it intends to publish a tender or transparency notice in the 18 months from that day.22 National Highways’ pipeline notice of covered SDF2 and estimated its tender notice for ; the tender notice came on . Here the pipeline gave the competition but not its timing: a bid team that planned on its date would have found requests to participate already closed, on .1, 23

Where the gate sits, buyer by buyer

Where the gate sits in the documents cited, as of each document’s date
Buyer and documentRoute to workTermGate
National Highways, SDF2 tender notice, Framework of 64 lots; contracts awarded with or without further competition to (estimated)Requests to participate by ; at most 4 to 20 invited to tender for each kind of work, across all the lots of that kind; quality 70%, price 30%
Die Autobahn GmbH des Bundes, open-house planning framework, Non-exclusive framework that any firm meeting the admission requirements can join while the procedure runsProcedure open to (extended on ); one further one-year extension provided forAdmission requirements only; no selection
Transport Infrastructure Ireland, MMaRC3G, Maintenance and renewals contracts, one per sub-network: three, or four if neededUp to 12 yearsRestricted procedure, up to 8 shortlisted (a stated minimum of 5 if enough submissions comply; TII may invite fewer); one lot per tenderer
Dirección General de Carreteras, six road sectors, Services contracts by sector, six lots24 months; the notice provides for extension by 36 months (24 in lot 6) and a further 9 months in every lotOpen procedure; one lot per tenderer
Trafikverket, basic road maintenance: Västerås, ; Blekinge, Works contracts, one area each to with an option of 1 or 2 years (Västerås); to (Blekinge)Open procedure
Texas Department of Transportation, statewide lettingContracts let project by project, at a letting every monthEach contract; prequalification renewed every yearAnnual prequalification; at the construction level, bidding capacity from net working capital, less TxDOT work under contract
Florida Department of Transportation, prequalification under state lawRoad, bridge and public transportation construction contracts above $250,000Prequalification renewed every yearApproved work classes and a maximum capacity rating; none for maintenance contracts, subcontractors or prime bids of $250,000 or less

Source: the notices and pages named, cited below; the gate column summarises each document’s conditions for taking part.1, 2, 3, 4, 5, 6, 7, 12, 14, 24

Sources (24)

  1. 1

    National Highways: Scheme Delivery Framework 2, UK4 tender notice 2025/S 000-060400 (Procurement Act 2023), published (Find a Tender) · Tier 1 · official · Verified

    Where in the document

    Notice sections (Find a Tender headings): section Scope, headings Description, Commercial tool, Total value (estimated) and Contract dates (estimated), and section Procedure, heading Procedure type, for C-3580; section Scope, the lot list (“Lots (64)”) and each lot section’s title, for C-3581; section Lot 1, Description, for C-3582; section Procedure (“relates to all Sublots under a Lot”) and each lot section’s sentence on the maximum number of suppliers to be invited to tender, for C-3583; section Award criteria, for C-3584; section Submission (requests to participate deadline; award decision date, estimated) and section Framework, headings Framework operation description and Award method when using the framework, for C-3585; section Framework, heading Justification for framework term over 4 years, for C-3586; the notice header (publication date) for C-3587; section Framework, heading Contracting authorities that may use the framework, for C-3616; section Framework, heading Maximum number of suppliers, for C-3618. The OCDS release (https://www.find-tender.service.gov.uk/api/1.0/ocdsReleasePackages/060400-2025) checked by script for each lot’s award criteria and invitation maximum, and for the framework type (no isOpenFrameworkScheme flag: not an open framework; C-3585’s evidence).

  2. 2

    Texas Department of Transportation: Contract letting · Tier 1 · official · Verified

    Where in the document

    Opening paragraph (letting defined; statewide letting in Austin; schedule) and “District local lettings”. The host’s terms restrict reuse: paraphrased.

  3. 3

    Transport Infrastructure Ireland: contract notice 776920-2025, TII487 Motorway Maintenance and Renewals Contract Third Generation (MMaRC3G) for TII, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/776920-2025/xml (eForms; the detail page answers 202 to plain requests). Procedure-level ProcurementProject: Name (the title above; the four lots are named MMaRC Network A to D, D “If needed”), Description and Note (sub-networks, contractors, term, estimate and range) for C-3592 and C-3594; each lot’s ProcurementProject Note and EconomicOperatorShortList (shortlist of up to 8, a stated minimum of 5 if enough submissions meet TII’s requirements, TII reserving the right to invite fewer; one lot per tenderer) for C-3593; LotDistribution; EstimatedOverallContractAmount; lot DurationMeasure; ParticipationRequestReceptionPeriod.

  4. 4

    Dirección General de Carreteras: contract notice 464902-2026, Conservación y explotación de las carreteras, en los sectores LO-03, Z-06, Z-05, Z-01, SO-04, CS-02, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/464902-2026/xml (eForms; the detail page answers 202 to plain requests). Title; contract nature; procedure; legal basis; estimated value; LotDistribution; PlannedPeriod; ContractExtension; AwardingCriterion. Spanish; translation B items G3-B4 and G3-B5.

  5. 5

    Trafikverket: contract notice 730978-2025, Basunderhåll väg område Västerås, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/730978-2025/xml (eForms; the detail page answers 202 to plain requests). Title; description; contract nature; procedure; legal basis; estimated value; contract period. Swedish; translation B item G3-B6.

  6. 6

    Trafikverket: contract notice 737624-2026, Utförande av basunderhåll väg på allmänna vägar inom område Blekinge, Blekinge län, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/737624-2026/xml (eForms; the detail page answers 202 to plain requests). Title; contract nature; procedure; legal basis; estimated value; contract period. Swedish; translation B item G3-B7.

  7. 7

    Texas Department of Transportation: Contractor prequalification · Tier 1 · official · Verified

    Where in the document

    Page section Questionnaires (the three levels, annual requalification; 1, the confidential questionnaire, normally for construction, with its audited CPA statement; 2, the bidder’s questionnaire, for waived projects) for C-3608 and C-3617; the Questionnaire guidance table (bidding capacity by questionnaire: net working capital times a TxDOT factor for the confidential questionnaire; $1 million without a compiled or reviewed statement for the bidder’s questionnaire) for C-3609 and C-3617; section Bidders, heading Qualification of bidders (bidding capacity; validity from the balance-sheet date or, for a bidder’s questionnaire without financial statements, from receipt; 10 days before the letting) for C-3608, C-3609 and C-3617; section Subcontractors for C-3610. The host’s terms restrict reuse: paraphrased.

  8. 8

    Procurement Act 2023, Part 3 (award of public contracts and procedures), legislation.gov.uk, latest revised text · Tier 1 · official · Verified

    Where in the document

    Section 34(1)–(5) (award by reference to a dynamic market; late applications); section 36(6)(a) and 36(7) (membership); section 38 (fees); section 40(1), (2), (5) and (6) (qualifying utilities dynamic market notices); section 45(2)–(5)(c) and 45(7) (frameworks; competition for call-offs; estimated value; fees); section 46(1), (2) and (7) (conditions of participation in a competitive selection process); section 46(8) and (9) (competitive selection process); section 49(1) and (2) (open frameworks); section 49(6) and (7) (single-supplier open frameworks: four years). In force from .

  9. 9

    Cabinet Office: Guidance: Frameworks (HTML), Procurement Act 2023 guidance, updated · Tier 1 · official · Verified

    Where in the document

    Paragraph 2 (most frameworks do not commit the authority to a call-off); 6 (award notice for each call-off); 16 (estimated value covers all call-offs); 19–20 (fees; no charge for access); 33–35 (open frameworks; suppliers locked out of standard frameworks); 35 and 44 (the single-supplier exception, four years); 50 (taxi-rank and highest-ranking mechanisms); 56–58 (conditions of participation for a call-off, including additional conditions); 75 (payments made under each call-off); 80, 82 and 84 (pipeline, tender and award notices for call-offs); 84 (award notices for all call-offs, with two exceptions).

  10. 10

    Procurement Act 2023, section 47 (frameworks: maximum term), legislation.gov.uk · Tier 1 · official · Verified

    Where in the document

    Section 47(1)(a), 47(2), 47(3) and 47(5)(b); in force from .

  11. 11

    Publications Office of the European Union: Directive 2014/24/EU of the European Parliament and of the Council of on public procurement, consolidated text of · Tier 1 · official · Verified

    Where in the document

    Article 33(1), third subparagraph, and 33(2), second subparagraph; the same wording as the Official Journal text (OJ L 94, ). The consolidated text as the Publications Office serves it; the EUR-Lex address of the act is https://eur-lex.europa.eu/eli/dir/2014/24/oj/eng (EUR-Lex refuses plain requests).

  12. 12

    Die Autobahn GmbH des Bundes: contract notice 387965-2026, Abschluss eines nicht-exklusiven Rahmenvertrags Planung Verkehrsanlagen 2025 ff. im Open-House-Verfahren der Autobahn GmbH des Bundes (OH-ZEN-2025_01), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/387965-2026/xml (eForms; the detail page answers 202 to plain requests). Title; procedure description (service areas); ProcurementProject note (no selection; joining; call-offs; not a public contract under Directive 2014/24/EU; review); lot note and renewal description (term and extensions). German; translation B items G3-B1 to G3-B3.

  13. 13

    Main Roads Western Australia: Road Maintenance Contracts · Tier 1 · official · Verified

    Where in the document

    Opening paragraph (transition complete) and the list of contract transitions with dates. The host’s terms restrict reuse: paraphrased.

  14. 14

    Florida Department of Transportation: Prequalification Information · Tier 1 · official · Verified

    Where in the document

    Opening paragraphs (section 337.14, Florida Statutes; Rule 14-22, Florida Administrative Code; threshold; work classes; maximum capacity rating; exemptions).

  15. 15

    Main Roads Western Australia: Prequalification · Tier 1 · official · Verified

    Where in the document

    Opening paragraphs (National Prequalification System; mandatory regardless of value; mutual recognition). The host’s terms restrict reuse: paraphrased.

  16. 16

    Office of the Federal Register and Government Publishing Office, eCFR: 23 CFR part 635 subpart A, Contract procedures (Federal Highway Administration), text up to date as of · Tier 1 · official · Verified

    Where in the document

    Section 635.104(a), (c), (d) and (e); section 635.110(b), (c) and (f), with (f)(1) and (f)(2); section 635.112(b), (d) and (f). Read through the eCFR versioner API (sections 635.104, 635.110, 635.112, date 2026-10-28); last amended 2020-11-16 (635.104, 635.110) and 2023-03-30 (635.112). For C-3613 (how-road-authorities-buy-works): section 635.110(c), third sentence, 635.110(d) and 635.110(f), opening sentence. Address: the eCFR renderer API’s point-in-time text as of (the title’s “up to date as of” date on 2026-10-30), chosen because it answers plain requests; the human-readable eCFR page, https://www.ecfr.gov/current/title-23/chapter-I/subchapter-G/part-635/subpart-A, sends automated requests (and the coordinator’s browser) to a bot-verification page, which is not bypassed. GovInfo’s annual CFR edition was not used: the eCFR’s dated text is the one every row was checked against, and one address type serves every regulation the guide buy-america-dbe-federal-aid cites.

  17. 17

    Caltrans: Construction Manual, chapter 3, section 2, Bidding (2019) · Tier 1 · official · Verified

    Where in the document

    Section 3-202 (advertising: California State Contracts Register; minimum of three weeks before bid opening; emergency projects).

  18. 18

    Texas Department of Transportation: NHHIP 3C-2, request for qualifications (RFQ) · Tier 1 · official · Verified

    Where in the document

    Page text (Commission authorisation, Minute Order 117235; design-build; RFQ issue date; project limits). The host’s terms restrict reuse: paraphrased.

  19. 19

    Trafikverket: Planerade upphandlingar (planned procurements), last updated or reviewed · Tier 1 · official · Verified

    Where in the document

    Page text on the procurement timetable, the map and the planning-status column. Swedish; translation B item G3-B8. The host’s terms restrict reuse: paraphrased, nothing quoted on the page.

  20. 20

    Rijkswaterstaat: Inkoopplanning en meerjarenoverzicht (procurement plan and multi-year overview), page modified · Tier 1 · official · Verified

    Where in the document

    The paragraphs on the procurement plan and on the programming for 2027–2030. Dutch; translation B items G3-B11 and G3-B12.

  21. 21

    Rijkswaterstaat: Groot onderhoud (major maintenance page; undated, read ) · Tier 1 · official · Verified

    Where in the document

    Dutch. Letter to parliament of 16 October 2026 on the proposed prioritisation and an extra 18 billion; decision at the spring budget memorandum of 2027, then an update of the procurement planning; work may take place later than foreseen. Re-read in revision 1 (page modified 2026-10-16, unchanged), with the cabinet’s letter of . Newer than S-1070 (modified 2026-07-20) on when the procurement planning returns: conflict X-060. Market data: re-read before publication. Translation B items F2-B39 and F2-B40.

  22. 22

    Procurement Act 2023, section 93 (pipeline notices), legislation.gov.uk · Tier 1 · official · Verified

    Where in the document

    Section 93(1)–(4) (GBP 100 million in the coming financial year; contracts above GBP 2 million; reporting period of 18 months), 93(2) (within 56 days of the first day of the financial year) and 93(6)(a) and (b) (not private utilities or a transferred Northern Ireland authority).

  23. 23

    National Highways: Scheme Delivery Framework 2 (SDF2), UK1 pipeline notice 2025/S 000-022269, published (Find a Tender) · Tier 1 · official · Verified

    Where in the document

    Notice sections (Find a Tender headings): section Scope, headings Description and Total value (estimated), and heading Publication date of tender notice (estimated), for C-3587.

  24. 24

    Die Autobahn GmbH des Bundes: change notice 746687-2026 to contract notice 387965-2026 (OH-ZEN-2025_01), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/746687-2026/xml (eForms; the detail page answers 202 to plain requests), ; XML SHA-256 41a7d9596a400e70fa3d463b6973fc995702d03ecbcb8c597ad7fd424bcaab73. Change notice (cor-pub, LOT-0000) of notice 387965-2026 (S-1063): its reason, the extension of the open-house procedure by a further year to 31.12.2027, and the moved submission and opening dates (2026-12-31 to 2027-12-31, 23:59 +01:00); the description it repeats (procedure to 31.12.2026, two extensions of one year; framework agreement to 31.12.2026 subject to the options). Evidence note (owner, ): the notice’s descriptive text still shows the old 2026 date, while its change section and its deadline field give 31 December 2027; the change section is the operative part. German; translation B item G3-B14 (reports/2026-11-02/transport-recheck/translation-b.json) agrees with translation A (comparison in reports/2026-11-02/transport-recheck/translation-comparison.md).

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “How road authorities buy works, and when a contractor’s chance is decided”, . https://www.listingminds.com/transport/guides/how-road-authorities-buy-works