Rail and metro · Sector guide

ERTMS procurement: separate streams, gated by approvals

ERTMS is bought in separate streams: trackside by place, onboard by vehicle class, radio sometimes as a network of its own. For a supplier, the gates often come before any notice: product approvals, the EU Agency’s check of draft trackside specifications and, at some buyers, a qualification system or few-supplier framework.

ListingMinds · Published and updated · Sources verified · Reviewed

Markets and rounds covered: European Union, Germany, Sweden, Great Britain, Spain, Austria, Netherlands, Italy

On this page

On , DB InfraGO awarded the first planning section of its ETCS project between Flensburg and Maschen without publishing a new call for competition. Its award notice, published on , gives the reason: a call for competition had already been made, for the prequalification.1

Deutsche Bahn runs a qualification system for ETCS trackside work: its notice of asks for a supplier or developer of approved international ETCS or a company Deutsche Bahn has prequalified, and warns that qualifying promises no place in any competition.2 Under the EU utilities directive, suppliers must be able to apply to such a system at any time.3 For a firm not yet on the list, the practical question is how long qualification takes, not whether the list has closed. How such systems work is the subject of our guide to rail qualification systems.

ERTMS work comes to the market in separate streams, trackside, onboard and radio, and for a signalling supplier much of what decides who can bid is settled before a notice appears: in the approvals a product must hold, in the EU Agency’s check of draft trackside specifications, and at some buyers in a qualification system or a framework with few suppliers.

In the EU’s technical specification for signalling, ERTMS is train protection (ETCS), radio communication and automated train operation, and its Class A radio systems are GSM-R and FRMCS, the Future Railway Mobile Communication System.4 The trans-European transport network regulation requires ERTMS on the core network by , with exceptions for certain connections, deployed trackside and on board in step.5 The approval rules below come from the EU’s rail interoperability directive, which does not apply to metros, to trams and light rail, or to functionally separate networks used only for local, urban or suburban passenger services.6 This guide is about main-line railways.

Trackside work is let by place

The Flensburg–Maschen section is four new electronic interlockings and the adaptation of others, in a project that will equip the lines with ETCS Level 2 with signals and PZB. Trafikverket’s notice published on is for an execution contract to introduce ERTMS at Fosieby and Lernacken, estimated at SEK 230 million. Both name price as the award criterion.1, 7

Trafikverket also buys the signalling system itself for groups of control areas: on its page updated on , it said it was procuring its existing ERTMS system for about 20 further control areas, with the procurement to be advertised in the autumn or winter of 2026 and the areas upgraded during 2029–2036.8 A trackside pipeline is a list of places, each with its own date, and the system and the works can reach the market as different contracts.

In the EU, before any call for tenders for ERTMS trackside equipment, the European Union Agency for Railways checks that the technical solutions in the draft tender specifications are fully in line with the technical specifications for interoperability. The Agency says within one month whether the applicant’s file, with the draft specifications, is complete, and within two months of receiving all relevant information issues a positive decision or names the deficiencies. If the draft specifications change after a positive decision, the applicant informs the Agency and the national safety authority without undue delay; that authority later authorises placing the trackside in service.6 So the technical solution of an EU trackside tender is largely set in its draft specifications before the tender opens.

Onboard fitment is bought by vehicle class, approvals included

DB InfraGO’s award notice published on is for developing, manufacturing and installing ETCS equipment on seven class 721.3 driving trailers in its own machine pool, commissioning them and obtaining all the necessary approvals, for EUR 7,450,000.9

In Great Britain, Network Rail’s year-three update of its plan for digital signalling, on a forecast as at , reports that procuring and mobilising some fitment contracts is taking longer than planned, and that design approvals for the first-in-class fitment of the Class 66 locomotive have been delayed.11

Network Rail’s planned procurement notice of is for Package 1 of its charter and heritage onboard ETCS fitment framework, a single-supplier framework to design, supply, fit and test ETCS on existing locomotive classes in that sector, estimated at £140,123,500 excluding VAT.12 The summary of changes published with it explains why Network Rail dropped its earlier plan for three suppliers competing for each class in mini-tenders, in favour of one supplier commissioned directly: market feedback was that low volume commitments, fragmented opportunities and uncertain workload would make a multi-supplier model unattractive. It also cut the scope to five priority classes, about 67–122 vehicles, which Network Rail says gives suppliers a clearer minimum volume commitment, and replaced a target cost with a fixed price indexed to CPI.13

The first-in-class design is what an onboard buyer least wants to pay for twice: Network Rail justifies a framework term beyond the Procurement Act’s standard eight years because re-tendering during delivery would mean repeating it.

Radio is funded with the trackside, and can be bought on its own

The European Commission reports the ERTMS projects supported under the second Connecting Europe Facility in two groups: trackside, covering ETCS, interlocking and Class A radio, and onboard, covering vehicles.14 Adif’s notice published on is for a service contract to maintain, operate and renew the central systems of its high-speed GSM-R core network, with centralised telecommunications management, energy remote control and the telecommunications and other installations on named lines. It runs for 48 months with a possible 12-month renewal, and the estimate of EUR 181,268,319.30 covers the whole scope.15 In Austria, ÖBB-Infrastruktur runs a qualification system for planning, supplying, integrating and operating FRMCS systems; its notice of stresses that this is not a tender, and that firms entered in its register are invited to tender for specific contracts directly, without a further notice.16

So a radio supplier may meet radio inside a funded trackside project, as a network service of several years, as at Adif, or behind a qualification system, as at ÖBB-Infrastruktur.

Some large buyers choose their product suppliers before the schemes

Network Rail’s year-three update says it has awarded a development contract to each of the four suppliers on its Train Control Systems Framework, with final products expected before the end of the control period on .11

ProRail’s axle-counter contract for ERTMS, announced on , lets the supplier deliver for at most eight years after successful development, with 2032 as the expected year of the last delivery, followed by 25 years of maintenance services, for at most 100 million euros.17 Its framework notice published on , by competitive dialogue, is for a single-supplier framework to develop an object controller cabinet that houses parts ProRail has already contracted under its other ERTMS frameworks, including the signalling system and the axle counters, with at least 84 cabinets to follow development and acceptance.18 Once those places are filled, the product for each part of the system is chosen for years, and later contracts are let among the suppliers already selected.

Under the EU utilities directive, a framework agreement may not run for more than eight years, save in exceptional cases duly justified. It is an agreement with one or more suppliers that sets the terms for the contracts awarded during its term, and competition for those contracts may be reopened among the suppliers party to it as concluded. Under a qualification system, by contrast, the contracts it covers are awarded among the suppliers already qualified.3 For a utilities framework under the Procurement Act 2023, the limit is also eight years, unless the buyer considers that the nature of the work requires a longer term and gives its reasons in the tender or transparency notice; the limit does not apply to a private utility’s framework or an open framework.19 The Cabinet Office’s guidance adds that in most cases a framework does not commit the buyer to a call-off, though some may.20

Under the EU directive, what differs for a firm outside is timing: a qualification system can be joined while it runs; a framework’s suppliers are those party to it when it is concluded. Even a place on a framework is not an order book: what a supplier can plan on is the volume the buyer commits to.

Approval is the gate, and much of it falls on the supplier

Under the EU rail interoperability directive, each component on which the interoperability of the rail system depends carries an EC declaration of conformity or suitability for use, signed by its manufacturer and backed by a notified body’s certificate where the specification requires one, and Member States may not repeat checks already carried out in that procedure.6 In the EU, whether a train and a line work together is checked separately, as ETCS System Compatibility and, for radio, Radio System Compatibility. For ETCS, the infrastructure manager defines the compatibility types for its network and, with the support of its ETCS suppliers, submits the definition of the checks for each type to the Agency, which publishes the list; the onboard supplier produces the statement for its equipment, and a notified body assesses the check reports. A check passed stays valid while the vehicle is not modified, and once the checks are published, national rules for ETCS compatibility testing are withdrawn.4

That work can be bought on its own: RFI’s award notice published on records a framework agreement signed on with the supplier of the trackside and onboard subsystems, to demonstrate their safe integration and the compatibility of the ETCS and radio systems. It was negotiated with that supplier alone under the Italian procurement code’s exception for exclusive rights, including intellectual property, which applies only where no reasonable substitute or alternative exists and the lack of competition is not the result of artificially narrowed parameters.21, 22 Compatibility work can depend on whoever holds the rights to the existing subsystems, so a new entrant’s price has to allow for the checks its product must pass on each network, and for who is able to carry them out.

In Great Britain, Network Rail adds a gate of its own: its plan of provides for market application readiness work to support the appointed ETCS trackside suppliers through product development, to confirm that their solutions comply with the GB specifications for ETCS.10 Its year-three update plans the start of progressive testing of their products at national test facilities during 2026-27.11

Procurement can delay ERTMS, and Network Rail’s ETCS plan has shrunk

A European Commission page last modified on lists, among the causes of delay to ERTMS deployment, procurement procedures that led to delays, or even to projects being cancelled, because too few offers came in or offers exceeded the budget, and demanding requirements that lengthened tenders.23

Network Rail’s year-three update, on its forecast as at , puts its ETCS spending for the control period that ends on at £994m, against £1,544m in its plan of , including signalling renewals at £257m against £545m and fleet modification at £535m against £812m, in cash prices.11 On those figures, the money for ETCS signalling renewals is less than half what the 2024 plan set.

What to check in an ERTMS notice

Checklist

  • Whether the buyer awards from a qualification system, and how long its examination takes
  • Which stream the work belongs to, and who obtains the approvals
  • For an EU trackside contract, whether the Agency’s check is done, and what the draft specifications already fix
  • Which compatibility checks your product must pass on that network, and who holds the rights to carry them out
  • What a framework commits the buyer to, beside its estimated value

The rules behind the gates

The EU and UK rules behind ERTMS procurement
RuleWhat it doesApplies to
Directive (EU) 2016/797, article 19The Agency checks the technical solution for ERTMS trackside equipment before any call for tenders, on the draft tender specifications or a description of the solutionTrackside subsystems with ETCS or GSM-R, EU
Directive (EU) 2016/797, article 18The national safety authority authorises placing trackside in service, with the Agency’s positive decision in the file where ETCS or GSM-R is involvedTrackside control-command and signalling, EU
Directive (EU) 2016/797, articles 8 to 10An EC declaration of conformity or suitability for use for each interoperability constituent, with a notified body’s certificate where the specification requires itInteroperability constituents, EU
Implementing Regulation (EU) 2023/1695, Annex I, points 4.2.17.1 to 4.2.17.3ETCS and radio system compatibility checks; for ETCS, types defined by the infrastructure manager with the support of its ETCS suppliers, and a statement from the onboard supplierNew onboard and trackside control-command and signalling, EU
Regulation (EU) 2024/1679, articles 3 and 18ERTMS on the core network by , the extended core network by and the comprehensive network by , with exceptions for certain connections, trackside and on board in step; radio-based ERTMS (ETCS level 2 that does not require lineside signals) on a new line from and on upgraded signalling from ; class B systems decommissioned by , and on the same three networks, provided an appropriate level of safety is ensured, except on certain sections in urban nodes also used by suburban passenger trains with their own class B systemsThe trans-European transport network
Directive 2014/25/EU, articles 51 and 77Framework agreements of up to eight years save in exceptional cases, with contracts awarded under rules that may reopen competition among the parties; qualification systems open to applications at any time, their contracts awarded among the suppliers qualifiedUtilities in the EU, rail included
Procurement Act 2023, section 47Utilities frameworks of up to eight years, unless the buyer considers that the nature of the work requires a longer term and gives its reasons in the tender or transparency noticeUtilities under the Act, other than private utilities and open frameworks
Directive (EU) 2016/797, article 1(3)Does not apply to metros, to trams and light rail and the infrastructure only they use, or to networks functionally separate from the rest of the EU rail system and used only for local, urban or suburban passenger servicesUrban and local rail

Source: the directives, regulations and Act named in the table, cited below.3, 4, 5, 6, 19

Sources (23)

  1. 1

    DB InfraGO AG: contract award notice 861128-2025, ETCS Flensburg-Maschen PA1, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/861128-2025/xml (eForms): section TenderingProcess (procedure type neg-wo-call; its justification: a call for competition held for the prequalification, so no new notice required); section ProcurementProject (name and description: planning section 1, four new interlockings, ETCS L2mS and PZB); section TenderResult (award date ); the lot’s section AwardingTerms (award criterion price, weight 100); legal basis 32014L0025. Issue date 2025-12-23.

  2. 2

    TED: Deutsche Bahn AG, qualification system for ETCS L1 LS and L2 infrastructure installations on the network of DB InfraGO AG, notice 818928-2025 · Tier 1 · official · Verified

    Where in the document

    Procurement project name and description; the notice’s note (continuation of 775234-2024; no promise of participation; call for competition; German); selection-criteria description (two stages; no charge); legal basis and notice type. In German; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending). For G2 (merged from G2's S-1050, away run D coordinator): Read through https://ted.europa.eu/en/notice/818928-2025/xml (eForms): notice type qu-sy; ProcurementProject name, description and note (continuation of 775234-2024; prequalification promises no participation in a competition); the lot’s note on the qualification requirements (approved international ETCS and/or prequalification by Deutsche Bahn AG; two-stage examination; list of qualified companies; free of charge); legal basis 32014L0025.

  3. 3

    EUR-Lex: Directive 2014/25/EU on procurement by entities in the water, energy, transport and postal services sectors, consolidated text of · Tier 1 · official · Verified

    Where in the document

    Article 43; article 51(1); article 77(1) and 77(5); article 85(1) and 85(2). The consolidated text of has the same wording as the original 2014 text for these articles.

  4. 4

    Publications Office of the European Union: Commission Implementing Regulation (EU) 2023/1695 on the technical specification for interoperability relating to the control-command and signalling subsystems, consolidated text of (CELEX 02023R1695-20260505) · Tier 1 · official · Verified

    Where in the document

    Article 2(1) (scope); Annex I, point 2.2 (ERTMS composed of ETCS, RMR and ATO; GSM-R and FRMCS as Class A radio), points 4.2.17.1 (ETCS System Compatibility), 4.2.17.2 (requirements for ESC: ESC types defined by the infrastructure manager, checks submitted with the support of the ETCS suppliers, the Agency’s technical document, validity of passed checks, withdrawal of national rules) and 4.2.17.3 (Radio System Compatibility). Amended by Implementing Regulation (EU) 2026/693.

  5. 5

    Publications Office of the European Union: Regulation (EU) 2024/1679 on Union guidelines for the development of the trans-European transport network (OJ L, 2024/1679, ) · Tier 1 · official · Verified

    Where in the document

    Article 3, points (21) and (22) (definitions of ERTMS and radio-based ERTMS); article 18(1), 18(2), 18(3) and 18(5) (deployment and decommissioning deadlines). Other parts of the act are not used (research record). The EUR-Lex address is https://eur-lex.europa.eu/eli/reg/2024/1679/oj/eng.

  6. 6

    Publications Office of the European Union: Directive (EU) 2016/797 on the interoperability of the rail system within the European Union (recast), consolidated text of (CELEX 02016L0797-20260802) · Tier 1 · official · Verified

    Where in the document

    Article 1(3) (scope); article 2, point (7) (interoperability constituents); article 8(2); article 9(1) to 9(3); article 10(1) and 10(2); article 18(1), 18(2), 18(4)(d) and 18(5); article 19(1) to 19(4) and 19(6). Amended by Directive (EU) 2020/700 and Regulation (EU) 2024/1689; the cited articles read in the consolidated text. The EUR-Lex address of the act is https://eur-lex.europa.eu/eli/dir/2016/797/oj/eng (EUR-Lex refuses plain requests).

  7. 7

    Trafikverket: contract notice 837167-2025, Program ERTMS – Utförandeentreprenad ERTMS SO Fosieby och SO Lernacken, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/837167-2025/xml (eForms): section ProcurementProject (name and description: execution contract for introducing ERTMS at Fosieby and Lernacken; estimated overall contract amount SEK 230,000,000); section TenderingProcess (procedure type neg-w-call); the lot’s section AwardingTerms (award criterion price); legal basis 32014L0025. Issue date 2025-12-15.

  8. 8

    Trafikverket: Trafikverket upphandlar befintligt ERTMS-system på ett 20-tal styrområden, updated · Tier 1 · official · Verified

    Where in the document

    The introduction and the first two paragraphs of the article’s body text: the national plan 2026–2037 and the 2042 direction; about 20 further control areas for the existing ERTMS system, the procurement to be advertised in the autumn/winter of 2026, upgrade years 2029–2036. The last paragraph: the ongoing procurement of the new ERTMS system for 64 control areas. Date line “Senast uppdaterad/granskad: 2026-05-29”. Facts cited and linked, not reproduced (the publisher’s terms restrict reuse).

  9. 9

    DB InfraGO AG: contract award notice 857988-2025, ETCS-Nachrüstung BR721.3 (Steuerwagen), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/857988-2025/xml (eForms): section ProcurementProject (name and description: ETCS on-board equipment for 7 class 721.3 driving trailers, commissioning, all necessary approvals); the lot’s section AwardingTerms (price; performance assessment by criteria catalogue); section TenderingProcess (procedure type neg-w-call); section NoticeResult (total and lot tender amount EUR 7,450,000); legal basis 32014L0025. Issue date 2025-12-22.

  10. 10

    Network Rail: CP7 Delivery Plan 2024-2029, Our approach to digital signalling in CP7 · Tier 1 · official · Verified

    Where in the document

    Section 1.4 and Table 2 (ETCS renewals £545m); section 1.4.1 (market application readiness after the award of the TCSF); section 1.5.2 (freight programme); Table 3 (fleet modification £812m; Network Rail-wide total £1,544m); section 2 (key enablers: four new ETCS suppliers; c.180 passenger vehicles across six classes). Publication date from the PDF’s creation date (), consistent with the year-three update, which says the plan was published in . Facts cited and linked, not reproduced (the publisher’s terms restrict reuse).

  11. 11

    Network Rail: Our delivery plan for digital signalling, Control Period 7, year three update (2026) · Tier 1 · official · Verified

    Where in the document

    Foreword (procurement of fitment contracts taking longer; core product development for the four TCSF suppliers, final products before the end of the control period; schemes with allocated signalling partners); “Our CP7 Year 2 outcomes” (development contracts under the TCSF; sourcing strategy grouping similar vehicle types); “Introduction to this document” (CP7 dates); “Our expenditure” (forecast as at ; Class 66 design approvals delayed) and Table 1 ( and delivery plan columns); “Delivery for the year ahead (2026-27)”. The document shows no publication date (PDF created , address in the upload folder of ). Facts cited and linked, not reproduced (the publisher’s terms restrict reuse).

  12. 12

    Network Rail Infrastructure Limited: UK3 planned procurement notice 2026/S 000-072760, Charter & Heritage National Onboard ETCS Fitment Framework – Package 1, published (Find a Tender) · Tier 1 · official · Verified

    Where in the document

    Sections Scope (Description; Total value (estimated) £140,123,500 excluding VAT), Framework (Maximum number of suppliers: 1; Justification for framework term over 8 years) and Procedure (competitive flexible procedure; utilities). Same procurement (OCID ocds-h6vhtk-0596a6) as S-1047; the OCDS record, read 2026-10-30, lists the UK1 (), UK2 () and UK3 () notices and no later notice.

  13. 13

    Network Rail Infrastructure Limited: UK3 Planned Procurement Notice – Summary of Changes Post UK2 Notice, Charter & Heritage National Onboard ETCS Fitment Framework – Package 1 (attachment A-19960 to notice 2026/S 000-072760, , Find a Tender) · Tier 1 · official · Verified

    Where in the document

    Table 1, “Outlines of Changes to Strategy: PME to Present”: rows Framework Duration, Framework Name, Scope, Commercial Model, Call-Off Model, Packaging Strategy and Pricing Model (pages 2 to 4). Dated by the notice it is attached to.

  14. 14

    European Commission, Directorate-General for Mobility and Transport: EU funding for ERTMS · Tier 1 · official · Verified

    Where in the document

    The paragraph on CEF II (trackside projects covering ETCS, interlocking and Class A radio; on-board projects covering vehicles) and the paragraph on unit contributions. The page shows no date; its metadata gives a last modification of . The table of unit contributions the page refers to is not shown as text and is not used.

  15. 15

    Administrador de Infraestructuras Ferroviarias (Adif): contract notice 529710-2026, maintenance, network operation and renewal of the GSM-R core network central systems of the high-speed network, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/529710-2026/xml (eForms): section ProcurementProject (name and description: the GSM-R core network’s central systems, telecommunications management, energy remote control and the installations on named high-speed lines; estimated overall contract amount EUR 181,268,319.30); section TenderingProcess (procedure type open); the lot’s note (term 48 months) and its section on contract extension (renewal of 12 months); legal basis 32014L0024. Issue date 2026-07-29.

  16. 16

    TED: ÖBB-Infrastruktur AG, qualification system ProVia-ID 1033 for FRMCS MCx/5G systems, notice 472247-2026 · Tier 1 · official · Verified

    Where in the document

    Procurement project name; the notice’s note (a qualification system, not a tender; register; direct invitation without further notice; ProVia only); period code; legal basis and notice type. In German; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).

  17. 17

    ProRail: ProRail en Thales tekenen contract voor assentelsysteem ERTMS, news item of · Tier 1 · official · Verified

    Where in the document

    The paragraph under the heading 600 kilometer: delivery for at most eight years after successful development; 2032 as the expected year of the last delivery of axle counters; then 25 years of maintenance services; contract value at most 100 million euros.

  18. 18

    ProRail B.V.: contract notice 222782-2026, ERTMS – Raamovereenkomst Objectcontroller Kasten (OCK) ten behoeve van ERTMS projecten, published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/222782-2026/xml (eForms): section ProcurementProject (name and description: parts already contracted; development and acceptance; at least 84 cabinets; the maximum is 460 in the procedure’s description and 355 in the lot’s, conflict X-055); section TenderingProcess (procedure type comp-dial; framework agreement, maximum 1 operator); the lot’s section on duration (8 years); legal basis 32014L0025. Issue date 2026-03-31.

  19. 19

    Procurement Act 2023, section 47 (frameworks: maximum term), legislation.gov.uk · Tier 1 · official · Verified

    Where in the document

    Section 47(1)(a), 47(2), 47(3) and 47(5)(b); in force from .

  20. 20

    Cabinet Office: Guidance: Frameworks (HTML), Procurement Act 2023 guidance, updated · Tier 1 · official · Verified

    Where in the document

    Paragraph 2 (most frameworks do not commit the authority to a call-off); 6 (award notice for each call-off); 16 (estimated value covers all call-offs); 19–20 (fees; no charge for access); 33–35 (open frameworks; suppliers locked out of standard frameworks); 35 and 44 (the single-supplier exception, four years); 50 (taxi-rank and highest-ranking mechanisms); 56–58 (conditions of participation for a call-off, including additional conditions); 75 (payments made under each call-off); 80, 82 and 84 (pipeline, tender and award notices for call-offs); 84 (award notices for all call-offs, with two exceptions).

  21. 21

    Rete Ferroviaria Italiana S.p.A.: contract award notice 337801-2026, DAC.0706.2025 Accordo Quadro per le attività del fornitore del Sottosistema di Terra e del Sottosistema di Bordo (ESC/RSC), published (TED) · Tier 1 · official · Verified

    Where in the document

    Read through https://ted.europa.eu/en/notice/337801-2026/xml (eForms): section ProcurementProject (name: the framework for the supplier of the trackside and on-board subsystems, ESC and RSC); the lot’s note (framework signed after a single negotiated procedure under article 158(2)(c)(3) of Legislative Decree 36/2023); section TenderingProcess (procedure type oth-single); section NoticeResult (contract signed ; the lot’s framework maximum value and the tender’s payable amount EUR 3,945,872.55, the notice-level overall maximum EUR 3,945,873.55, a one-euro difference, so the piece states no amount); legal basis 32014L0025. Issue date 2026-05-14.

  22. 22

    Normattiva (Istituto Poligrafico e Zecca dello Stato): Decreto legislativo 31 marzo 2023, n. 36, Codice dei contratti pubblici, article 158 (Procedura negoziata senza pubblicazione di un bando), text in force · Tier 1 · official · Verified

    Where in the document

    Article 158(1) and 158(2)(c), point 3 (protection of exclusive rights, including intellectual property rights; only where no reasonable substitutes or alternatives exist), text in force as served on 2026-10-30.

  23. 23

    European Commission, Directorate-General for Mobility and Transport: What are the deployment challenges? (ERTMS) · Tier 1 · official · Verified

    Where in the document

    The list of challenges: “Changes to national ERTMS deployment strategies”, “Fleet equipment”, “Public procurement” and “Technical aspects”. The page shows no date; its metadata gives a last modification of .

ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work

How to cite

ListingMinds, “ERTMS procurement: separate streams, gated by approvals”, . https://www.listingminds.com/transport/guides/ertms-procurement