A rail buyer in the EU may make a qualification-system notice its call for competition, then award contracts only among firms it has already qualified. At the large networks, entry is decided trade by trade and can take months, so the decision that counts is when to apply.
ListingMinds · Published and updated · Sources verified · Reviewed
Markets and rounds covered: European Union, Germany, Italy, Netherlands, France, Belgium, Austria, Ireland, United Kingdom
On this page
When a rail buyer awards work through a qualification system, who can bid is settled before any contract goes to tender: each contract is put out only to firms already qualified in the system. Directive 2014/25/EU, which applies to networks serving the public by railway, automated systems or tramway, lets the buyer make the system’s notice its call for competition, provided the notice says so; each contract the system covers is then awarded by restricted or negotiated procedure, with every tenderer chosen from the candidates already qualified.1 For a contractor, the decision that matters is whether, and when, to get onto the list.
Iarnród Éireann’s notice of , for a qualification system for civil engineering works of €1m to €5m, says that all project works shall be tendered to the companies approved for the system.2 ÖBB-Infrastruktur’s notice of stresses that it concerns a qualification system and not a tender: firms that pass are entered in a register and, in specific awards, invited directly to tender without further notice.3 Deutsche Bahn’s notice of for ETCS infrastructure installations calls itself a call for competition, and warns that passing the prequalification does not guarantee a place in any competition.4 How signalling work is bought around systems such as this one is the subject of the ERTMS procurement guide.
Where the effort of running a procedure calls for it, the directive also lets a buyer reduce, on objective rules, the number of candidates it invites, though the number must take account of the need for adequate competition.1 Under the directive, a place on the list is the condition for an invitation, not a promise of one. Network Rail can select from a standing list in the same way, through RISQS, the Rail Industry Supplier Qualification Scheme that RSSB runs, but under UK rules rather than the directive.
What the notice tells a supplier
The notice states what the system will buy, the conditions a supplier must meet and how long the system runs; the buyer reports any change to that period and ends the system with an award notice. The buyer keeps a written record of qualified firms, which may be divided by type of contract.1
A notice used as the call for competition stays published for as long as the system runs, and suppliers must be able to apply at any time in that period. It is not a closing date. The buyer must decide on an application within six months, and explain within two months if it will need more than four. A firm short of references may rely on other companies’ capacities, if it proves they stay available to it for the system’s whole validity, and for qualifications and experience only where those companies will do the work.1
RISQS and the UK’s dynamic markets
The Cabinet Office’s guidance says the Procurement Act 2023 replaces qualification systems, and dynamic purchasing systems, with the dynamic market: a list of qualified suppliers eligible to take part in future procurements.6 Qualification systems under the Utilities Contracts Regulations 2016 continue where the utility submitted the notice before , and they expire at the end of at the latest; those Regulations do not extend to Scotland.7, 8
As of , Network Rail’s supplier page calls RISQS a qualification system under those Regulations, from which it may select participants for what it buys directly without a further call for competition; suppliers of safety-critical goods, works or services who want to contract with it directly register on RISQS with audited status.9 RSSB said on that Network Rail and Network Rail High Speed had confirmed they use RISQS as a qualifying utilities dynamic market under the Act, and that other rail buyers use it in that context.10 Both statements can hold during the transition, since a system whose notice was submitted before runs on under the 2016 Regulations until it expires; which regime governs a given procurement is a question for that procurement’s own documents.
Under the Act, a utility may award contracts by reference to membership of a utilities dynamic market, and arrangements set up by anyone count as such a market if they meet the Act’s requirements for one set up by a private utility. That is what lets a scheme run by someone else, such as RISQS, serve a utility as its market. Where the market was set up by a qualifying utilities dynamic market notice, one published beforehand saying that only members will be told of future contracts, each tender notice is not published: it goes to members, and may also go to suppliers whose applications are still pending.5, 6
Applications must be accepted at any time and membership cannot be capped; the conditions, which cannot change during the market’s term, must be proportionate and may not require a supplier to have been awarded a contract by a particular authority. A utilities dynamic market may charge suppliers fees for obtaining and maintaining membership.5
Qualification is granted trade by trade, and by size or kind of work
Under its procedure rules valid from , Deutsche Bahn runs its infrastructure prequalification as a qualification system under Germany’s Sector Procurement Ordinance, with a notice in the Official Journal every year for each category; 15 categories are run centrally, and a firm applies separately for each. Track alone has nine product groups: track and switches, each in four line classes up to high-speed lines above 160 km/h, plus repair work.11
As of , RFI’s page lists its active works systems trade by trade, among them railway track and signalling.12 Its track system has six value classes, from class 1, up to €850,000, to class 6, above €16,000,000.13 When RFI tenders works from one of its value-class systems, it invites every firm registered, on the day the invitation goes out, in the system that the contract’s main category belongs to; each may take part up to its own class plus one fifth.14 Here RFI goes further than the directive requires: registration in the right system brings the invitation, though not the work, and the class caps the size of contract a firm may bid for.
ProRail’s page, updated , says it recognises firms branch by branch, from engineering firms to suppliers of rail infrastructure systems, so that no separate selection is needed for each tender.15 At DB and RFI, a place on one list does not carry over to the next, and within a list the class or product group sets what a firm can be invited to.
Getting in rewards work done for the buyer
Deutsche Bahn’s procedure runs in German and under German law, as a rule in two stages, the second examining references, technical equipment, staffing and qualifications, among other things. A prequalification is valid for four years, provided requalification is applied for in time and granted, and the application is due at least two years before the term ends; a refused firm may reapply only after six months.11 A firm that wants to stay in must apply no later than halfway through its term.
A firm new to DB or newly founded, for example, can obtain a prequalification “with conditions”, which only references for DB group work in that product group can replace. Moving up to higher-rated product groups needs DB references at the higher level, as a rule as DB’s main contractor, rated at least “good”, and is closed to firms with conditions. In track, a prequalification with conditions stops at the mixed-traffic class (121 to 160 km/h), and the high-speed and S-Bahn classes can be reached only by extending a mixed-traffic prequalification, with at least one reference at the next level, in principle under a direct contract with DB.11 A newcomer cannot qualify straight into DB’s high-speed track work on the strength of work for other clients: the way up runs, as a rule, through work on DB’s own contracts, which DB then rates.
In the long run, staying in takes DB work too. Requalification asks for work for DB in the category in the last three years, directly or as a subcontractor. Comparable work for other clients earns one extension; the next time, a firm must show at least a tender or a request to participate in a DB competition, for a last extension, or it falls back to a prequalification with conditions.11
RFI’s track system puts a firm that shows no works contracts from the previous 60 months in class 1, the access class, provided it meets the other requirements.13 Under its general rules of , RFI decides within six months of a complete application, and a qualification then stays valid without time limit while the requirements continue to be met.18
Under ProRail’s recognition scheme, in force from , a firm that meets every other requirement but cannot show its technical ability through completed work must carry out one or more recognition projects and, until ProRail decides, is invited to its tenders below the European threshold in the field applied for.19 Recognition then stays valid until it is withdrawn, and ProRail checks, among other things through performance measurements, that firms still meet the requirements.15
All three start a first-time entrant on smaller or lower-rated work, through DB’s conditions, RFI’s access class or ProRail’s recognition projects, before the larger contracts open to it. With decisions allowed to take up to six months and entry starting low, a firm that waits to apply until it sees the contract it wants risks missing it.
One qualification can open several buyers’ contracts
Under the directive, a buyer may accept another body’s qualification system as meeting its requirements, and must then tell interested suppliers which bodies those are.1 DB’s prequalification applies across the DB group.11 Firms qualified by RFI may be invited by RFI and by other companies of the Ferrovie dello Stato Italiane group.18 Ferrovie Emilia Romagna said in a notice of that it may use RFI’s systems at its discretion, or require qualification in the relevant RFI system as a condition for taking part in its tenders.21 SNCF Réseau’s system may be used by four other SNCF companies, among them SNCF Voyageurs and Fret SNCF, provided its qualification requirements are met.16 A qualification with a large network can thus count for its group companies’ contracts too and, in Italy and through RISQS in the UK, for other buyers’ contracts as well: a benefit to set against the cost and time of obtaining it.
Published lists show who else is in the field
Deutsche Bahn publishes its directory: as of , the track category lists each firm by product group, marks those with conditions, and gives each firm’s deadline to apply for requalification and the end of its validity.20 ProRail’s scheme makes its list of recognised firms public.19 For a bidder, DB’s directory shows who can be selected alongside it, which of them hold only a conditional status, and when each listed firm’s status comes up for renewal.
Contracts at or above the directive’s thresholds, set for 2026-2027 at €5,404,000 for works and €432,000 for supplies and services, net of VAT, still produce award notices: the directive requires one within 30 days of each such contract’s conclusion.1 For a firm outside the system, those notices are a public record of the larger contracts the system has been used to buy, and from whom.
The EU’s proposal keeps the mechanism under another name
On , the European Commission proposed a regulation on public contracts and concessions, COM(2026) 590, that would repeal Directive 2014/25/EU among others and apply two years after it enters into force. The proposal would let a buyer set up a qualification list, open to requests for admission at any time during its stated duration, and award each contract by inviting the operators admitted to the list or category, with a public summary of each result.22 As of , the European Parliament’s procedure file showed the proposal in its preparatory phase in Parliament.23 As proposed, the mechanism would stay under another name; until any regulation is adopted and applies, the directive’s rules govern.
Each buyer’s system: legal basis, term and how to apply
| Buyer | What the system covers | Legal basis it names | Term | How to apply |
|---|---|---|---|---|
| Deutsche Bahn AG, infrastructure procurement | 15 categories run centrally, from conventional ballasted track to the planning of control-command and signalling; a separate system for ETCS infrastructure installations | § 48 SektVO (Germany’s Sector Procurement Ordinance) | Each prequalification: 4 years; requalification applied for at least 2 years before the end | Register in SMaRT, DB’s supplier management system; a fee per application (track: €980 first application, €450 requalification, net); the ETCS procedure carries no charge |
| RFI (Rete Ferroviaria Italiana) | Works systems by trade, among them railway track, electric traction and energy installations, signalling, and civil works on lines in operation; qualification by category and value class | Article 168 of Legislative Decree 36/2023 | Each qualification: no time limit while the requirements are met; documents every three and every five years | Through RFI’s purchasing portal (Portale Acquisti) |
| Ferrovie Emilia Romagna, notice of | Railway track works; electric traction and energy installations; through RFI’s systems, used at its discretion or required as a condition | Directive 2014/25/EU (notice on a qualification system) | Systems used: indefinite | Qualification in the relevant RFI system |
| ProRail | Branches from engineering firms and track contractors to workplace protection and suppliers of rail infrastructure systems | Aanbestedingswet 2012 (the Dutch Public Procurement Act); scheme EP2019 | Each recognition: until withdrawn | Under EP2019 and its branch part, in Dutch unless ProRail decides otherwise |
| SNCF Réseau, notice of | Track; earthworks and structures; signalling; telecommunications; fixed electric traction installations | Directive 2014/25/EU (notice on a qualification system); requirements in SNCF framework GF 01106 and its specific qualification requirements (ESQ) | System: unlimited | Some certificates and documents filed on Provigis |
| Infrabel, through TUC RAIL, notice of | Civil engineering, track, catenary and cable works | Directive 2014/25/EU (notice on a qualification system) | System: 3 years, renewable twice; this notice is the first renewal | A qualification file, not needed again from firms qualified under the first publication |
| ÖBB-Infrastruktur AG, notice of | FRMCS MCx/5G systems for its telecommunications infrastructure | Directive 2014/25/EU (notice on a qualification system); direct invitations under §§ 228 and 256 BVergG 2018 (Austria’s Federal Procurement Act) | System: unlimited | Only on the ProVia platform |
| Network Rail | RISQS, run by RSSB, for safety-critical goods, works or services supplied directly | A qualification system under the Utilities Contracts Regulations 2016 (its page, as of ); a qualifying utilities dynamic market under the Procurement Act 2023 (RSSB, ) | A system under the 2016 Regulations expires at the end of at the latest | Register on the central digital platform and BravoNR, and on RISQS with audited status |
Source: the rules, pages and notices named, cited below; the legal basis is as each document names it, and the term is either each firm’s qualification or the system’s own.3, 4, 7, 8, 9, 10, 11, 12, 15, 16, 17, 18, 19, 21
Sources (23)
- 1
EUR-Lex: Directive 2014/25/EU on procurement by entities in the water, energy, transport and postal services sectors, consolidated text of · Tier 1 · official · Verified
Where in the document
Article 43; article 51(1); article 77(1) and 77(5); article 85(1) and 85(2). The consolidated text of has the same wording as the original 2014 text for these articles.
- 2
TED: Iarnród Éireann, qualification system for civil engineering works of €1m to €5m, lot 1, notice 280745-2026 · Tier 1 · official · Verified
Where in the document
Procurement project name and description, first and second sentences; legal basis and notice type. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).
- 3
TED: ÖBB-Infrastruktur AG, qualification system ProVia-ID 1033 for FRMCS MCx/5G systems, notice 472247-2026 · Tier 1 · official · Verified
Where in the document
Procurement project name; the notice’s note (a qualification system, not a tender; register; direct invitation without further notice; ProVia only); period code; legal basis and notice type. In German; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).
- 4
TED: Deutsche Bahn AG, qualification system for ETCS L1 LS and L2 infrastructure installations on the network of DB InfraGO AG, notice 818928-2025 · Tier 1 · official · Verified
Where in the document
Procurement project name and description; the notice’s note (continuation of 775234-2024; no promise of participation; call for competition; German); selection-criteria description (two stages; no charge); legal basis and notice type. In German; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending). For G2 (merged from G2's S-1050, away run D coordinator): Read through https://ted.europa.eu/en/notice/818928-2025/xml (eForms): notice type qu-sy; ProcurementProject name, description and note (continuation of 775234-2024; prequalification promises no participation in a competition); the lot’s note on the qualification requirements (approved international ETCS and/or prequalification by Deutsche Bahn AG; two-stage examination; list of qualified companies; free of charge); legal basis 32014L0025.
- 5
Procurement Act 2023, Part 3 (award of public contracts and procedures), legislation.gov.uk, latest revised text · Tier 1 · official · Verified
Where in the document
Section 34(1)–(5) (award by reference to a dynamic market; late applications); section 36(6)(a) and 36(7) (membership); section 38 (fees); section 40(1), (2), (5) and (6) (qualifying utilities dynamic market notices); section 45(2)–(5)(c) and 45(7) (frameworks; competition for call-offs; estimated value; fees); section 46(1), (2) and (7) (conditions of participation in a competitive selection process); section 46(8) and (9) (competitive selection process); section 49(1) and (2) (open frameworks); section 49(6) and (7) (single-supplier open frameworks: four years). In force from .
- 6
Cabinet Office: Guidance: Dynamic Markets (HTML), Procurement Act 2023 guidance, updated · Tier 1 · official · Verified
Where in the document
Paragraph 1 (a list of qualified suppliers eligible for future procurements); 4(c) (qualifying utilities dynamic market: tender notice only to members, not published); 7 (replaces dynamic purchasing systems and qualification systems); 10 (admittance is not the award of a public contract); 11 (late applications considered).
- 7
The Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 (SI 2024/716), regulation 8, legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Regulation 8, paragraphs (1) and (3) (the 2016 Regulations continue to apply where, before , the framework was concluded or a notice, including a notice on the existence of a qualification system, was submitted). The revised text read includes the amendment of to regulation 8(1).
- 8
The Utilities Contracts Regulations 2016 (SI 2016/274), regulation 1 (citation, commencement and extent), as made, legislation.gov.uk · Tier 1 · official · Verified
Where in the document
Regulation 1, paragraph (5): “These Regulations do not extend to Scotland.”
- 9
Network Rail: Becoming a supplier (web page) · Tier 1 · official · Verified
Where in the document
Section “How to register as a Network Rail supplier”: the first two steps (the central digital platform; BravoNR) and the three paragraphs on RICCL codes and RISQS (a ‘Qualification System’ under the 2016 regulations, direct selection; audited status; not mandated on Tier 1 suppliers). The page shows no date; read .
- 10
RSSB (RISQS): Network Rail, Network Rail High Speed and other contracting authorities confirm use of RISQS as a QUDM, news item of · Tier 2 · direct participant · Verified
Where in the document
First paragraph; the paragraph introducing the list of other contracting authorities; “What this means for suppliers”, first and second paragraphs. Network Rail’s own dynamic market notice for RISQS was searched for on Find a Tender on ; the service refused the automated search, and the notice was not found.
- 11
Deutsche Bahn AG, Beschaffung Infrastruktur: Verfahrensregeln zum Präqualifikationssystem, version 34, valid from · Tier 1 · official · Verified
Where in the document
Sections 1.1, 1.3 and 1.4 (categories, yearly notices, registration, fee); section 2, paragraphs (1), (2) and (14); section 3.1, paragraph (2); section 3.2.2, paragraphs (1) and (2); section 3.4, paragraphs (2) to (5) and (7); section 3.5.1, paragraph (1); section 3.5.2, paragraph (2); section 3.6, paragraphs (1), (2), (4) and (5); section 4.1, paragraph (1); section 5.2 (fee table); section 6.1 (conventional ballasted track), points B(1), B(4), B(9), C, E and G. In German; quoted in translation.
- 12
RFI (Rete Ferroviaria Italiana): Qualificazione operatori economici, Lavori (web page) · Tier 1 · official · Verified
Where in the document
Page section listing the active works qualification systems (“Per il settore LAVORI sono attivi i seguenti Sistemi di Qualificazione”), read . In Italian; quoted in translation.
- 13
RFI: Sistema di Qualificazione SQ004, Normativa, interventi all’armamento ferroviario, revision 2 (2020 edition) · Tier 1 · official · Verified
Where in the document
Articles 3.3.1 (point 1, first sentence; point 5, a and b), 3.4 (first sentence), 3.7, 4.1, 5.1 and 5.2. The address linked from RFI’s works page; the earlier address SQ004_Normativa.pdf serves the same text. In Italian; quoted in translation.
- 14
RFI: Regole generali per la partecipazione alle gare d’appalto lavori da sistema di qualificazione (marked “Rev. 16 Aprile 2024”) · Tier 1 · official · Verified
Where in the document
Opening sentence; first, second and fifth bullet points. In Italian; quoted in translation.
- 15
ProRail: Erkenningsregeling (web page), updated · Tier 1 · official · Verified
Where in the document
Lead paragraph; the date line; “Vooraf selecteren en beoordelen”, first three sentences; “In aanmerking voor erkenning?”, last two paragraphs; the list of branch documents. In Dutch; quoted in translation.
- 16
TED: SNCF Réseau SA, qualification system for companies in railway infrastructure works, notice 175019-2026 · Tier 1 · official · Verified
Where in the document
Procurement project name and description (the five domains); the note on submissions (first and third sentences); the note on use by other SNCF companies; period code; legal basis and notice type. In French; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).
- 17
TED: Infrabel, through TUC RAIL, qualification system TR 889007 for civil engineering, track, catenary and cable works, notice 292925-2026 · Tier 1 · official · Verified
Where in the document
Procurement project name and description; the note (first renewal; no new file for firms already qualified); duration and renewal description; legal basis and notice type. In French and Dutch; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).
- 18
RFI: Disciplinare dei Sistemi di Qualificazione con classi d’importo, revision 16, edition of · Tier 1 · official · Verified
Where in the document
Articles 1.1, 1.2, 2.1, 4.2 (first sentence), 10 (closing paragraph), 10.6 (first sentence), 11.1 (first sentence) and 14.4. In Italian; quoted in translation.
- 19
ProRail: Erkenningsregeling van ProRail EP2019, algemeen deel (ACD00018), in force from · Tier 1 · official · Verified
Where in the document
Colophon; preamble, second to fourth indents; articles 3.3, 3.4, 5.7, 6.3, 13.4 and 13.5 (first sentence). In Dutch; quoted in translation.
- 20
Deutsche Bahn AG: Verzeichnis der präqualifizierten Unternehmen Infrastruktur (directory of prequalified companies) · Tier 1 · official · Verified
Where in the document
Category “Oberbau, konventionell-Schotter”, page 1 of the category (“Seite 1 von 6”): header (status of ; “Als Ausschlusskriterium freigegeben”, notice 800698-2025 of ), legend and column heads. In German; quoted in translation.
- 21
TED: Ferrovie Emilia Romagna S.r.l., use of the qualification systems established by RFI, notice 583588-2026 · Tier 1 · official · Verified
Where in the document
Procedure description, points 1 and 2; the names of the two lots; period code; legal basis and notice type. In Italian; quoted in translation. Read as the notice’s XML from TED (the detail page answers plain requests with HTTP 202; browser check pending).
- 22
European Commission: Proposal for a Regulation on public contracts and concessions (Public Procurement Act), COM(2026) 590 final, 2026/0265 (COD) · Tier 1 · official · Verified
Where in the document
Cover page and title (date, reference, the three directives repealed); article 2(17) (“public buyer”, p. 37); article 49(1)–(3) and (5) (qualification list, p. 71); article 103(2)–(4) (framework agreements, including the public summary of result for each contract based on a framework agreement, p. 109); article 149, second paragraph (application two years after entry into force, p. 147). A proposal, not adopted.
- 23
European Parliament, Legislative Observatory: procedure file 2026/0265(COD), “Public Procurement Act”, the Commission’s proposal COM(2026) 590 · Tier 1 · official · Verified
Where in the document
Cited for the procedure’s stage (C-2100; earlier C-1320), and watched by hand each month for the procedure’s progress. Read on : key events table (row “Legislative proposal published”, , COM(2026)0590); stage “Preparatory phase in Parliament”; rapporteur “Pending final decision on the referral”.
ListingMinds uses primary procurement, regulatory and contracting sources wherever available. How we work
How to cite
ListingMinds, “Rail qualification systems: who can bid is settled before the tender”, . https://www.listingminds.com/transport/guides/rail-qualification-systems